437
|
08 Jan 2018, 09:50 |
Monica Aresté | General | Information | Reminder Readiness meeting today at 13:00 | Dear all,
This is a reminder to inform you
that Readiness meeting will resume today |
|
436
|
18 Dec 2017, 10:48 |
Gerd Wellenreuther | General | Information | Status and plans after Readiness Meeting | PSPO:
M. Areste presented a report
about the progress so far achieved in the |
|
435
|
14 Dec 2017, 09:12 |
Lewis Batchelor | XTD2 | Information | FXE Collimating CRL | The LENS_3X limit switch (switched when
driving towards the chamber center) is broken
and must be replaced, hence further work |
|
434
|
13 Dec 2017, 16:28 |
Tobias Haas | General | Information | Status and plans after SASE1 Status/SASE3 Readiness Meeting | General
Meeting on Friday will
take place at 1300 due to overlap with XDAC
M. |
|
433
|
08 Dec 2017, 15:49 |
Tobias Haas | General | Information | Fire alarms in tunnels and shafts on 13 Dec 9 - 11 | FYI
Author: F. Saretzki |
|
432
|
08 Dec 2017, 11:35 |
Tobias Haas | General | Information | Status and plans after SASE1 Status/SASE3 Readiness Meeting | General
Starting from next week
shutdown activities will be tracked using M. |
|
431
|
07 Dec 2017, 09:04 |
Tobias Haas | General | Information | Rack extinguishing system in SASE2 | Please note following info from DESY:
Author: F. Saretzki |
|
430
|
06 Dec 2017, 17:17 |
NEREA JARDON | General | Information | SASE1 MOV | The Motion loop in SASE1 is totally operated
again. |
|
429
|
06 Dec 2017, 13:46 |
Adriano Violante | General | Information | Status report after dispatch meeting 13:00 | General:
Shutdown started.
Instruments
SPB:
AGIPD |
|
428
|
04 Dec 2017, 10:56 |
Tobias Haas | General | Information | Status after 0930 meeting | General:
User operation with good
beam conditions over the weekend
One |
|
427
|
01 Dec 2017, 11:42 |
Tobias Haas | General | Information | Status and plans after SASE1 Status/SASE3 Readiness Meeting | General:
User Operation ongoing
until Tuesday 5 Dec 8 AM
CAS shall |
|
426
|
29 Nov 2017, 09:56 |
Adriano Violante | General | Information | Status after 9.30 dispatch meeting | General
Preparation for the user's
run starting tomorrow (until 7:00 Tuesday |
|
425
|
24 Nov 2017, 13:15 |
Tobias Haas | General | Information | Status and plans after SASE1 Status/SASE3 Readiness Meeting | General
User operation ongoing
in SPB/SFX and FXE
|
|
424
|
22 Nov 2017, 10:57 |
Tobias Haas | General | Information | Status and Plans after 0930 meeting | General
User experiments resume
tomorrow morning
Beam should be |
|
423
|
20 Nov 2017, 10:21 |
Tobias Haas | General | Information | Status after 0930 meeting | General
Intensity and availability
of beam was good over the weekend
Large |
|
422
|
17 Nov 2017, 17:14 |
Tobias Haas | General | Information | Status and plans after SASE1 Status/SASE3 Readiness Meeting | General
Beam is back with good
intensity (up to 1 mJ)
Next |
|
421
|
15 Nov 2017, 11:51 |
Tobias Haas | General | Information | Status after 0930 meeting | Instruments
SPB:
Waiting
for beam to come in a usable condition (500 |
|
420
|
14 Nov 2017, 11:05 |
Gerd Wellenreuther | General | Information | Tunnel access schedule updated | Dear all,
I received updates from DESY (M.
Hüning) about how the access to the |
|
419
|
13 Nov 2017, 09:45 |
Adriano Violante | General | Information | Status after 9.30 dispatch meeting | General
No user operation.
During
the week end the accelerator was not able |
|
418
|
10 Nov 2017, 11:46 |
Tobias Haas | General | Information | Status and plans after SASE1 Status/SASE3 Readiness Meeting | General
User operation is delayed
by 48h due to rocky startup of FEL.
FEL |
|