Notes XO Integration Meeting 22.11.2023, posted by Frederik Wolff-Fabris on 22 Nov 2023, 10:39
|
General Announcement:
-
|
Notes XO Integration Meeting 20.11.2023, posted by Frederik Wolff-Fabris on 20 Nov 2023, 10:01
|
General Announcement:
-
|
Notes XO Integration Meeting 15.11.2023, posted by Frederik Wolff-Fabris on 15 Nov 2023, 09:48
|
General Announcement:
- As PRC, A. Galler informs the machine runs without major issues but kicker adaptation has difficulties with 4.5MHz. For the next 20 mins machine colleagues
will introduce stronger kickers and during
|
Notes XO Integration Meeting 13.11.2023, posted by Frederik Wolff-Fabris on 13 Nov 2023, 10:16
|
General Announcement:
- This and next week of operation are the last 2 delivery weeks, which are done with 4.5MHz base rep rate.
|
Notes XO Integration Meeting 08.11.2023, posted by Frederik Wolff-Fabris on 08 Nov 2023, 09:55
|
General Announcement:
-
|
Notes XO Integration Meeting 06.11.2023, posted by Frederik Wolff-Fabris on 06 Nov 2023, 09:53
|
General Announcement:
- As PRC, Jan G. reports that on Saturday morning no beam permission at the North branch happened. An issue with XTD2 solid attenuator vacuum happened
and together with VAC-OCD the threshold was changed
|
Notes XO Integration Meeting 01.11.2023, posted by Frederik Wolff-Fabris on 01 Nov 2023, 10:04
|
General Announcement:
- Jan G. as PRC comments: 1. reminds SQS and FXE instruments to place entries at the Operations e-log;
2. machine is running well and ZZ accesses happened on Monday (hindered by issues with tunnel entrance) but all done;
|
Notes XO Integration Meeting 30.10.2023, posted by Frederik Wolff-Fabris on 30 Oct 2023, 09:47
|
General Announcement:
-
|
Notes XO Integration Meeting 25.10.2023, posted by Andreas Galler on 25 Oct 2023, 09:26
|
General Announcement:
CTRL:
nothing major --> a couple of people on vacation, i.e. issue repsonse time may be a bit longer this week
DA: |
Notes XO Integration Meeting 23.10.2023, posted by Andreas Galler on 23 Oct 2023, 09:26
|
General Announcement:
CTRL:
nothing major
DA: |
Notes XO Integration Meeting 18.10.2023, posted by Frederik Wolff-Fabris on 18 Oct 2023, 10:01
|
General Announcement:
- Next Friday 20th Oct. is the deadline for submitting the Winter maintenance task list back to XO.
|
Notes XO Integration Meeting 16.10.2023, posted by Frederik Wolff-Fabris on 16 Oct 2023, 09:46
|
General Announcement:
- Last X-ray delivery week went normal.
- Friendly reminder for the submission of the maintenance task list on 20.10, next Friday. In case of questions please do not hesitate in contacting XO.
|
Notes XO Integration Meeting 11.10.2023, posted by Frederik Wolff-Fabris on 11 Oct 2023, 10:15
|
General Announcement:
- Reminder that next week, on 20.10, is the deadline to submit the Winter maintenance task lists to XO. In case of help, please contact Martin Doering
at xo-planning@xfel.eu.
|
Notes XO Integration Meeting 09.10.2023, posted by Andreas Galler on 09 Oct 2023, 09:23
|
General Announcement:
CTRL:
nothing major
DA: |
Notes XO Integration Meeting 04.10.2023, posted by Frederik Wolff-Fabris on 04 Oct 2023, 09:52
|
General Announcement:
- A. Galler reminds this is a facility development week and for the next UOM on Friday a report of stability/jitter shall be done by the instruments.
- Martin Doering announces the Winter maintenance period 23/24:
|
Notes XO Integration Meeting 02.10.2023, posted by Frederik Wolff-Fabris on 02 Oct 2023, 09:59
|
General Announcement:
-
|
Notes XO Integration Meeting 27.09.2023, posted by Frederik Wolff-Fabris on 27 Sep 2023, 10:30
|
General Announcement:
- The Winter Maintenance Task list will be sent to all groups in the course of today. Next Wednesday 04.10 Martin Doering will make a quick presentation
on the list itself and take questions.
|
Notes XO Integration Meeting 25.09.2023, posted by Frederik Wolff-Fabris on 25 Sep 2023, 12:31
|
General Announcement:
- Two severe power glitches happened on the weekend (SAT and SUN around 7AM). We thank all colleagues that were in shift, OCD or volunteered to help assessing
the situation and restoring their operation
|
Notes XO Integration Meeting 20.09.2023, posted by Frederik Wolff-Fabris on 20 Sep 2023, 10:04
|
General Announcement:
- The access and maintenance day is taking place today. Current ZZs at the accelerator are scheduled until 10AM and then it follows the tuning for cw38
beam delivery that starts from tomorrow at 7AM.
|
Notes XO Integration Meeting 18.09.2023, posted by Frederik Wolff-Fabris on 18 Sep 2023, 10:01
|
General Announcement:
- Differently from standard Mondays, today is a beam delivery day. The machine tuning day for cw38 takes place on Wednesday.
|