  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther, Page 12 of 29  Not logged in ELOG logo
Entry   Office network in XTD10, posted by Krzysztof Wrona on 17 Aug 2017, 07:59 
Dear All,

In XTD10 there are now office network ports available in each rack. These can be used to connect your regular laptops with a network cable without
special configuration and registration of your laptop.
Entry   Status and plans after SASE1/3 Readiness Meeting, posted by Tobias Haas on 11 Aug 2017, 10:07 
General


The focus of activities next week for the AE and vacuum groups is on getting as much done in XTD10 as possible. There is a conflict with
the aim to bring AGIPD to SPB and start commissioning. A lot of preparatory work was done for the latter this week already. Nevertheless this conflict
Entry   Status and Plans after 09:30 meeting, posted by Tobias Haas on 09 Aug 2017, 10:23 
General



Main focus for Vacuum Group and AE next week will be to get as much done in XTD10/SASE3 as possible. Conflicts with activities
in SASE1 need to be carefully monitored
Entry   KARABO 2.1.13, posted by wajid ehsan on 08 Aug 2017, 15:25 
The system is up and running.

Regards,

Wajid 
Entry   KARABO 2.1.13, posted by wajid ehsan on 08 Aug 2017, 13:10 
As previously announced we will deploy KARABO 2.1.13 in tunnel under topic SA1. The system will go down in 10 mins. I will announce it
again as soon the system is up again.

Regards,
Entry   Radiaiton Measurements Complete for SASE 1, posted by Eric Boyd on 07 Aug 2017, 18:30 
Radiaiton Measurements are complete for SASE 1 Normal access is restored.

 
Entry   Status after 9:30 disptach meeting, posted by Monica Aresté on 07 Aug 2017, 12:45 
General



The Radiation measurement test will be postponed until the beam reach the 30 bunches.



 
SPB
Entry   Time Schedule change in Radiation Measurements for Monday, posted by Eric Boyd on 04 Aug 2017, 15:24 
Dear All,

We have just changed the time that the Radiation Protection Measurements will take place on Monday. This will now begin at 15:00. The time has
been pushed back so that the DESY Radiation Protection group will be able to also be there.
Entry   Radiation Measurements of FXE Monday 07.08, posted by Eric Boyd on 04 Aug 2017, 13:41 Restricted_areas_for_FXE_EXP_measurments.pptx
The control room thinks that they will be able to very easily provide us the desired parameters for commissioning  the FXE EXP Hutch this coming
Monday. If that is the case we will be restricting access in SASE 1 in accordance to the attached presentation from 8:00 am until completion of the radiation
measurements. A SASE 1 log book entry will be made when restrictions go into effect and are lifted.
Entry   No Radiation Measurements in SASE 1 This week, posted by Eric Boyd on 03 Aug 2017, 10:52 
Do to repairs that need to be made with the cold compressor. We will be unable to perform Radiation Hutch Commissioning for SASE 1 this week. We will
attempt to reschedule the Measurments for Thursday or Friday (10.08 or 11.08) of next week, depending on if it can be coordinated with all involved parties.

There is no restricted access to SASE 1 until then.
Entry   Status after 9:30 dispatch Meeting, posted by Monica Aresté on 02 Aug 2017, 10:17 
General



This Thursday the radiation test in D.05 (FXE) will be performed (from approximately 0900 to 1500), access to all areas adjacent
to the hutch is only allowed by those that are assisting with the measurements.
Entry   Status after 9.30 dispatch Meeting, posted by Adriano Violante on 31 Jul 2017, 11:58 
General



SRP was not able to measure any radiation even inside D.09 and D.02. This Thursday the radiation test in D.05 (FXE) will be performed. 


Tomorrow XTD9 open 7:00 ==>14:00
Entry   Tunnel access schedule updated, posted by Gerd Wellenreuther on 30 Jul 2017, 23:04 
Dear all,

on Tuesday, XTD9 will be accessible from 7:00 - 14:00, due to requests by Naresh and Konrad. I updated the TAS:

https://docs.xfel.eu/share/page/site/PSC/wiki-page?title=Tunnel_access_schedules
Entry   Status and plans after SASE 1/3 Readiness Meeting, posted by Frederike Wittmaack on 28 Jul 2017, 11:50 
General



The radiation test in SASE1 could not take place yesterday since the machine was not able to deliver proper light intensity with
30 bunches. Another tentative is happening now.
Entry   No Restricted Areas for Radiation Commissioning, posted by Eric Boyd on 28 Jul 2017, 11:10 
Desired parameters where reached for radiation measurments of the SPB OPT and SPB EXP hutches. Radiaiton could not be detected inside the hutch with
the beam shutters open and beam verified hitting the target, therefore it was not deemed necessary to take radiation measurments outside the hutches. As
a result there are no additional access restrictions in SASE 1.
Entry   Restricted areas Durring Radiation Measurements of SASE 1, Friday 28.07, posted by Eric Boyd on 27 Jul 2017, 15:42 Restricted_areas_for_measurments.pptx
No radiation measurements have taken place today (27.07) due to insufficent energy of the machine. We think we can achive the desired energy by tomorrow
morning at which time the SRP group will attemtp to commission both the SPB OPT and SPB EXP hutch. The attached presentation shows the new expected time
schedule.
Entry   Fast valves in XTD9, posted by Martin Dommach on 26 Jul 2017, 18:04 
Dear all,

the problem with the fast valves XTD9 tripping randomly is still not fully understood but we exchanged the controllers for both valves and they
now seem to be stable. The valves are set back to active mode again with 1*10^-6 mbar trigger level while vacuum pressure at the sensors is around 1*10^-8
Entry   SPB - Loop 5 is back online, posted by Bernard Baranasic on 26 Jul 2017, 14:10 
SPB Loop 5 is back online:

- but without crate BKF00095-SPB_IRU_CHL (there is missmatch of hardware and documentation (investigation is ongoin)),

- pumps: PUMP_TURBO4, PUMP_TURBO5, PUMP_TURBO8, PUMP_ROOT_1, PUMP_ROOT_2 ,PUMP_ROOT_3 and IRU_VAC/PUMP_ROOT_1  are without serial connection
Entry   Status after 9.30 Meeting, posted by Adriano Violante on 26 Jul 2017, 10:35 
General


Today the machine is being prepared to lase with 30 bunches in order to allow the radiation measurements in SASE1 Exp. Hall on Thursday
and Friday.
Today GUI will be down for a couple of minutes at 11.30 to allow modifications of the servers for bugs fixing.
Specific
Entry   Tunnel access schedule updated, posted by Gerd Wellenreuther on 25 Jul 2017, 13:26 
Dear all,

I had some minor updates of the TAS during the last days, please check again.

https://docs.xfel.eu/share/page/site/PSC/wiki-page?title=Tunnel_access_schedules&listViewLinkBack=true