General Announcement:
- A cryo failure happened today at 09:15AM. Machine is down and shifts for today are cancelled. Experts are investigating the issue to define when to expect ramp-up for the delivery week. Naresh K., as
PRC, adds that the expected downtime is 12 hs.
- As PRC, Naresh K. informs the blue week activities were successful so far. On Sunday the AC for SPB/SFX was making strange noises - TS is aware and will look into details.
CTRL:
- Nothing to report.
- Dennis Goeries informs on DAQ report: Last week run configurations were replaced; this week the new DAQ will run completely ON at SPB/SFX – if everything runs fine then MID will be updated next week
and others in cw15.
DA:
- Nothing to report.
EEE:
- Agreed to update tomorrow the SPB EPS.
VAC:
- Nothing to report.
XPD:
- Many studies were conducted; minor issues with calibration on XGM, but fixed;
- Diamond detector beamtime was successful.
DET:
- Nothing to report.
ITDM:
- Nothing to report.
XRO:
- All fine.
LAS:
- Nothing to report.
UNSYS:
- SA1 cell 25 need replace terminal on undulator control rack - needs ZZ.
- Communication between undulator server to DOOCS is problematic for last cells (from 31) in SA1.
SPB:
- Issue with AGIPD 1-M Julabo chiller which does not work; needs TS.
FXE:
- A ticket for the Data groups for DAQ is sent.
MID:
- All fine.
HED:
- Preparing for next experiment. New DAQ with half upgrades are installed and will be running the whole week.
SCS:
- Nothing to report.
SQS:
- Nothing to report.
SXP:
- Not present. |