SASE1 Status and SASE3 Readiness
|
Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther |
Not logged in |
|
|
Message ID: 485
Entry time: 29 Jan 2024, 09:57
|
Author: |
Frederik Wolff-Fabris |
Location: |
General |
Severity: |
Information |
Subject: |
Notes XO Integration Meeting 29.01.2024 |
|
|
General Announcement:
- Experiment tuning week starts on Wed 7AM until Tue 7AM next week. It is the first week with Tuesday as tuning day by machine.
CTRL:
- Nothing to report.
- Steffen H. inform on DAQ update: SPB run with AGIPD (data aggregator) worked nicely; With runs over the weekend making progress.
DA:
- Nothing to report.
EEE:
- One PLC update requested by HED was done.
VAC:
- Nothing to report.
XPD:
- Fine from XPD side;
- As PRC, Jan G. informs that overall all program points for last week were completed even if small issues happened; On Sunday machine had a downtime during the day.
DET:
- Contacts with bring up days: detectors were put into operation and all good.
ITDM:
- Info regarding new online storage for SA1: still on preparation and in good way to have ready for this week. A switch will be done and organized with SPB/SFX and FXE.
XRO:
- Ramp-up time last week: SA1 and SA2 mirror motors are recalibrated and/or readjusted. Please see 2024 e-log for details. Instruments can use these values as starting point.
- Beam commissioning still limited due to bunch limitations by interlocks from MDL instrument side.
LAS:
- Not present.
UNSYS:
- Small problem with cell12/SA3 undulator. A ZZ is planned for today.
SPB:
- Nothing to report.
FXE:
- Nothing to report.
MID:
- All fine at MID.
HED:
- Everything looks good so far.
SCS:
- Everything is fine.
SQS:
- Everything OK.
SXP:
- Problem with safety keys: not returned before Friday. A. Galler mentions that for the future it will be incorporated as a maintenance activity. |