Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 485     Entry time: 29 Jan 2024, 09:57
Author: Frederik Wolff-Fabris 
Location: General 
Severity: Information 
Subject: Notes XO Integration Meeting 29.01.2024 
General Announcement:
- Experiment tuning week starts on Wed 7AM until Tue 7AM next week. It is the first week with Tuesday as tuning day by machine.

CTRL:
- Nothing to report.
- Steffen H. inform on DAQ update: SPB run with AGIPD (data aggregator) worked nicely; With runs over the weekend making progress.

DA:
- Nothing to report.

EEE:
- One PLC update requested by HED was done.

VAC:
- Nothing to report.

XPD:
- Fine from XPD side;
- As PRC, Jan G. informs that overall all program points for last week were completed even if small issues happened; On Sunday machine had a downtime during the day.

DET:
- Contacts with bring up days: detectors were put into operation and all good.

ITDM: 
- Info regarding new online storage for SA1: still on preparation and in good way to have ready for this week. A switch will be done and organized with SPB/SFX and FXE.

XRO:
- Ramp-up time last week: SA1 and SA2 mirror motors are recalibrated and/or readjusted. Please see 2024 e-log for details. Instruments can use these values as starting point.
- Beam commissioning still limited due to bunch limitations by interlocks from MDL instrument side.

LAS:
- Not present.

UNSYS:
- Small problem with cell12/SA3 undulator. A ZZ is planned for today.

SPB:
- Nothing to report.

FXE:
- Nothing to report.

MID:
- All fine at MID.

HED:
- Everything looks good so far.

SCS:
- Everything is fine.

SQS:
- Everything OK.

SXP:
- Problem with safety keys: not returned before Friday. A. Galler mentions that for the future it will be incorporated as a maintenance activity.