Karabo Names in Vacuum component list, posted by Tobias Haas on 24 Jan 2017, 08:23
|
Post on behalf of Alessandro Silenzi:
|
Karabo Names in Vacuum component list, posted by Tobias Haas on 24 Jan 2017, 08:21
|
Post on behalf of Harald Sinn:
for the non-vacuum part of WP73 we have the following situation:
|
STATUS UPDATE: XTD2 Differential Pumping Modules running under interlock control, posted by Tobias Haas on 24 Jan 2017, 08:17
|
Post on behalf of Raul Villanueva:
As we just finished the exhaustive testing and final adjustments of local |
VCTF-list updated, posted by Sabine Cunis on 09 Jan 2017, 10:47
|
The VCTF-components-list
has been updated. Labels on components, as far as visible, are in accordance with names in list.
... please, check for consistency, when naming and labeling XGM components! |
Meeting Minutes 23 Dec 2016, posted by Frederike Wittmaack on 03 Jan 2017, 08:46
|
Please follow the link to view the minutes:
http://tinyurl.com/h3qspzz |
XGM Safe State Definition, posted by Frederike Wittmaack on 19 Dec 2016, 09:44
|
as defined by Jan Grünert:
available on Alfresco: XGM-safe-state.docx
and available at N:\4all\intern\User data\wp74\Devices\11-1_XGMD\03 - Components\XGM-safe-state.docx |
Meeting Minutes 16 Dec 2016, posted by Frederike Wittmaack on 19 Dec 2016, 09:32
|
http://tinyurl.com/zzzy7sd |
Meeting Minutes 09 Dec 2016, posted by Frederike Wittmaack on 09 Dec 2016, 15:31
|
http://tinyurl.com/gqykf7z |
Meeting Minutes 02 Dec 2016, posted by Frederike Wittmaack on 07 Dec 2016, 17:09
|
http://tinyurl.com/hzq7ats |
Remote access to control network form , posted by Frederike Wittmaack on 02 Dec 2016, 11:47
|
http://tinyurl.com/jskzj2h
|
Meeting Minutes 25 Nov 2016, posted by Frederike Wittmaack on 02 Dec 2016, 11:46
|
http://tinyurl.com/jydty26
|
new components list , posted by Sabine Cunis on 02 Dec 2016, 11:43
|
please find the new (extended) components list under the old link given in the minutes http://tinyurl.com/zn7otsa
,
and check whether all components are included and charakterized by the correct data. |
Meeting Minutes 17 Nov 2016, posted by Frederike Wittmaack on 24 Nov 2016, 11:38
|
http://tinyurl.com/hxaxdm9 |
Meeting Minutes 11 Nov 2016, posted by Frederike Wittmaack on 14 Nov 2016, 14:10
|
http://tinyurl.com/juhjcbf |
Mandate for the Extension of the Vacuum Controls Commissioning Task Force, posted by Tobias Haas on 11 Nov 2016, 15:43
|
The Vacuum Controls Commissioning Task Force initially helped to get the vacuum components extending from the gate valve at 2678 m to the gate valve
at 2730 m in XTD2. This comprised the valves and pumps and the associated vacuum interlock logic. The necessary components were all installed and locally
tested. As the next step the PLC firmware for the control of these devices was generated including the interlock logic. Finally the system was connected |
Update of Component list, posted by Tobias Haas on 09 Nov 2016, 15:36
|
I have included the status columns provided by Alessandro and Sandor in the component list. Please find it in the usual location here: http://tinyurl.com/zn7otsa |
Karabo Installation back to normal, posted by Alessandro Silenzi on 07 Nov 2016, 19:15
|
Karabo to PLC communication has been tested successfully in the SA1 Vacuum installation.
in attachment:
OK.png -> Initial Status, all OK |
BeckhoffDevices back to responsive, posted by Alessandro Silenzi on 04 Nov 2016, 18:08
|
I reproduced the behaviour of the PLC on beckhoffSim. This reproduces the same behaviour seen in the tunnel devices (devices hang).
Implemented the fix and verified the correct behaviour with beckhoffSim.
Fixes will be verified next Monday with the tunnel system. |
Minutes - Meeting November 4, 2016, posted by Frederike Wittmaack on 04 Nov 2016, 14:22
|
http://tinyurl.com/jbog6tz |
Minutes of last weeks meeting (Oct 28, 2016), posted by Frederike Wittmaack on 04 Nov 2016, 08:03
|
http://tinyurl.com/jy5rsbx |