ID |
Date |
Author |
Location |
Severity |
Subject |
437
|
08 Jan 2018, 09:50 |
Monica Aresté | General | Information | Reminder Readiness meeting today at 13:00 | Dear all,
This is a reminder to inform you that Readiness meeting will resume today at 13:00.
Best regards and Happy New Year !!
|
436
|
18 Dec 2017, 10:48 |
Gerd Wellenreuther | General | Information | Status and plans after Readiness Meeting | PSPO:
- M. Areste presented a report about the progress so far achieved in the shutdown (see Indico for details).
- Most tasks are ongoing, on schedule.
- Few still have to be scheduled, mostly because support groups wait for feedback.
- C. Youngman does detailed coordination of SASE3tasks.Will organize meeting on Tuesday 9:30 for SASE3 tunnel only
- We will review the progress again in Mid-January!
SPB (M. Sikorski):
- AGIPD was tested.
- Roll back to crystallography configuration is ongoing.
FXE: No one attended.
Vacuum (M. Dommach):
- 1st mirror M1 in SASE3 installed, chamber closed, pumped down & leak tested
- Preparations for 2nd mirror in SASE3 installation ongoing, to be installed next week.
- MCP taken out of SASE3, put in parking position and pumped down again.
- Grating chamber from FXE was installed by JJ X-ray, is to be pumped in CW 51.
- SASE2 XS2 beam pipe behind shutter and lead wall installed, ready for TÜV inspection next week.
Diagnostics (A. Koch):
- XGM in XTD1 is almost cabled, more cabling was done in XTD10.
- Gas supply system in XTD1+6 was worked on.
- Photonics Science camera was tested.
- Trouble with the motion loop in XTD2 and XTD10, reported to AE.
AE (P. Gessler ):
- MCP motion and k-monochromator were tested.
- Motion loop was split in SASE1 tunnel.
- Many tests, lots of work in progress, need to act quick as time is short.
- T. Wilksen (DESY) is going to update the timing hardware è devices would have to switch to local timing, and switch back later to be operable.
Laser (M. Lederer):
- Further commissioning of the PP-laser was started.
- Upgraded Karabo and PLC firmwares. Works are on schedule.
- Measurements on the dependence of humidity are ongoing.
- DESY is working on the timing system, laser synchronization will be down until the 21.1.18.
- PP-laser pattern selection with machine timing:DESY is now pushing for the originally planned implementation. DESY will have to do some software development in this context.
Detectors (J. )
- Tested the AGIPD @ SPB, but 1 board was not working. Detector consortium could not provide a replacement board, so only half of the detector was tested before SPB/SFX had to close the detector vessel again.
- LPD was tested with train builder, but only tests using 2 memory cells could be conducted (2 images per train), so train builder was not tested with all memory cells.
- More tests with full load (i.e up to 510 images per train) still have to be performed.
- Test with DSSC will take place in HERA South in CW 51.
ITDM (K. Wrona)
- Monday til Wednesday there will be no DAQ due to extension of the Infini-band bandwidth, upgrades, firmware updates, recabling etc.
- DAQ up again on Thursday
Software (S. Brockhauser)
- CAS-People are currently working only in SASE3. In the future, they can either work on SASE3 or SASE2, but not both!
- Slides with Project-plan provided by Hugo Santos (see Indico)
- Release of Karabo 2.2.0 on the 18.12. (in the meantime shifted to the 20.12.)
- Testing by ITDM and consecutive deployment in tunnels and at the instruments takes until 22nd of January
- Karabo 2.2.1 to be expected mid of January
- Further decisions will be taken mid of January
|
435
|
14 Dec 2017, 09:12 |
Lewis Batchelor | XTD2 | Information | FXE Collimating CRL | The LENS_3X limit switch (switched when driving towards the chamber center) is broken and must be replaced, hence further work is required on the next JJ visit 9/10 Jan (TBC)
The in vacuum components also need further work during the above visit. The lens that lost alignment during commissioning was also found to be more severley damaged than anticipated - the B4C guard is cracked and this deposited some fragments under the lens. All lens cassettes will be exchanged, rebuilt and realigned in Jan.
The patch panel has been removed for rework (to switch motor direction)
The Be lenses seem to be in exactly the same condition as 'new' |
434
|
13 Dec 2017, 16:28 |
Tobias Haas | General | Information | Status and plans after SASE1 Status/SASE3 Readiness Meeting | General
- Meeting on Friday will take place at 1300 due to overlap with XDAC
- M. Areste shall ask for updates on task list on Thursday
Instruments
- SPB
- Work on AGIPD is ahead of schedule. Closing of detector should happen at the beginning of next week
- Additional installations for roughing pump system is going on and will probably finish this year
Tunnels
- Diagnostics group currently working in the Southern tunnels, cabling components and aligning imagers
- Colleagues from Russia are coming 3 - 20 Jan to work on MCP in SASE3
- KMono local tests in SASE3 should also happen in early Jan
- Diagnostics requests scenes for XGM in XTD1
AE
- Vacuum loop in SASE3 will be modified. Some components shall be moved to a separate loop, e. g. Soft Mono
- SPB tunnel loop will be re-deployed to include the attenuator
- The motion loop in SASE1 will also be split to allow more rapid updates for newly integrated components
- Z-motion crate for detector in SPB will be done until next week or early next year
CAS
- Currently working with AE and ITDM on refining release schedule for KARABO
- Testing the version for release next week. This will then first be used by ITDM and is needed for the firmware upgrade of AGIPD
- Work is going on on the XGM train ID problem
- FXE will be moved to a separate topic (broker) to disentangle some dependencies at least temporarily
- FEL imager performance problem was investigated. This runs on a server that is very busy and should be moved to a different server
|
433
|
08 Dec 2017, 15:49 |
Tobias Haas | General | Information | Fire alarms in tunnels and shafts on 13 Dec 9 - 11 | FYI
Author: F. Saretzki
English version below
Ankündigung:
Aufgrund von Sachverständigenprüfungen wird es am folgenden Termin zu Auslösungen des Evakuierungsalarms kommen:
Gebäude: XHE2/XS2, XHE4/XS4, XSDU1, XTD1, 3, 5, 6, 7 und 8
Datum: 13.12.2017 ca. 09:00 Uhr – 11:00 Uhr
Sie brauchen bei ertönen der Sirene in diesen Zeiträumen das Gebäude nicht verlassen.
============================================================================
Announcement:
Due to expert testing there will be an evacuation alarm on the following date:
Building: XHE2/XS2, XHE4/XS4, XSDU1, XTD1, 3, 5, 6, 7 and 8
Date: 13th of December 2017 between 09:00 a.m. and 11:00 a.m.
You don’t need to exit the building while the alarm occurs.
|
432
|
08 Dec 2017, 11:35 |
Tobias Haas | General | Information | Status and plans after SASE1 Status/SASE3 Readiness Meeting | General
- Starting from next week shutdown activities will be tracked using M. Aresté's list
- Dispatch meeting on Monday and Wednesday at 13:00
- Next Friday Readiness meeting also at 13:00 because of conflict with XDAC
Instruments
- FXE:
- Currently focussing of implementing all default parameters into the next firmware release
- SPB:
- Major detector work with AGIPD disassembly started
Tunnels
- Currently testing firmware and software in SASE3
- Installation of first mirror starts next week. Mirror installation takes about 1 wk/mirror
- CRL in XTD2 will be vented to align internal mask and fix stuck arm
- Drilling takes place at the end of XTD9 for the installation of the FXE diamond grating
- Mirror cooling will not be installed this shutdown. It is not needed for the planned bunch rates and might introduce unwanted effects/vibrations
- Activities of Diagnostics:
- Photonics Science camera in SASE1 exchange.
- Tests are being carried out in SASE3 together with J. Tolkiehn
- Cabling is going on in XTD1 on the XGM
- There is a noise problem on the Gotthardt detector in the HIREX. Need support from AE to find the origin
AE
- Motion loop in SASE3 will be split into mov1 and mov2. This will allow to sort components into more and less stable sets and keep one of the loops up most of the time
Laser
- Laser activities had to start late due to problems with AC and laser interlock (delays of 6 and 5 months respectively)
- Availability of trigger pattern from the machine was also a problem
- Specs could just be reached for the Nov user period
- Eventually the PP laser was not used for any of the experiments
- Work on the laser is far from finished and will require 3 more months to come to full funtionality
- Currently, the Karabo version is being upgraded and the most up-to-date PLC firmware is being installed
- These updates had intentionally been delayed until the end of the user period.
Detector
- Detector group not present at the meeting
- Information from SPB: major work is ongoing on AGIPD
AE
- Train builder is being tested as it was not used so far. This required re-cabling
- PLC motor loops are also being split in SASE1
- Many activities in SPB
- Remaining modifications of modules have started
- Export of input for firmware generation for loop 8 has been provided by EETF
- Waiting for go in FXE
- Need to work on the interface for the EPS system
- No tasks currently from laser group
- New information available on SmarACT stages: The observed problems arise from a cable problem and can be solve by configuration
- The problems with movers in the sample chamber in SPB (non-functioning encoders) arise from cable cross talk at the vacuum feed through. This require hardware re-design
- In SASE2 there are tests coming up together with the diagnostics group
ITDM
- Train builder tests are scheduled next week
- Recabling of Infiniband network happens on 18/19/20 Dec. No DAQ and controls available on these days
- A summary of DAQ statistics was shown (see slides on INDICO)
CAS
- Release of KARABO 2.2 on 18 Dec
- Freeze of functionality on 21 Jan
- Discussion reveals that a discussion on specific deployment dates and needs of different groups is urgently needed (Instruments, Tunnels, DAQ)
|
431
|
07 Dec 2017, 09:04 |
Tobias Haas | General | Information | Rack extinguishing system in SASE2 | Please note following info from DESY:
Author: F. Saretzki
Ab sofort werden die Rack-Löschanlagen in den südlichen Tunneln in Betrieb genommen. Die Anlagen bleiben danach scharf.
|
430
|
06 Dec 2017, 17:17 |
NEREA JARDON | General | Information | SASE1 MOV | The Motion loop in SASE1 is totally operated again. |
429
|
06 Dec 2017, 13:46 |
Adriano Violante | General | Information | Status report after dispatch meeting 13:00 | General:
Instruments
- SPB:
- AGIPD prepared for exchange modules intervention
- AE is in contact with SPB for crates issues fixing
- The schedule for next year, especially when the experiment has to be ready before the users run has to be known as soon as possible.
- FXE
- Starting loops update in the next days. Reason for the small delay is that FXE is checking all the default parameters to be able to restore them after the update.
- In order to solve some DAQ issues, FXE requested to have their own topic. AE agrees, ITDM agrees, CAS is trying to find out how to do it and to do it before the next users run. Technical details have to be discussed offline with FXE.
ITDM
- in KW 51 (18-22 Dec.) the DAQ and online cluster will not be available due to recabling works in the balcony rooms.
- Update of the servers in the experiments has to be done. ITDM requested to know from CAS when the major update of Karabo is taking place to coordinate the effort and minimize the downtime. CAS will present a schedule concerning Karabo this Friday.
- 700 Tb of data are stored on the online cluster. It has to be communicated by the experiments what can be moved from there, since there is almost no space left.
Diagnostics
- Implementation of Gotthard detector in Karabo is still a problem. S.Hauf will invite the main groups involved for a meeting to find a solution.
- The data correlation with time stamps when using the Karabo DAQ has to be done carefully and contacting WP74 since there are still issues present.
AE
- Activities on the Hirex in SASE1 will need the MOV loop to be brought down in the afternoon. An entry in the ELOG will be written.
- SPB loop 8 prepared.
- Full list of new crates belonging to the motion loop in SASE3 tunnels has to be delivered to AE
- Full list of new crates belonging to the IPS loop in SASE3 tunnels has to be delivered to AE in order to be able to close the loop.
- Technosoft controller issues in SASE3 will be attacked once the SASE1 activities will allow it.
VAC
- VAC testing ongoing.
- 2 mirrors will be installed before Christmas
- Motion crates for the motion lopps and test of the VAC interlock will happen this week.
|
428
|
04 Dec 2017, 10:56 |
Tobias Haas | General | Information | Status after 0930 meeting | General:
- User operation with good beam conditions over the weekend
- One interlock trip in the FXE branch in XTD9. Restored by CAS
- Shutdown starts tomorrow at 08:00.
- Next dispatch meeting takes place Wednesday at 13:00. A reminder will be sent.
Instruments
- SPB:
- Started with the actual sample during the night shift
- Some DAQ issues
- 108TB data was recorded
- Problems appear to occur between 01:00 and 02:00 and between 13:00 and 14:00
- FXE
- Running is ok.
- Temporal and spatial overlap with optical laser established
- Currently taking pump-probe data
- People on shift were uncertain about how to recover from interlock trip
- Statement from Vacuum: Pumps can restarted/valves open if the respective button in KARABO can be clicked
CAS:
- Delay between data taking and "online" analysis in the "Hummingbird" software is about 0.3s
ITDM
- On Friday, there was a global network outage affecting the Office Network on the DESY site.
- The transponder system in the experiment hall was down
- SRP organised a guard at the hall entrance so that the hall had not to be evacuated
- The control network (XDAC) was not affected
|
427
|
01 Dec 2017, 11:42 |
Tobias Haas | General | Information | Status and plans after SASE1 Status/SASE3 Readiness Meeting | General:
- User Operation ongoing until Tuesday 5 Dec 8 AM
- CAS shall present a release plan for KARABO 2.2 next week
- Dispatch meetings shall move to a Mo/Wed 13:00 schedule starting next Wedneday 6 Dec
Instruments
- FXE:
- Scantool was successfully used to establish overlap with laser beam (Tangerine)
- Some problems with slow DAQ in particular also for tunnel components
- Comment from ITDM: There are known issues with the slow data acquisiton. A new version exists that was intentionally not deployed before the end of UOP
- SPB
- Just finished first shift of laser user experiment
- No big problems
- All goals in the optimistic schedule were achieved
Tunnels
- Currently preparing for the shutdown
- Sticking condition of mirror bender could be reproduced in the lab
- WP74 just installed the last missing pieces in XTD1
Laser
- Running
- temporal and spatial overlap with beam is achieved
- But now instruments do not intend to use the PP laser for the last experiment
Detectors
- Both detectors are working
- The DAQ for slow data is crashing occasionally
- Gotthard is fully operational but there problems getting the data out. Help from PSI is needed
AE
ITDM
CAS
- CAS-XPD Running:
- We will finish next Monday
- We have been addressing issues related to MCP, Karabo-DAQ, Cameras, and K-Mono
- Deploy K-mono today
- Review DAQ Groups in Karabo: Cyril (interface to ITDM), Liubov, Koch
- Gotthard we have to address in a separate and more systematic discussion: trigger, operation, calibration...
- XGM memleak - we already have a fix to get it stable but have to check when we will be able to upgrade (only device).
- Internal discussion about CAS/Karabo priorities for the winter shutdown
|
426
|
29 Nov 2017, 09:56 |
Adriano Violante | General | Information | Status after 9.30 dispatch meeting | General
- Preparation for the user's run starting tomorrow (until 7:00 Tuesday morning)
Instruments
- FXE:
- On Monday night the DAQ seemed to be slow. This problem was caused by a misconfiguration in the DAQ which could be solved by ITDM once they were informed. In general both the Configuration understanding by the users and the communication with ITDM has to improve.
- The Gotthard detector could not be used. The Greateyes detector is being used now and works properly.
- PP laser is now synchronized but not commissioned yet. This is going on now (crucial point is the pulse width measure). It is not yet clear whether the PP laser will be used in the next users run.
- SPB
- AGIPD was moved 5 m downstream for the next experiments. Vacuum is OK. Alignment checked with the ALAS, will be checked with beam probably today evening.
- A change in the DAQ configuration has to be (is being) done today (CAS/ITDM)
ITDM
- Upgrade switches today at 9:00 will be checked if there were problems right after this meeting.
|
425
|
24 Nov 2017, 13:15 |
Tobias Haas | General | Information | Status and plans after SASE1 Status/SASE3 Readiness Meeting | General
- User operation ongoing in SPB/SFX and FXE
Instruments
- FXE:
- User operation started during the night
- Some concerns over running LPD as the sample chamber is from diamond and direct reflections could cause damage
- Generally instrument worked very well
- Synchronization with PP laser is now in a state where it can be tested
- SPB
- Many data taken for detector calibration
- Severe issues with KARABO
- Response is very slow
- Major crash this morning
- Detector controls complex and instable
- A failure of AGIPD related to FPGA not understood
- Strange interlock issue: EPS interlocks appeared disabled
Tunnels
- L. Samoylova spent many hours on Wednesday to set up the DAQ in the tunnel
- With the help of many support people she managed to get the system to work
- The system is instable and also seems to record many more parameters than are needed
- Use of the system is very clumsy
- Comment from ITDM (L. Maia): The data sources were specified by the users. It is acknowledged that the system needs a lot more work
- Diagnostics is working with CAS in a squad to work down a list of open redmine tickets
- The DOOCS - KARABO bridge is now working. The FEL imager is routinely available in DOOCS to the BKR crew
- DESY set up a statistics server to help collect data about beam pointing instabilities
Laser
- Local pattern generation synchronized to machine timing is working
- Overlap finding together with FXE was done but has to be tested under real condition next week
- A few suddent shutoffs of the front end occured. The origin might be understood
- There are large timing drifts in the ADCs that are currently not understood (up to ms)
ITDM
- Next Wednesday there will be a 1h shutdown of the load balancer in the DESY RZ. This should affect mostly the web services
- It should be noted that the DAQ ran quite stably in SPB and FXE. More than 20 runs were collected in each case without a restart
CAS
- Two hot fixes are out (2.1.18.4/5). These address very specific issues
- A major new release (2.2) is planned for the winter shutdown. This will be mandatory
- Comment from instrument: It must happen early so that wrinkles can be ironed out!)
|
424
|
22 Nov 2017, 10:57 |
Tobias Haas | General | Information | Status and Plans after 0930 meeting | General
- User experiments resume tomorrow morning
- Beam should be coming back late this morning or early this afternoon
- After the Operation Coordinaton Meeting H. Sinn, L. Samoylova and the instruments will align the mirrors
- Beam to the instruments should be available directly after this
Instruments
- SPB:
- The last night with beam on Monday was used to take flat field calibrations with AGIPD
- The timing for overlap with the optical laser was adjusted
- 5 out of 6 SmarACT rotational stages are now operations. Some problems remain and AE is talking to the manufacturer
- FXE
- Request for use of the beam after 9 PM
- Can be given to SPB starting at 5 AM tomorrow for final setup
Detectors
- Connection to the ONDA system was set up for the detectors
- Significant latency develops quickly an saturates at approximately 2 mins
ITDM
- Simultaneous use of the DAQ system by both instruments should be done carefullly
AE
CAS
|
423
|
20 Nov 2017, 10:21 |
Tobias Haas | General | Information | Status after 0930 meeting | General
- Intensity and availability of beam was good over the weekend
- Large drifts and jitter were observed that are significantly higher than previously
- Beam has two horizontal lobes as if it is too large for the mirrors
Instruments
- SPB:
- Many tasks were achieved during the weekend, e. g. instrument alignment, detector calibration
- Issue with encoders whose cables are close to motor cables persists. These encoders are being disabled
- Rotational SmarACT stages still do not work and are needed for this week's user experiment
- FXE
- At shift start on Saturday after reloading beam parameters there was no beam in the hutch.
- Beam had to be brought back by hand. This was a large effort
- This situation did not repeat on Sunday
- LPD detector had problems: Only one super module correctly recorded data. Comment from S. Hauf: FXE should have called the detector expert
- PP laser synchronisation does not work properly yet: Increments when adjusting timing are too coarse. Scan range is limited to 18ns
Detector
- Detector group was not informed about the LPD issues in FXE.
- AGIPD calibrations were successfully taken on Sunday
ITDM
- Still work is needed for slow data DAQ
- DAQ behaves differently in SPB and FXE. In FXE it appears overloaded and in SPB it works fine
- Comment from CAS:
- Many changes were made in the KARABO framework to allow asynchronous operation
- These changes have to be also pulled through to DAQ. This will only be done during the winter shutdown
- Until then, DAQ is very vulnerable to any delay in the system
CAS
AE
- Currently working on problems with rotational stages in SPB
|
422
|
17 Nov 2017, 17:14 |
Tobias Haas | General | Information | Status and plans after SASE1 Status/SASE3 Readiness Meeting | General
- Beam is back with good intensity (up to 1 mJ)
- Next user period starts on 23 Nov
- Time between now and then should be used to optimize FEL, beam lines and Instruments
Instruments
- FXE:
- Measurements of pulse intensity were done using an XGM from DESY in the hutch
- A pulse intensity of ca 40 uJ was found. This is in rough agreement with the expectations
- Spectrometer was aligned
- GreatEyes and Gotthardt detectors are working fine
- LPD still to be checked
- SPB:
- Using beam to do alignment
- Not such a good focus (too big)
- Plans are to continue with instrument commissioning today and Saturday
- Work is currently being done by Mahadi on the SmarACT rotary stages
- FXE points out that most likely SPB operated with the FXE CRLs inserted into the beam
- Note: The standard "switching script" from Harald should be used to make sure parameters and devices are properly adjusted when beam is switched from one instrument to the other
- Detector calibration on Sunday
Tunnels
- Last Friday there was a Bender failure on mirror M2
- The mirror was removed from the tunnel during the weekend and the SASE2 spare was inserted
- In the process one Beckhoff controller was found broken
- In the removal process a further problem was caused in one of the Beckhoff loops
- This problem could be fixed from outside the tunnel
- After this 20h were spent to redo Beam-Based Alignment in 7 iterations
- The new orbit deviates from the old by up to 80 um.
- After using the new orbit, the FEL lased quickly with good intensity
- The replaced mirror M2 could be re-aligned
- On Thursday beam was available to FXE
- Remark from J. Grünert: Instruments should make sure that most up-to-date DOOCS panel is loaded to see proper XGM info
- Update of DAQ caused DAQ in tunnels to be broken. This is now fixed according to K. Wrona
- HIREX commissiong is going in parallel
Detectors
- AGIPD:
- Before the bender failure a few X-Rays could be taken on AGIPD
- It looks like 30 X-Ray pulse can be taken now
- Additional flat field calibration is needed now
- On Sunday a full shift is foreseen for commissioning with beam
- LPD:
- One quadrant was disassembled to find the cooling leak.
- Leak now appears to be fixed
- No sign of dead spots on detector
Laser
- We are operating in shifts: early / late, although experiments have been cancelled, performing shift change and other excercises for commissioning.
- Operating the laser with machine timing was so far hampered by the fact that the transmitted laser patterns from the machine were limited to the actual number of x-ray pulses, i. e. mostly non-deterministic 1 or 0. Optical alignment and characterization is not possible under those conditions. Therefore, on the weekend we have switched to local timing to give guys some power.
- Following this experience, we have decided to attempt local generation of laser patterns under machine timing in order to be independent of the machine and not have to switch back and forth between local and machine timing. This has been implemented and is under test today and over night. We still observe spurious long term drifts, which are under investigation. However, if finally successful, this can only be a make shift solution for the coming weeks. Mid to long term we need proper implementation by DESY, allowing pattern changes on short notice and independent of the machine. This is in preparation (time line ca. mid 2018).
- Currently, beams are sent to FXE and SPB with 30 pulses each, 800nm broadband, should be compressible to 15fs. This is under machine timing but with locally generated patterns.
- There are other curiosities concerning machine timing, which are related to the increased T0 arrival time jitter compared with our local timing. Debugging is ongoing. We are also testing various features under above conditions (machine timing, local pattern): phase shifter, trigger shifter, shift change. Time line: depending on outcome, daily updates will be provided.
AE
- When the breakdown of the interlock occured in conjunction with the broken Beckhoff terminal it became obvious that crucial emergency phone numbers are not available
- Better emergency procedures are needed
- The special EPS operation mentioned to align the mirrors should be written down so that it can be implemented an no override of the interlock system is needed
- The list of shutdown activities compiled by PSPO contains a lot of work for AE. This is now being discussed.
ITDM
- Some problems occured this week with DAQ of slow data. This should have been fixed yesterday
CAS
- Doing 24/7 OCD support
- During switch between instrument CAS comes in to provide support
- The cancellation of user operation last weekend was not properly communicated so that people came in unnecessarily
- Next week additional work for WP74 is being done
|
421
|
15 Nov 2017, 11:51 |
Tobias Haas | General | Information | Status after 0930 meeting | Instruments
- SPB:
- Waiting for beam to come in a usable condition (500 uJ and pointing within aperture of optical elements)
- FXE
AE
- There was an interrupt of the vacuum loop in XTD2 due to a faulty pump controller. This was fixed by ZZ
- Rotational SmarACT stage and slits in the sample chamber for SPB are being worked on
CAS
- Due to change of beam schedule, now working on implementing more devices in DOOCS-KARABO for Jan Grünert
ITDM
- Will upgrade DAQ software today. Note: Still based on KARABO 2.1.16
|
420
|
14 Nov 2017, 11:05 |
Gerd Wellenreuther | General | Information | Tunnel access schedule updated | Dear all,
I received updates from DESY (M. Hüning) about how the access to the southern tunnels is being restricted in the next months, due to interlock tests etc., and included it in the TAS. Please check, if you have work to be done in these tunnels:
https://docs.xfel.eu/share/page/site/PSC/wiki-page?title=Tunnel_access_schedules
Cheers, Gerd |
419
|
13 Nov 2017, 09:45 |
Adriano Violante | General | Information | Status after 9.30 dispatch meeting | General
- No user operation.
- During the week end the accelerator was not able to deliver reliable and stable beam for the user operation.
- The M2 mirror bender stopped working on Saturday morning and had to be replaced. The mirror and blender were replaced as a whole durig the week end. Normally it would have taker weeks but a "spare" system was already set up for SASE2 and could be used on a short notice. Pumping of the M2 section is ongoing and leak test be performed today.
- The non working M2 does not show apparent problems so far, and the reason why was not working is not clear.
- Some sections of the LINAC were warmed up due to some maintenance required for the cold compressors.
- LINAC is being cooled down and ready for operation today afternoon.
- The technical support groups were not informed about the problems until saturday afternoon. The communication channels in these cases have to be improved.
Instruments
- SPB and FXE:
- The goal is to be able to strat the secondo users run on Thursday (Day FXE, Night SPB).
Tunnels
- XTD2,9 Ready to take beam in the afternoon (if no leak in M2 is discovered).
ITDM
- A small bug was found in the DAQ that affects only slow devices with certain train ids
- It is proposed to fix this during the next break. Decide on Wednesday
|
418
|
10 Nov 2017, 11:46 |
Tobias Haas | General | Information | Status and plans after SASE1 Status/SASE3 Readiness Meeting | General
- User operation is delayed by 48h due to rocky startup of FEL.
- FEL still has not reached acceptable levels of stability and power
Instruments
- SPB:
- Instrument was brought back to a somewhat running state
- There are still problems with motors in the sample chamber
- Alignment with beam is ongoing at this time
- FXE
- New scan tool was tested
- Currently working on user-specific alignment tasks
- Laser was routed to the sample position
- The beam is still drifting around
Tunnels
- FEL had trouble to find lasing
- There was a controled access on Wednesday to fix various problems. However, further problems appeared
- It was decided to roll back the changes made for a new injector laser, but this did not improve the situation
- At some point 400 uJ were reached and lost again
- There are many problems with the undulator system
- Incorrect values in lookup tables
- Difficult operation of the entire system
- FXE should be able to start up tonight
- SPB would follow Saturday morning since time is needed for alignment during the day today
- Shifts for photon diagnostics were largely cancelled due to FEL problems
- KMONO gave some interesting results pointing to the problems in the undulator system
- Next week FEL Imager and KMONO will be installed in SASE2
Laser
- Both SASE1 instruments have laser beam with local timing.
- Tests with machine timing start today at lunchtime
Detectors
- AGIPD is in best possible state.
- Firmware and DAQ were upgraded
- Some commissioning time with beam is needed today
- LPD had a cooling leak and a power problem last night
- At 6 pm yesterday, this was still not fixed
AE
- Continuing small activities for user operation
ITDM
- A small bug was found in the DAQ that affects only slow devices with certain train ids
- It is proposed to fix this during the next break. Decide on this Monday
CAS
- Dedicated squads for the setups of SPB/FXE, DOOCS integration, Scan Tool closed now
- Tools delivered but with significantly reduced scope
- All necessary things for DOOCS Karabo integration were delivered. Now waiting for DESY
|
|