ID Date Authordown Location Severity Subject Text Attachments
  294   19 Jun 2017, 10:17 Monica ArestéGeneralInformationStatus and plans after SASE1 Readiness MeetingXTDs:


  
  352   02 Aug 2017, 10:17 Monica ArestéGeneralInformationStatus after 9:30 dispatch MeetingGeneral



This Thursday the
radiation test in D.05 (FXE) will be performed
  
  356   07 Aug 2017, 12:45 Monica ArestéGeneralInformationStatus after 9:30 disptach meetingGeneral



The Radiation measurement
test will be postponed until the beam reach
  
  372   30 Aug 2017, 09:53 Monica ArestéGeneralInformationStatus and plans after SASE1/3 Readiness Meeting
 

 
 

 
  Normal
  
  390   25 Sep 2017, 12:58 Monica ArestéGeneralInformationStatus and plans after SASE1/SASE3 Readiness meetingGeneral


Beam was lost due to incident
with electron beam hitting & damaging
  
  391   27 Sep 2017, 10:11 Monica ArestéGeneralInformationStatus and plans after SASE1/SASE3 Readiness meetingGeneral


T. Tschentscher inform
about Management Board priorities for the
  
  393   29 Sep 2017, 11:03 Monica ArestéGeneralInformationSASE1/SASE3 Readiness meeting on Monday cancelled The SASE1/SASE3 Readiness meeting next
Monday is cancelled we will meet again on
Wednesday the 3rd of October.
  
  394   29 Sep 2017, 11:09 Monica ArestéGeneralInformationSASE1/SASE3 Readiness meeting on Monday cancelled Correction: We will meet again on Wednesday
the 4th of October.

  
  397   04 Oct 2017, 12:10 Monica ArestéGeneralInformationStatus and plans after Readiness MeetingGeneral:

Reminder to all the groups to provide
the shutdown task list today afternoon to
 Shut_down_task_list.xlsx 
  437   08 Jan 2018, 09:50 Monica ArestéGeneralInformationReminder Readiness meeting today at 13:00Dear all,

This is a reminder to inform you
that Readiness meeting will resume today
  
  438   08 Jan 2018, 13:47 Monica ArestéGeneralInformationStatus and plans after Readiness MeetingPSPO: 

- G. Wellenreuther
inform that DESY is commissioning a new gun
  
  441   10 Jan 2018, 13:22 Monica ArestéGeneralInformationStatus and plans after Readiness meetingPSPO:

- G.Wellenreuther inform that MKK
is planning to test the Umschaltautomatik,
  
  480   26 Feb 2018, 12:09 Monica ArestéGeneralInformationStatus report after dispatch meeting 26.02SPB:


Ion pumps running in the
Mirror chamber.
Starting test
  
  Draft   25 Sep 2017, 10:25 Monica ArestéGeneralInformationStatus and plans after SASE1/SASE3 Readiness MeetingGeneral

To stablish proper conditions for
the beam as it was before. On Wednesday to
  
  51   24 Feb 2017, 15:14 Martin DommachXTD9Informationwork on FXE distribution mirror chamberDear all,
on Monday, 27th in the morning we
will start with preparation work for the
  
  52   24 Feb 2017, 15:15 Martin DommachXTD9Informationwork on FXE distribution mirror chamberDear all,
on Monday, 27th in the morning we
will start with preparation work for the
  
  334   14 Jul 2017, 12:44 Martin DommachXTD9ProblemFast Valves in XTD9Dear all,

the fast valves in XTD9 were causing
some trouble. From time to time they collect
  
  346   26 Jul 2017, 18:04 Martin DommachXTD9InformationFast valves in XTD9Dear all,

the problem with the fast valves
  
  440   09 Jan 2018, 10:32 Martin DommachGeneralProblemShutdown of compressed air distribution in XTDs todayDear all,

we got the information from MKK,
that they have to fix a leak in the main
  
  462   29 Jan 2018, 10:32 Martin DommachXTD10Informationclosing of XTD10 shifted to WednesdayDear all,

the closing of the XTD10 tunnel
is shifted to Wednesday (January 31st.) at
  