Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther, Page 19 of 30  Not logged in ELOG logo
ID Date Authordown Location Severity Subject
  382   11 Sep 2017, 14:03 Gerd WellenreutherGeneralInformationTAS updated

Dear all,

I updated the tunnel access schedule to reflect the access to the XTDs tomorrow.

Cheers, Gerd

  383   11 Sep 2017, 14:04 Gerd WellenreutherGeneralInformationTAS updated

Dear all,

I updated the tunnel access schedule to reflect the access to the XTDs tomorrow.

Cheers, Gerd

  386   18 Sep 2017, 17:39 Gerd WellenreutherGeneralInformationTunnel access schedule updated

Dear all,

XTD9 will be accessible tomorrow until the afternoon, but access should be communicated to M. Dommach, H. Sinn and T. Tschentscher. Martin will organize a search team for the afternoon.

https://docs.xfel.eu/share/page/site/PSC/wiki-page?title=Tunnel_access_schedules

Cheers, Gerd

  388   22 Sep 2017, 16:06 Gerd WellenreutherGeneralInformationStatus and plans after SASE1 Status/SASE3 Readiness Meeting

General

  • First users have done experiments - despite the current problems it appears as if everybody was able to take some data for future publications.

Short Report from SASE1 Instruments

  • ​SPB (A. Mancuso): 
    • Beam was lost due to incident with electron beam hitting & damaging components downstream of the northern dump.
    • Currently only single bunch operation
    • Lots of work to be done in Oct. shutdown, Adrian will provide a list to Thomas Tschentscher
  • FXE (T. Tschentscher):
    • Problem with the Tangerine-laser affects PP-experiment ==> to be fixed on Tuesday
    • Consider to switch to oscillator only until then ==> lower repetition rate, lower OL pulse energy
    • Next experiments require Gotthard & LPD in parallel operation ==> merge Gotthard & LPD to same run control next week before user run.
    • Today, test with DAQ and Gotthard was successful, but Gotthard has never seen XFEL X-rays so far. ==> Test with beam could happen potentially Monday night (instead of user experiment)

Tunnels (M. Dommach, J. Grünert):

  • SASE1:
    • Few issues with XGM, have been or are being solved.
    • It was suggested to put the Hirex-grating into the beam while FXE is taking beam to measure / commission parasitically. But it appears next week neither Naresh nor Jan will be available.
  • SASE3:
    • ​Due to the electron beam incident the first vacuum sections have been vented, there is most probably a hole in the V0, but only Rad. Safety to access the tunnels right now. ZZ/Access by anyone else only after clearance through SRP - working there is probably only possible in Octorb
    • Beam did hit the beam pipe apparently just upstream of the transmissive imager. Imager and further (vacuum) electronics seems to have been damaged in the upstream part of XTD10.
    • Due to this incident, it should be reconsidered if dosimeters are required in XTD10, too. SRP did unfortunately not participate, and thus was not able to comment.

Laser

  • Working still on improving the laser
  • Issue regarding motors coming back to their position is most probably a firmware/options issue

Detectors

  • AGIPD:
    • According to Yolanta "operates better than expected"
  • LPD
    • Also operates better than expected
    • Configuration of LPD is getting messed up by people working in parallel / unclear status of the detectors Gotthard & LPD ==> There should be a responsible for the detector, who is present in the control room and can allow remote access to work with the detectors / run configuration. ==> These steps should be well-documented in the FXE-Logbook.
    • K. Wrona: Next week will be better with just one run controller.

Electronics (P. Gessler)

  • There is an issue with some motors & encoder @ SPB.
  • AE will finish the work on the last loops in SASE1.
  • WP79 needed & got support by AE.

ITDM (K. Wrona)

  • DAQ for the tunnels is setup. ==> XGM-run control for the tunnel is to be tried.
  • Slow data: It is an issue how and how fast to store slow data (lots of properties which do not change).

Software

  • FXE:
    • Still daily meetings, prepare LPD & Gotthard
    • Working on GreatEyes, too
  • SPB
    • Configure slow-data cameras
    • Laser project is running in CAS
  • SASE3:
    • C. Youngman is the CAS-responsible, should collect requirements to compile master equipment list for SASE3 ==> to be compared against MEL SASE1 to identify additional work required.
  • SASE1:
    • Loops & Karabo will be updated together.

October Shutdown:

  • SASE1
    • No major items here currently, focus is on SASE3 / XTD10.
  • SASE3
    • First priority is to get all items required for first lasing up & running ==> Vacuum system including anything up to the absorber.
    • CAS is starting to set up Karabo and all controls.
    • ITDM will also start to work, but does not require access to the tunnel.
    • C. Youngman to generate MEL from input from the groups ==> invites to a meeting if necessary.
    • Eplan for PES will not be available on time ==> has to be pumped in a provisional fashion.
  392   29 Sep 2017, 10:43 Gerd WellenreutherGeneralInformationStatus and plans after Readiness Meeting

SPB (A. Mancuso): 

 

  • Users are in good shape
  • Beam operation with ca. 600 microJ, but beam seems to be ring-shaped after M2?
  • Preparing for first pump&probe experiments in November.
  • Start of the focussing mirror controls should start after the user run

FXE ():

  • Was not present at the beginning of the meeting, so nothing was reported.

Tunnels (M. Dommach):

  • SASE1:
    • Nothing particular.
  • SASE3:
    • ​Preparing for the works in XTD10 during the Oct. shutdown are ongoing.
    • PES: Will just be connected to vacuum & pumped, not functional.

Laser (M. Lederer)

  • Sustained small damage during set-up
  • Not much time left until user run requires PP-laser
  • Issue regarding motors not coming back to their position reliably still persists / is not solved. ==> To be tackled by Gabriele (CAS) + Nerea / Nicola / Janna (AE)

Detectors (P. Lang)

  • Detectors are in operation
  • Works in Oct. shutdown mostly indepenent from other groups
  • LPD & Gotthard run together, but Gotthard has not yet detected X-rays?

Electronics (P. Gessler)

  • Preparing for Oct. shutdown
  • Train-builder should be tested in the Winter shutdown, because the contract only runs until March.

ITDM (K. Wrona)

  •  There are some issues with run-control, being investigated.

Software (S. Brockhauser):

  • Daily meetings with FXE & SPB.
  • C. Youngman is working on the Master Equipment List for SASE3. The basic assumption is to copy any configurations/parameters from SASE1 to SASE3.
  • Focussing now more on the SASE1-issues (e.g. Karabo-DOOCS-Interface ==> will mirror devices from Karabo into DOOCS.)

Priorities & Schedule (T. Tschentscher, G. Wellenreuther):

  • Performance of SASE1 has to be improved, in particular the performance of the accelerator. This has higher priority than continuing building up SASE3 or SASE2.
  • For example, the measurement of gain curves requires the MCP, consequently its completion has highest priority.
  • The control room also needs fast & direct access to more devices than just the XGM to properly tune lasing, consequently the Karabo-DOOCS interface has highest priority.
  • For the overall planning of the next ca. 5 weeks all groups are expected to report back to T. Tschentscher & PSPO until Wednesday next week. PSPO will produce a Gantt-chart of all activities. Template for the feedback will be sent around still today.
  • PSPO is tracking ALL major activities associated in all SASEs in the presentation shown. Missing items to be reported to G. Wellenreuther. Will be revisited on a ca. monthly timescale
  • Planning for the next shutdown in December should commence in early November (= after the upcoming shutdown), to allow for proper planning and preparations.
  • Despite the priority on SASE1, activities in SASE3 and SASE2 should progress. We still would like to attempt to do first lasing in SASE3 before the November user run!
  398   06 Oct 2017, 11:15 Gerd WellenreutherGeneralInformationStatus and plans after Readiness Meeting

SPB (B. Weinhausen): 

  • Users took good data
  • Problems occured with the DAQ / control system
  • Working on diamond @ beamstop
  • Preparation for several updates / activities regarding AGIPD

FXE (A. Galler):

  • User took good data, analysis is ongoing
  • Will rework cable routing/connections
  • Chiller was moved to the rackroom, redo the connections etc.

Tunnels (M. Dommach, H. Sinn, J. Gruenert)

  • SASE3:
    • ​1st section is not recovered yet, DESY Vacuum has to replace the last valve here, works have not started yet
    • 2nd section with K-Mono, which was vented, is now pumped again.
    • Diff. pumping in gas section has been tested, upcoming are interlock tests
    • Gas attenuator still needs a lot of cabling, cooling water and compressed air
    • Leak test starts
    • MCP has to be connected next week
    • Leak @ absorber: has to be reweld by Trinos, or a blind flange has to put right after the absorber ==> should not hinder the 1st lasing attempt.
    • Absorber was moved ==> has to be realigned by MEA
    • A. Koch is ready to commission several imagers as soon as the motion loop is up&running
    • Next Monday AE, WP74, Vacuum etc. will finalize which components will be implemented in the motion loop during the October shutdown
    • MCP, FEL-Imager: Crates are there, AE still has to understand and define the priorities of their work
    • Repair of MCP: Access to XTD required, WP74 to clarify with SRP.
    • No access to the tunnels with visitor cards! (Access to tunnels requires rebreather training, knowledge about procedures, warnings, dosimetry etc.)
    • Hirex was calibrated @ 9keV, is ready to measure the bandwidth, was determined to be 20eV FWHM

Laser (M. Lederer)

  • NOPA-Alignment progressing
  • Some setbacks due to shutdown activities by MKK, which affected the humidity stability ==> tables bend
  • Laser synchronization has to be implemented by WP18, is questionable, the responsible expert is going on vacation next Friday.
  • Motors seem to move reliably now
  • No process yet to let the users easily change the laser burst pattern via software. Currently, BKR is being informed about our needs, and they "drive" the laser through timing signals from BKR.
  • Laser group will operate in a shift pattern:
    • 8-16h morning shift
    • 15-23h late shift

Detectors (M. Kuster)

  • AGIPD:
    • Decided not to modify the vacuum
    • Working on internal calibration
    • Working on increase of the bias voltage to improve the performance
    • Electronics are being replaced partly
  • LPD:
    • Upgraded the chiller
    • A leak occured due to the increased pressure, since the chiller was put into the rack room ==> pressure reducer is used now
    • Will exchange faulty super-modules
    • Working on the internal calibration
  • Planning next beamtime & shift schedule as laser group has setup
  • There still exists a risk to collide AGIPD-modules, meeting with the AGIPD-consortium to agree on changes for the next detectors
  • Problem with additional frames which had to be taken during data acquisition: pattern upgrade / firmware upgrade required, will not come in October.

Electronics (P. Gessler)

  • Responsibles
    • SASE1: Bernard Baranasic
    • SASE3: Jan Tolkiehn
    • Instruments SASE1: Tobias Freyermuth
  • Lots of updates are required, could all be done in short succession ==> can the beamline be put in an insensitive state, to allow quick series of updates?
  • Documentation by WP74 + Vacuum is not consistent ==> AE will provide an Excel-sheet to be used, which should give a consistent picture of all terminals, connections etc.

ITDM (K. Wrona)

  • Both online & offline-filesystems have to be updated. Monday: Online-FS will be down, offline-FS will be worked on continuously, should not be down, but at reduced performance, since update will be server by server.
  • How should ITDM communicate this to the user? Suggestion: Setup an email-list for users to subscribe to, so those individuals who actually work on the data get the updates, and not every user.
  • Capacity of the offline FS has to be increased
  • DAQ-Upgrade: still running Karabo 2.1.12 on detectors, which requires lots of restarts. Will upgrade to .13 first.
  • Still there is no proper commissioning of the Gotthard. Testing would be appreciated to improve reliability ==> time required from Detector and Instrument

Software (S. Brockhauser):

  • Karabo 2.1.18 to be released today, but not immediately to be installed. To be deployed after PLC upgrades.
  • Karabo + DOOCS: A meeting took place with T. Wilksen (responsible for DOOCS). ==> interface for slow data / digits exists, but not for pipelined data / cameras / images
  • Highest priority of the DOOCS-Team are the SASE3 undulators, which is not in line with the XFEL priorities (improving the stability / reliability of the SASE1 operation)
  • C. Youngman to work on the master equipment list for SASE3
  • A. Galler: Is the current situation really bearable for the instruments, can we actually call this upcoming beamtime "user time"? ==> S.Brockhauser: Lots of problems have been solved, new will arise...
  • A. Galler: Will we be able to do a simple blade scan through a laser beam and get a plot?
    ==> S. Brockhauser: We are working on this. You can have plots showing motor positions, intensity, and then correlate this.
  • H. Sinn: Basically, we still to not have a working scan tool, which is a big drawback. This is one of the very basic functionality every user will expect!

Priorities & Schedule (G. Wellenreuther, H.Sinn):

  • Operation board should decide about updated schedule next week
  • Users & instruments request time to with beam to set up before user time!
  • OCD-contacts for TS were provided (again?)
  • In general, interface to OCD should be harmonized for all groups (e.g. always have a fixed cellphone number)
  • Activities for the shutdown have been gathered by PSPO, and are being provided to the support groups for crosschecking.
  • No major collisions/ bottlenecks appeared apart from the high workload / demand for support by AE and CAS.
  • AE and CAS will crosscheck and provide feedback to PSPO regarding resources & priorities if required.
  404   16 Oct 2017, 17:11 Gerd WellenreutherGeneralInformationTunnel access schedule updated

Dear all,

I updated the schedule for the tunnel access in the upcoming weeks based on the discussions in the PSO- and the Operation Board-meetings:

https://docs.xfel.eu/share/page/site/PSC/wiki-page?title=Tunnel_access_schedules

Cheers, Gerd

  415   06 Nov 2017, 13:58 Gerd WellenreutherGeneralInformationTunnel access schedule updated

Dear all,

I updated the TAS to include the upcoming user runs up to and including the winter shutdown. As you can see, there will only be access to the XTDs in cases of urgency. In these cases, please contact Martin Dommach, Harald Sinn or Thomas Tschentscher.

https://docs.xfel.eu/share/page/site/PSC/wiki-page?title=Tunnel_access_schedules&listViewLinkBack=true

Cheers, Gerd

  420   14 Nov 2017, 11:05 Gerd WellenreutherGeneralInformationTunnel access schedule updated

Dear all,

I received updates from DESY (M. Hüning) about how the access to the southern tunnels is being restricted in the next months, due to interlock tests etc., and included it in the TAS. Please check, if you have work to be done in these tunnels:

https://docs.xfel.eu/share/page/site/PSC/wiki-page?title=Tunnel_access_schedules

Cheers, Gerd

  436   18 Dec 2017, 10:48 Gerd WellenreutherGeneralInformationStatus and plans after Readiness Meeting

PSPO:

  • M. Areste presented a report about the progress so far achieved in the shutdown (see Indico for details).
  • Most tasks are ongoing, on schedule.
  • Few still have to be scheduled, mostly because support groups wait for feedback.
  • C. Youngman does detailed coordination of SASE3tasks.Will organize meeting on Tuesday 9:30 for SASE3 tunnel only
  • We will review the progress again in Mid-January!

 

SPB (M. Sikorski):

  • AGIPD was tested.
  • Roll back to crystallography configuration is ongoing.

 

FXE: No one attended.

 

Vacuum (M. Dommach): 

  • 1st mirror M1 in SASE3 installed, chamber closed, pumped down & leak tested
  • Preparations for 2nd mirror in SASE3 installation ongoing, to be installed next week.
  • MCP taken out of SASE3, put in parking position and pumped down again.
  • Grating chamber from FXE was installed by JJ X-ray, is to be pumped in CW 51.
  • SASE2 XS2 beam pipe behind shutter and lead wall installed, ready for TÜV inspection next week.

 

Diagnostics (A. Koch):

  • XGM in XTD1 is almost cabled, more cabling was done in XTD10.
  • Gas supply system in XTD1+6 was worked on.
  • Photonics Science camera was tested.
  • Trouble with the motion loop in XTD2 and XTD10, reported to AE.

 

AE (P. Gessler ):

  • MCP motion and k-monochromator were tested.
  • Motion loop was split in SASE1 tunnel.
  • Many tests, lots of work in progress, need to act quick as time is short.
  • T. Wilksen (DESY) is going to update the timing hardware è devices would have to switch to local timing, and switch back later to be operable.

 

Laser (M. Lederer):

  • Further commissioning of the PP-laser was started.
  • Upgraded Karabo and PLC firmwares. Works are on schedule.
  • Measurements on the dependence of humidity are ongoing.
  • DESY is working on the timing system, laser synchronization will be down until the 21.1.18.
  • PP-laser pattern selection with machine timing:DESY is now pushing for the originally planned implementation. DESY will have to do some software development in this context.

 

Detectors (J. )

  • Tested the AGIPD @ SPB, but 1 board was not working. Detector consortium could not provide a replacement board, so only half of the detector was tested before SPB/SFX had to close the detector vessel again.
  • LPD was tested with train builder, but only tests using 2 memory cells could be conducted (2 images per train), so train builder was not tested with all memory cells.
  • More tests with full load (i.e up to 510 images per train) still have to be performed.
  • Test with DSSC will take place in HERA South in CW 51.

 

ITDM (K. Wrona)

  • Monday til Wednesday there will be no DAQ due to extension of the Infini-band bandwidth, upgrades, firmware updates, recabling etc.
  • DAQ up again on Thursday

 

Software (S. Brockhauser)

  • CAS-People are currently working only in SASE3. In the future, they can either work on SASE3 or SASE2, but not both!
  • Slides with Project-plan provided by Hugo Santos (see Indico)
  • Release of Karabo 2.2.0 on the 18.12. (in the meantime shifted to the 20.12.)
  • Testing by ITDM and consecutive deployment in tunnels and at the instruments takes until 22nd of January
  • Karabo 2.2.1 to be expected mid of January
  • Further decisions will be taken mid of January
  439   09 Jan 2018, 10:14 Gerd WellenreutherGeneralInformationAccess to XTDs

Dear all,

according to H. Sinn the closing of the XTDs 2, 4 and 10 will be delayed until the 30th of January.

Cheers, Gerd

  448   12 Jan 2018, 11:10 Gerd WellenreutherGeneralInformationStatus and plans after Readiness Meeting
SPB:
- AGIPD was tested with old mc board to verify that it was working fine
after the in-vacuum intervention in Dec 2017. The detector is working
and also the vacuum is ok.
- The exchange of the mc and mfpga boards is ongoing and will continue
next week (according to planning)

FXE:
- Diffraction Grating is being installed by JJ-XRay. End to end tests to 
follow.
- Karabo being updated to the 2.2.1. version.

Vacuum:
SASE1:
- CRL XTD2 closed yesterday, seems to be leak tight
- PLC VAC loop update done yesterday
SASE3:
- soft mono chamber still open, XRO is installing mirrors
- MCP connected to beamline again, pumped down yesterday
- VAC - GATT loop separation ongoing, loop restart next Monday

XPD:
SASE1:
- rebooted vacuum loop yesterday, XGM vacuum gymnastics
SASE3:
- MCP technical comm.:  motor tests, some rewiring & enabling control of HV
- Imagers: all imagers in motion Loop 1 and 2 - some small mistakes
- Photonic Science camera issue (16bit) is solved
SASE2:
- MCP transported into tunnel XTD6
- now ALL vacuum chambers of XPD are in the TUNNELS (few more for the hall)

Laser:
- the timing specification has been extended, 6 laser patterns available
for SASE1/2/3 and the laser lab. 4 others are reserver for SASE4/5. In
the next months desy will upgrade doocs servers and firmware.
- SASE1: pp-laser upgrade and remaining commissioning progress as per
plan (finish end of March). No commitments to experiments till then.
- SASE3 and 2: Plenums are being installed. Plans for laser table
installations: currently still for April.

Detectors:
- did not attend

AE:
SASE3
- Gas attenuator is in separate loop and loop running
- MOV loop 1 updated (incl. MCP related change)
- Plan to update EPS loop today
- VAC loop update planned for Monday
- MicroTCA crate for PES replaced - Timing back for this crate and also
for XGM and KMONO
General 
- Timing changes - Machine switched to 1Hz and they reset the train IDs to avoid soon issues with the machine DAQ system

ITDM:
 - LPD recabled with Infiniband connection. Test ongoing.
 - Meeting next week to decide whether to use or not the train builder for 
AGIPD and LPD detectors
 - in 3 racks in XTD10 some network connection added last year do not work 
properly. The responsible company is comeing back next week to check the 
cabling. Interventions have to be planned accordingly since the Beckhoff 
loops are running!

CAS:
- Karabo 2.2.1 has been created and its roll out for hw tests on real
field has been started
- We have started at FXE. Until now only a single problem has been found
with LPD FEM.
- Laser Laboratory has also been updated without any problem detected
until now
- Next Monday Lasers group's PPL installation will be upgraded
- Next week, SPB will be upgraded also step-by-step
- Finally, SASE1 will also be upgraded.

  455   22 Jan 2018, 10:36 Gerd WellenreutherGeneralInformationStatus and plans after Readiness Meeting

SPB/SFX:

  • 2nd AGIPD intervention will be finished today.
  • SE worked on a reliable procedure for nozzle exchange and trained the instrument scientists
  • SmarAct motors are in error, Mahadi / AE is informed. These motors are needed for user operation / commissioning.
  • loop 5 update still outstanding
  • Karabo update for loop 1-4 was done, seems to be ok. Full update is planned for beginning of next week.

FXE:

  • JJ X-rays finalized installation of the last components at FXE:
    • Diamond grating (in XTD9)
    • Spectrum analyzers
    • Timing tool
    • repositioning of the sample manipulator and working on better cabling
    • minor work on cables of FXE CRL to allow full movement along the beam direction
    • Johann spectrometer
  • FXE got the information from CAS that the Karabo update was successful and it’s ready for testing
  • FXE decided not not pursue the further commissioning of the new equipment due to the emergency power off tests
  • FXE is working on a more universal sample environment allowing faster and more reliable changes from solid to liquid experiments.

Vacuum:

SASE1:

  • vacuum system closed,
  • PLC loop update done,
  • ready for restart

SASE2:

  • XTD1 all devices in the tunnel and aligned

SASE3:

  • Soft Mono chamber closed yesterday, pumpdown, leaktest later today
  • GasAttenuator comissioning ongoing
  • Karabo scene developement

XPD:

  • SASE3 MCP detector technical commissioning:
    • HV tested OK (MPOD operational), today ADC/signal test
    • motors: rewiring done --> correct directions and limit switches
    • motors were intermediately ok, but are not stable (now there are again issues)
    • several PLC / karabo issues were sorted out, ok
  • SASE3 XGM:
    • test with Kr gas supply yesterday/today
    • test with gas plus HV
  • SASE3 PES:
    • ordered grounding works (cabling) to be done similar to what was done for the XGM
  • SASE2 XGM:
    • vacuum incident: vacuum operation of the XGM in XTD6 was unauthorized interrupted for some time, The rack had been powered down without prior information to XPD.
    • Reminder to all that rack near the XGMs shall be powered down only after informing and coordinating with XPD.

Laser:

 

  • SASE1 PP-laser commissioning and upgrade is continuing according to our plan.
  • Karabo upgrade to 2.2.1 was rather uneventful and successful.
  • Hutch readiness milestones for laser hutches in SASE 3 and 2 seem to consolidate:  15. March. If this continues to hold, we will start our Phase II installation of PP-lasers in E.04 and A.04 with laser tables at the start of April. Laser tables for the ILHs will be installed at the same time.

Detectors: Did not attend.

Advanced Electronics:

  • Replacement of the microTCA for the PES was done
  • microTCA update of the timing system was done
  • local test of the CRL can be done after the cables and the hardware have been fixed by the Vacuum group
  • All loops of FXE updated (firmware etc.)

ITDM:

  • Network ports for SASE2 in the racks have been fixed
  • DAQ in SASE1 needs fixing of hardware, foreseen for CW 4
  • Test of DAQ with new Karabo release is on its way, should be done by Wednesday 24.1.

CAS:

 

  • Karabo 2.2.1 has been deployed on FXE, LAS-LAB, LAS-PPL, and 3 SPB loops without any real problems
  • migration continues next week on SPB
  • BKR will be equiped with a 3rd Karabo Control PCs (we work with Tim already on it)

 

  460   29 Jan 2018, 09:29 Gerd WellenreutherGeneralInformationStatus and plans after SASE1 Status/SASE3 Readiness Meeting 26.1.

SPB/SFX:

  • Preparation for the mirror installation were ongoing as planned.
  • The Karabo and server update went smooth, but scenes were broken a bit more then anticipated so we are still testing on that part.
  • ITDM was working on DAQ update and Jola checked out the detector with the new Karabo successfully.
FXE:
  • did not attend / did not send any report

Vacuum:

  • SASE1:

    • Vacuum system ready for restart

  • SASE3:

    • loops were updated

    • final interlock test ongoing

    • GATT tests with Karabo

      • Vacuum possible

      • manual attenuation of the beam possible, no PID control

      • Controls of Ebara pump needs commissioning.

  • SASE2:

    • XTD1: under vacuum, leak test done, all pumps running

Diagnostics:
  • final checklist tour today 11h (because XTD10 closes tuesday), remove material
  • MCP: installed webcam, some trigger issue with MCP-CAM-BEAMVIEW
    • manipulator motors unstable
  • KMONO: found some wrong motion directions, urgent work ongoing today to correct this, AE support needed
  • PES: still no eplan available (laid some vacuum cables but of course unconnected)
    • consequence: further progress on PES Beckhoff system only in April
    • positive news: non-Beckhoff controls (HV, detector signals) operational ! 
  • IMAGERS: The imagers in motion loop 1 are operational for first lasing.
  • Some minor rework is planned until tunnel closure: default parameters, EPS, trigger in some cases

Laser:

  • SASE1 PP-laser commissioning: progress is according to plan.
  • SASE 2 and 3 laser safety and access control installations are in time for start of laser table installations in all laser hutches at beginning of April.

Detectors:

  • LPD is waiting for DAQ-test with new Karabo
  • DAQ-test for AGIPD is ongoing and okay so far
  • Some issues were found, but they are not considered critical for the operation

AdvancedElectronics:

  • Machine trigger is back to 10Hz, should again stay at 10Hz "forever", let's see...
  • PLCs have been updated in SASE3 tunnels, and many tests are ongoing, with little time left
  • Gas attenuator has an issue, AE is working on it, but it should not be a showstopper
  • XTD2: Some issues with the CRLs, but first local test has to be done, then remote-control test can be done using Karabo
  • MC2-based motors for synchronized movement of the mirrors are being done. Next week a test with the real nano-KB-system with fake mirrors will be done
  • Jan found some issues in the SASE3 kMono, and is working on them

ITDM:

  • Testing DAQ with new Karabo release, so far so good...
  • DAQ for LPD is being deployed
  • By the end of CW 5 the DAQ for SASE3 tunnels will be deployed
  • Meeting with the laser group to check requirements for data acquisition
  • Broken Linecard should have been replaced on the 26.1.
  • Paths to Online- & Offline-data folders have been given the same pathname
  • Update/switch for the gateway to the control network will happen in CW 5

CAS:

  • This week we have been prioritizing: SASE1, SASE3 & SPB (Karabo 2.2.1) Deployment.
  • We also have been working internally to speedUp the Karabo 2.2.2 tests and releases. This version will have, mainly, GUI improvements.
  • We also have been discussing XGM requirements and tests. We will perform more XGM-TraindID tests, but the final statement can be done only after tests again real beam.
  • FXE provided a "next steps list": Digitizer, OGT1_BIU, beam-position feedback
  • Sergey and Hamed are working and prioritizing Digitizer implementation

 

  461   29 Jan 2018, 10:02 Gerd WellenreutherGeneralInformationLink to "Access Request" gathering for tunnels after the shutdown

Dear all,

please enter your access requests to the tunnels into the list provided by Winni Decking & Co.:

https://ttfinfo.desy.de/elog/XMLlist?file=/XFELelog/data/doc/Access-Requests&xsl=/elogbook/xsl/elog.xsl&picture=true

Can be also found through the usual XFEL-Logbook, and then clicking on "Access Request" on the left hand side.

Cheers, Gerd

  479   23 Feb 2018, 15:54 Gerd WellenreutherGeneralInformationStatus and plans after Readiness Meeting 23.02.

Photon Run Coordinator (L. Samoylova):

  • SASE1 tuning is ongoing (350 microJ)
  • SASE3 3000microJ
  • SASE1 interlocks enabled, SASE3 only vacuum interlock enabled
  • Soft monochromator is being commissioned
  • K-mono studies were carried out
  • HiRex was being commissioned
  • SASE1 and SASE3 DAQ was used
  • Gain curves should now be possible

 

SPB/SFX (M. Messerschmidt):

  • Recorded data with detector integrated in Karabo
  • problems with coupled motions persist, ran into & were not able to get out of end switches using Karabo
  • leak at mirror tank still has to be localized

 

FXE (P. Zalden / A. Galler):

  • Will be ready for beam by the end of the week
  • chamber was pumped, crystals mounted
  • I0 monitor was tested and commissioned
  • only have permission for <=2 bunches
  • scantool: Train IDs are not captured
  • DAQ-tests look good for LPD

PP-Laser (M. Lederer):

  • Final commissioning of the laser is ongoing
  • integration of the laser into DAQ during the April shutdown

 

Vacuuum (M. Dommach):

SASE1

  • nothing to report; Vacuum system ready of beam operation

SASE3:

  • XTD10 was open last Tuesday
  • Together with Diagnostic group Exchange of Turbo pump on XGM
  • Gas Attenuator commissioning ongoing

SASE2:

  • Working on cabling of XTD1 components and vacuum installation in XTD6
  • Installation of cleantent at HED-SDU ongoing.

 

XPD (J. Grünert):

XGM SASE3 

  • tuesday XPD made XTD10 access to repair SASE3 XGM vacuum
  • one turbo pump failed Saturday noon, decided to repair during access tuesday, exchanged pump
  • tuesday detected another vacuum trip in the differential pumping around the XGM
  • wednesday afternoon VAC made ZZ-access to „repair“ what tripped the vacuum interlock
  • wednesday to thursday night: checking proper and stable SASE3 vacuum operation - is ok
  • XGM is back in operation since thursday morning 8am

XGM status overall:

  • XTD2 and XTD10 XGMs in operation
  • When will the XGM in XTD9 be needed? ==> Harald and Liuba believe that beam might be sent to XTD9 this weekend, therefore they request to start XTD9 operation today afternoon

Imagers 

  • SQS Exit slit imager has been set to beam position and can be used for some basic commissioning (limited functionality)

thursday work with beam:

  • SASE1 KMONO studies: two cells studies, height adjustment of single cells using DAQ (until it crashed at noon), data analysis today
  • HIREX commissioning
  • SASE1 beam conditions recorded with DAQ

Correlation of beam intensity monitored by XGM and imagers

  • Required e.g. for the current Gas Attenuator Transmission Calibration
  • need to prepare a simple table of calibration values for all imagers which are used as supplementary intensity monitors
  • will discuss offline among photon run coordinators

SASE2

  • need to rearrange space in one rack to be able to put our last crate into tunnel XTD1: Wolfgang will contact Ulf and VAC
  • Request to CAS: 
  • DOOCS devices shall be created for SASE3 (as in SASE1) for undulator and phase shifter and electron beam energy

Advanced Electronics (P. Gessler):

  • SASE3: No train IDs are being delivered in loop 2. Repair could potentially / in the worst case affect all electronics. ==> Should be fixed right now to get it done.

 

ITDM (K. Wrona):

  • Configuration / Testing of DAQ continues

Detectors (J. Sztuk-Dambietz, P. Lang):

  • AGIDP ready for 100/64 bunch operation
  • there will be a two-day training for AGIPD-operators
  • LPD was tested with new Karabo / DAQ
  • LPD has hardware problem regarding power line for one module, to be fixed

CAS (S. Brockhauser):

  • The issue reported in the beginning of the week regarding the TrainIDs was identified. We have an integer overflow problem when connection is lost with the timeserver. That happens sporadically, and we are working to fix it since yesterday.
  • We released Karabo Hotfix 2.2.2.2 to fix an issue on the RunConfiguratorGroup at SA1 (ITDM already checked and it is working)
  • We have improved the communication protocol with AE on handling loops/PLC updates and related (re)establishment of the Karabo services.
  • AGIPD library is extended to supply information if detector is in stop or acquire state. The next step will add the "acquisition time" to enable scantool integration
  • The old digitizer is running and integrated with DAQ. Also, we will add the "acquisition time" to enable scantool integration
  • We started to call the Sprint Meetings (for the moment we focus on updating the priorities of FXE and SPB topics)
  • A list of 'potential' SA3 technical coordingation activities was sent to the 'Photon run coordinators' and PSPO listing what technical coordination tasks can be done parasitically during access period.
  • The SA2 technical coordination planning has started initially with the front line groups: ITDM, AE, VAC, then Beam transport.
    • ITDM have nearly finished the server installation (same as SA3), AE have responded with loop and MTCA plans
    • VAC and Beam Transport have so far not confirmed their meetings for this task

AoB:

E. Boyd: A test @ FXE with Cu-Target and 300 bunches is required. This will affect the areas / hutches around FXE

A. Mancuso: Will try to work around this, but in general a message one week beforehand would be required / appreciated.

  492   25 Mar 2018, 10:57 Gerd WellenreutherXHEXPProblemFXE emergency power-off has been triggered

Dear all,
apparently the Emergency Power-Off at FXE was triggered at around 10:00 - 10:30 (my estimate). As far as I know power has been switched on again. BKR / PRC have been informed. More information will be provided by TS / Torsten Schön soon.

Edit: T. Schoen is on site and can be contacted under 0160 977 287 97

Regard, Gerd

  497   04 Apr 2018, 13:43 Gerd WellenreutherGeneralInformationStatus reports after dispatch meeting 13:00 4.4.

SPB/SFX:

  • Mirror installation next week

FXE:

  • Replaced broken diamond-window

SCS:

  • Installation of alignment laser
  • Mirror tank installation next week

SQS:

  • Not present / no issues.

SASE tunnels:

  • C. Youngman is coordinating the works in the SASE1, 2 and 3 tunnels, daily meetings are at 9:30 every morning.
  • Works have been scheduled and planned, most work to happen in SASE3 and SASE2.
  • Staff should be aware that works e.g. regarding the vacuum loops have been scheduled and are ongoing, in doubt contact C. Youngman, N. Jardon or V. Bondar

CAS:

  • Release test with Karabo 2.2.3 are concluding probably today, including test with PLC firmwares 1.26 and 1.27.
  • This would lead to a release for ITDM & Detectors by this evening. A timeslot is required to test the new Karabo with ITDM / DAQ.
  • Deployment at the beamline could potentially be in two weeks, if the test with ITDM and Detectors will conclude fine.

XPD:

  • Email to xfel-op-allhands was received, indicating that there could have been a shortage of cooling water for the magnets and racks supplied from XS4 and also XS2 (should be SASE2-branch only). If you have electronic racks in this area, check the temperature, email will be forwarded to readiness.

Detectors:

  • A single supermodule of the LPD-detector is flickering, is being investigated.

ITDM:

  • A rise of the temperature in the balcony room from 27° to 39° was observed in the morning from ca. 6:00 until 6:30.
  • This lead to damage at two power supplies.
  • There was no indication by MKK or TS about any kind of shortage or shutdown of the cooling water supply.
  514   18 Apr 2018, 15:06 Gerd WellenreutherGeneralInformationTunnel closing after shutdown

Dear all,

below please find the hottest and most up-to-date times for the closing of the tunnels after the shutdown:

XTD1: 23.04.
XTD2: 23.04.
XTD6: not before 02.07. 
XTD9: 27.04. after lunch
XTD10: 24.04. after lunch

Cheers, Gerd

  557   03 Sep 2018, 09:49 Gerd WellenreutherGeneralInformationStatus report after dispatch meeting 09.30

SPB / SFX:

  • Experiments are ongoing, users collected data on Sat. and Sun.
  • There have been issues with the detector/DAQ due to operator error
  • There have been issues with the sample delivery
  • There was an issue with the X-ray / Laser interlock systems on Saturday, which was fixed the same day.
  • Beam time was partially lost due to these issues...

FXE, SCS, SQS, MID, HED:

  • Did not attend
  • Support points pointed out it will be much more difficult if the instruments do not attend this meeting to provide support in-time
  • PSPO announced the Dispatch meeting will be discontinued if the instruments will not attend (it is not considered useful with just one instrument attending on a regular basis)

Detectors:

  • Server for calibration data died, ITDM and DESY are working to revive it, S. Hauf will bring it up again.

CAS:

  • CY will have the usual meeting regarding SASE2

AE:

  • PBLMs in SASE3 being integrated.
  • SmarAct stages for SQS are being brought up
  • Vacuum group + AE working on SASE3 interlock