Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther, Page 6 of 29  Not logged in ELOG logo
New entries since:Thu Jan 1 01:00:00 1970
Entry   Notes XO Integration Meeting 13.12.2023, posted by Frederik Wolff-Fabris on 13 Dec 2023, 10:04 
General Announcement:
-	 

CTRL:
- Few hiccups happened last days: 
1. SA3 Karabo topics required full restart of the topic due to hardware failure of the new broker; 
2. Network failure affecting communication between SA3 topic and broker. After a restart of topic, it runs well; 
3. Issue with communication between Karabo and PLC loops in SA2. It is solved but not fully understood yet.

DA:
- Nothing to report.

EEE:
- Fast electronics team finished the uTCA updates; from PLC side the mentioned problem by CTRL is solved and PLC system is stable; regular updates are continued.

VAC:
- Nothing to report.

XPD:
- Works are ongoing: SA1 PES detectors were tested and seem fine; work in HIREX is ongoing.

DET:
- Nothing to report.

ITDM: 
- Fast switch for SA2 was delivered yesterday and today ITDM will mount and configured it to be installed.

XRO:
- Not present.

LAS:
- Nothing to report.

UNSYS:
- Installation of Apple-X: all 4 devices are in place and cabling is ongoing. The first segment shall be controllable this afternoon.
- Update on problems with SA2/cell37: yesterday it was figured out that an encoder is damaged, which sits near from the new absorber. 
Encoder needs to be replaced but one does not have time and human power to do it during the WMP. Exchange will be done during the next Summer maintenance. Also Desy-VAC does not have Pb material to shield 
the absorber in the next 6 months. 
An alternative for this undulator is to control it with the rotary encoders in the meantime.

SPB:
- Nothing to report.

FXE:
- Nothing to report.

MID:
- All fine at MID.

HED:
- Not present.

SCS:
- Working with planned activities.

SQS:
- Nothing to report.

SXP:
- Not present.
Entry   Notes XO Integration Meeting 11.12.2023, posted by Frederik Wolff-Fabris on 11 Dec 2023, 09:51 
General Announcement:
-	 

CTRL:
- Last week updates on Karabo were done. Please check systems for functionality.
- Another update of data loggers will be done in coming days.

DA:
- Following the Karabo updates DA is checking their devices.

EEE:
- Suffering from illnesses in the group: colleagues that are not sick try to get all work done but some delay in some activities is expected in some areas;
- Also Wille company is suffering with sickness and they try to find substituted colleagues.
- Vacuum updates were fixed; plan to update of SA2 VAC was postponed from Friday to today.

VAC:
- Nothing to report.

XPD:
- Request to EEE when updates for XGM are to start, please inform Florian Dietrich and Jan Gruenert for that they prepare beforehand. After update is done one needs to restart vacuum and XGM.

DET:
- AGIPD at SPB/SFX intervention: replaced all modules; three attempts were needed and the situation is that detector is fully operational and all modules are working. 
Also tests after Karabo deployment worked nicely. Next is a test with DAQ and everything looks very promising.
- At MID AGIPD: Bias issue is also fixed; tested at real conditions went successful. Cause was a wire.

ITDM: 
- Most of the activities are done.
- Problem with exchange of switch in SA2 for DAQ collection: power supply had a problem but not only it, so new chassis will be delivered and needs to be replaced. DAQ connections for SA2 is not working.

XRO:
- Planned works are continuing and everything is going fine.

LAS:
- Nothing to report.

UNSYS:
- More two last Apple-X are being installed; from today Beckhoff technicians will connect the cabling.
- Issues with encoders are solved (radiation damage). Replacement was done and calibration was successful.

SPB:
- Nothing to report.

FXE:
- Nothing to report.

MID:
- Nothing to report.

HED:
- Not present.

SCS:
- Nothing to report.

SQS:
- Nothing to report.

SXP:
- Not present.
Entry   Notes XO Integration Meeting 06.12.2023, posted by Frederik Wolff-Fabris on 06 Dec 2023, 09:49 
General Announcement:
- Jan Gruenert announces a seminar done by UK guests from Daresbury on UK plans for FEL. The seminar happens on THU 13:30 at XHQ E2.042. Please contact Jan G. for zoom link.

CTRL:
- Few hiccups when performing Monday's update was done: restarted system again and fixed now.
- HED had also an issue with router but was understood and fixed.
- Performed SA1 update and today continuing with SA2 and tomorrow SA3 topics.

DA:
- Nothing to report.

EEE:
- Doing updates in SA1 tunnel PLC updates today.
- Affected by personal missing due to sickness.

VAC:
- Maintenance activities are ongoing.

XPD:
- Tasks progressing as scheduled.

DET:
- Nothing to report.

ITDM: 
- Routers update were done on Monday and Tuesday. They are operational and connected - looks successful.
- HED problem with a faulty connection/switch but for the time been it shall be fine.

XRO:
- Nothing to report.

LAS:
- Issue after Karabo update: can not instantiate and restart system; CTRL received a ticket and is looking into it.

UNSYS:
- Fixed problem with broken encoders in tunnels; calibration of cam movers was successful and is ready to install Apple-X; broken connector was found but reason for this happen still under investigation.
- First 2 Apple-X will be installed Thursday.
- Next 2 Apple-X to be moved to shaft building on Friday and installed on Monday.

SPB:
- Issue after power maintenance last week: downstream control room and experimental hutch does not have power in some white/orange sockets; A ticket to TS was written.

FXE:
- Nothing to report.
- Electronics rack room were switched ON now.

MID:
- All fine at MID.

HED:
- Nothing to report.

SCS:
- Not present.

SQS:
- Nothing to report.

SXP:
- Not present.
Entry   Notes XO Integration Meeting 04.12.2023, posted by Frederik Wolff-Fabris on 04 Dec 2023, 09:52 
General Announcement:
-	 

CTRL:
- E-mail sent this morning to xo-info for Karabo and CTRLs maintenance starting today.

DA:
- Nothing to report.

EEE:
- Personnel is affected by Covid-19 sickness; task schedules may be affected as well.

VAC:
- Not present.

XPD:
- Tasks ongoing.

DET:
- AGIPD 1-M at SPB/SFX: 16 modules were replaced but 1 is not working and new intervention has to be made to exchange it;
- AGIPD at MID with 2 modules problems: inspected by Desy colleagues and found the problem with wire, that was fitted and now is fixed and working again.

ITDM: 
- Starting today with maintenance: CTRL network replacement starting today
- Please expect until 6PM today that connection breaks may happen

XRO:
- Replacing Mono component at SA2 tunnel; needs Karabo to conclude when service is back.

LAS:
- Nothing in terms of unexpected issues.
- Last Thursday it was difficult to find when power went back (lost 4hs)
- SA3 shutdown due to fire alarm: needs feedback from SRP.

UNSYS:
- Two Apple-X undulators are in shaft building and preparing for installation; Today alignment of PS vacuum chambers; 
- Affected by sick leave as well as from sickness in Desy transport group.
- Two encoders are damaged in the cam movers below one Apple-X. In contact with Bekhoff; maybe delay can be expected.

SPB:
- Nothing to report.

FXE:
- Not present.

MID:
- Not present.

HED:
- Nothing to report.

SCS:
- Nothing to report.

SQS:
- Nothing to report.

SXP:
- Not present.
Entry   Notes XO Integration Meeting 29.11.2023, posted by Frederik Wolff-Fabris on 29 Nov 2023, 09:43 
General Announcement:
-  Please remember and remind group members that the machine day is on Tuesdays and not Mondays anymore. Delivery will then start on Wednesday.
- Regarding the 2025 shutdown at the 2nd half of the year: XO is collecting initial tasks. Please groups are asked to provide a draft to XO of the planned tasks by next Friday 01.12.
- The UOM does not take place next Friday.

CTRL:
- From next week the deployment of Karabo will start. E-mail with reminders will be sent.

DA:
- Nothing to report.
EEE:
- Power OFF in SA1 instruments; PLC colleagues will read all parameters beforehand to be in safe side. PLC will be down on Thursday.
- Learn that cooling in SA1 rack rooms will be OFF tomorrow. Does it affect balcony room? Tobias C. will verify with Oleg E. to check with company performing the job.

VAC:
- V0 valves are closed; also to the instruments. 
- Photon tunnels XTD6 and XTD9 will be opened in 30mins and XTD10 will be accessible after lunch.

XPD:
- Tests with IMGs are ongoing for the next 1-2 hours and need motors running. Please do not shutoff Karabo, racks until it is done.

DET:
- Yesterday started the AGIPD maintenance at SPB/SFX. Modules were exchanged together with Desy group. Today test of vacuum and temperature to be done;
- AGIPD at MID: Desy team will inspect it from today.

ITDM: 
- Planned tasks starting from next week.
- Tomorrow's electricity maintenance in SA1 - not clear who is responsible to open the racks door (ITDM, room manager or rack manager). To be clarified by TS and T. Clever.

XRO:
- Ramp down went fine last two days and thanks for the collaboration among the people.

LAS:
- Nothing to report.

UNSYS:
- Two problems in SA3 and SA2 will be fixed in the maintenance.
- Other tasks are ongoing accordingly to the plan.

SPB:
- Small issue with PLC but it was solved.

FXE:
- Nothing to report; preparing for the electricity task tomorrow.

MID:
- Nothing to report apart of the AGIPD.

HED:
- Not present.

SCS:
- Nothing to report.

SQS:
- Nothing to report.

SXP:
- Not present.
Entry   Notes XO Integration Meeting 27.11.2023, posted by Frederik Wolff-Fabris on 27 Nov 2023, 09:39 
General Announcement:
- User operation finished this morning 7AM for the year.
- Reminder that WMP starts on Thursday. Possible photon tunnels open on Wednesday but this still to be confirmed and e-mail will be sent.

CTRL:
- Nothing to report.

DA:
- Nothing to report.

EEE:
- Nothing to report.

VAC:
- Nothing to report.

XPD:
- Nothing to report.
DET:
- AGIPD at MID: issue on weekend with the bias motion. The power system for high voltage was changed but it did not cure the system. 
Further investigation with the modules will happen during the WMP. MID managed to finish the beamtime.

ITDM: 
- GPFS issue reported by DRC on Friday: happened only one time and did not repeat.

XRO:
- Not present.

LAS:
- Nothing to report.

UNSYS:
- Remind SA3 and SA2 problems (needs ZZ): BKR will continue working and during the WMP it will be fixed.

SPB:
- Pointing/jitter issue reported by Adam R. on E-log: Romain Letrun reports that is was a drift but not much different from usual behavior and not a real problem.

FXE:
- Nothing to report.

MID:
- Could run 2 AGIPD modules during the weekend.

HED:
- Not present.

SCS:
- Nothing to report.

SQS:
- Nothing to report.

SXP:
- Not present.
Entry   Notes XO Integration Meeting 22.11.2023, posted by Frederik Wolff-Fabris on 22 Nov 2023, 10:39 
General Announcement:
-	 

CTRL:
- Nothing to report.

DA:
- Issue reported on darks processing failure for data processing (Maxwell processes); ITDM and Desy is following.

EEE:
- Nothing to report.

VAC:
- Nothing to report.

XPD:
- Nothing to report.

DET:
- Nothing to report.

ITDM: 
- Nothing to report;
- Afternoon DOC member will look into ITDM reported issue.

XRO:
- Nothing to report; As PRC Maurizio says all fine.

LAS:
- Michael P. says a meeting with company is taking place and news will be brought to LAS.

UNSYS:
- SA3 cell 2 power terminal distribution has to be exchanged in ZZ;
- SA2 cell 37 problem with quadrupole mover in error state and top girder driver.

SPB:
- Thanks to SCS for helping with the chiller.

FXE:
- Nothing to report.

MID:
- Not present.

HED:
- Chamber contamination issue reported on Monday is closed. No contamination happened.

SCS:
- Nothing to report.

SQS:
- Nothing to report.

SXP:
- Not present.
Entry   Notes XO Integration Meeting 20.11.2023, posted by Frederik Wolff-Fabris on 20 Nov 2023, 10:01 
General Announcement:
-	 

CTRL:
- Nothing to report.

DA:
- Nothing to report.

EEE:
- Nothing to report.

VAC:
- Nothing to report.

XPD:
- Nothing to report.

DET:
- AGIPD SPB still offline with issues on Julabo chiller.
- Adam R. adds the AGIPD is not mandatory for the coming week of operation. Jola S.-D. adds they are in touch with SPB and the issue will be further investigated after run is ended. 
In addition, AGIPD is let out of beam for this week's operation.

ITDM: 
- Nothing to report.

XRO:
- Nothing to report.

LAS: 
- Fire alarm on Friday brought down all Lasermet systems (SA3 PP-laser and E.0 systems). Needs further investigation. PP-L is not needed for the current week.
- Fire alarm was due to smoke detectors triggering it accidentally

UNSYS:
- Nothing to report.

SPB:
- Nothing to report.
- Adam R. adds AGIPD detector may not be needed this week but it is good for checking.

FXE:
- Affected by fire alarm (timing sync down).

MID:
- Nothing to report.

HED:
- Experiment with PP-laser on Sat night faced a drop in pp-laser energy (not clear from LAS why);
- Users using hazards samples let contamination at chamber. Needs to be addressed with SRP.
- Covid-19 impacted personnel.

SCS:
- Nothing to report.

SQS:
- Since laser went down, the R&D was impacted.

SXP:
- Not present.
Entry   Notes XO Integration Meeting 15.11.2023, posted by Frederik Wolff-Fabris on 15 Nov 2023, 09:48 
General Announcement:
- As PRC, A. Galler informs the machine runs without major issues but kicker adaptation has difficulties with 4.5MHz. For the next 20 mins machine colleagues will introduce stronger kickers and during 
this time beam will be jittery at SA1/SA3. SA2 shall be unaffected. 
During the meeting PRC received a call from BKR informing the intervention was done at 09:45 and stable beam is currently available.
- Martin Doering announces on the Winter Maintenance period: 
1. The release of Maintenance Task List will happen tomorrow 16.11 and maintenance starts on 30.11; 
2. Major topics: 
Karabo (4-7.12 and 13.12), 
DAQ and CTRL network interruptions (4-8.12), 
Cooling water has no big interruptions planned apart of the regular maintenance with fluctuations in flow and temperature, 
Electrical maintenance in XHQ (4-22.12) with rooms affected in different days, 
electrical maintenance at XHEXP1 in 27.11-22.12, 
Timing missing, smoke detector tests, laser interlock upgrades, 
interlock test "light" (17.01); 
3. Please check for precise dates on above at the Maintenance Task List.

CTRL:
- No announcements for CTRL.

DA:
- Nothing to report.

EEE:
- Nothing to mention.

VAC:
- Nothing to report.

XPD:
- Nothing to report.

DET:
- Nothing for DET and for DRC (Monica T.).

ITDM: 
- Nothing to report.

XRO:
- Nothing to report.

LAS:
- Nothing to report.

UNSYS:
- Nothing to report.

SPB:
- Nothing to report apart of the Kicker issues.

FXE:
- Issues with Kicker as mentioned by the PRC.

MID:
- Nothing to report.

HED:
- Nothing to report. Tomorrow the switch to 24keV will take place and time has to be allocated for tuning.

SCS:
- Nothing to report.

SQS:
- Nothing to report.

SXP:
- Not present.
Entry   Notes XO Integration Meeting 13.11.2023, posted by Frederik Wolff-Fabris on 13 Nov 2023, 10:16 
General Announcement:
- This and next week of operation are the last 2 delivery weeks, which are done with 4.5MHz base rep rate. 

CTRL:
- Announcement: today IT will make an intervention in one of the hosts (204) for the DOOCS topic; downtime is expected and colleagues using cloning devices in this host (DOOCS requester to clone DOOCS) 
have to be refreshed and restarted.

DA:
- Nothing to report.

EEE:
- Incident that SCS motor not correctly moving during the weekend. PLC-OCD could not be reach due to phone issues; issue with motor was solved

VAC:
- ZZ on Thursday in XTD2 to exchange turbo pump was successful.

XPD:
- SA1 studies with 1nC was done in SA3 and not in SA1;
- 30keV went well on Wednesday but with Nepal-X no lasing was found on Friday.

DET:
- Nothing to report.

ITDM: 
- Nothing to add apart of CTRL report. An e-mail will be sent when it is done.

XRO:
- A. Trapp says the issue with SA2 motors moving slowly was fixed now after a patch was deployed.

LAS:
- Nothing to report.

UNSYS:
- ZZ last week for SA1 cell20 PS motor being replaced (damaged encoder). Many spare encoders are in house.

SPB:
- Nothing to report.

FXE:
- Preparing for in-house experiment.

MID:
- All fine at MID.

HED:
- 2 experiments this week at 18 and 24keV.

SCS:
- Not present.

SQS:
- Nothing to report.

SXP:
- Preparing experiments at 4.5MHz.
Entry   Notes XO Integration Meeting 08.11.2023, posted by Frederik Wolff-Fabris on 08 Nov 2023, 09:55 
General Announcement:
-	 

CTRL:
- Nothing to report.

DA:
- Nothing to report.

EEE:
- Nothing to report.

VAC:
- As PRC, Raul V. informs on a small issue at Hirex-Gotthard with number of pulses yesterday. Promptly solved in few minutes.

XPD:
- No issues and supporting the ongoing blue week with 30keV in SA2.
- Access happened on Monday in XTD2 to fix the solid attenuator.

DET:
- Nothing to report.

ITDM: 
- Monday intervention (announced in e-mail to xo-info) went OK and systems are recovered.

XRO:
- Solid Attenuator in SA1 temporarily solved: middle layer device calculating transmission shall be working; the automatic interlock is not yet working and a new interlock logic will be deployed. 
Please instruments in SA1 do that manually. Arm 5 and Arm 4 are currently disabled. 

LAS:
- Issue with 4.5MHz operation in SA3 but it was fixed.

UNSYS:
- SA1/cell20 phase shifter shows a problem and a ZZ will happen tomorrow morning.

SPB:
- Laser interlock issue happening yesterday evening was solved (signal of a power glitch happened yesterday evening).

FXE:
- Nothing to report.

MID:
- Seems that short pulses studies at MID were successful.

HED:
- Nothing to report.

SCS:
- Nothing to report.

SQS:
- Nothing to report.

SXP:
- Nothing to report.
Entry   Notes XO Integration Meeting 06.11.2023, posted by Frederik Wolff-Fabris on 06 Nov 2023, 09:53 
General Announcement:
- As PRC, Jan G. reports that on Saturday morning no beam permission at the North branch happened. An issue with XTD2 solid attenuator vacuum happened and together with VAC-OCD the threshold was changed 
to allow continuation of beam delivery. A ZZ will be needed today to fix the vacuum leak; 
On Sunday around 09:20 an issue with accelerator quadrupole magnet in A21 caused downtime initially until noon (SA2) and around 16:00 (North branch); also D3 had to come onsite to reset burn through 
monitors in the aftermath.

CTRL:
- Nothing to report.
DA:
- Nothing to report.
EEE:
- MID had couple of uTCA cards offline that needs to be rebooted. This will be discussed with MID offline.

VAC:
- Preparing for the needed ZZs in XTD2.

XPD:
- Nothing to report.

DET:
- Couple of tasks for the DSSC (SQS) to reconfigure the detector;
- DAQ of DSSC was affected by failure of GPFS servers.

ITDM: 
- GPFS issue happened last Friday and was fine over the weekend.
- An update of the clients will happen today in all SASEs. This was agreed with instruments.

XRO:
- Nothing to add to what was reported by the PRC.

LAS:
- SA2 issue with pulse on demand will be discussed with MID.

UNSYS:
- Nothing to report.

SPB:
- User beamtime went OK even with downtimes during weekend.

FXE:
- Nothing to report; last night shift (Sunday night) cancelled as program was finished on Saturday. 

MID:
- Supporting today the short pulses activities; from tomorrow interventions at MID can be scheduled.
- Regarding laser issue: when changing sequence for using Laser showed trains with pulses and trains with missing pulses. Running macro was changed for working to 1 pulse per second.
- Users were happy and the program was accomplished in full.

HED:
- Not present.

SCS:
- Detector tests to be done by end of the week.

SQS:
- Affected by beam losses but overall a lot of useful data was acquired.

SXP:
- Nothing to report.
Entry   Notes XO Integration Meeting 01.11.2023, posted by Frederik Wolff-Fabris on 01 Nov 2023, 10:04 
General Announcement:
- Jan G. as PRC comments: 1. reminds SQS and FXE instruments to place entries at the Operations e-log; 
2. machine is running well and ZZ accesses happened on Monday (hindered by issues with tunnel entrance) but all done; 
3. the XTD2 issue with upstream differential pump close to the XGM: one pump is defective and VAC will exchange if a ZZ is allowed next week.

CTRL:
- Nothing to report.

DA:
- Nothing to report.

EEE:
- FSSS motor in MID: OCD received a call yesterday and device was restarted and came back to operation.

VAC:
- Not present.

XPD:
- Nothing to report from XPD.

DET:
- Nothing to be reported.

ITDM: 
- Nothing to report.

XRO:
- On the XTD10 ZZ last Monday: V-slit was checked and a faulty cable for the encoder was found. For the time being this was fixed by tapping it and will continue monitoring.

LAS:
- Nothing to report.

UNSYS:
- All fine with Undulator.

SPB:
- Nothing to report.

FXE:
- Beam was not stable the last night / down for few times. To be investigated internally at FXE and reported to XO.

MID:
- Roll motor for M2 mirror at tunnel was moving very slowly; to be seen with XRO.

HED:
- Nothing to report.

SCS:
- Nothing to report; working in hutch preparations.

SQS:
- Nothing to report.

SXP:
- Not present.
Entry   Notes XO Integration Meeting 30.10.2023, posted by Frederik Wolff-Fabris on 30 Oct 2023, 09:47 
General Announcement:
-	 

CTRL:
- No announcements for today.

DA:
- Nothing to report.

EEE:
- Nothing to report.

VAC:
- Issue with turbo pump in XTD2 (happened 22:30 yesterday). Getting in touch the PLC team. Maybe a ZZ is needed today.

XPD:
- Nothing to report.

DET:
- Nothing to report.

ITDM: 
- Nothing to report.

XRO:
- Open points from last week: vertical slit SA3 bottom (error); SRA in SA1 is currently in error. To be followed up if fixed or not.

LAS:
- Nothing to report.

UNSYS:
- Yesterday night problems in SA1 (XTD2): cell 2 motor drive problems; cell 11 power distribution terminal in cabinet; cell 14 bridge terminal problem; errors from cell#31 to downstream segments.
- Yesterday night possible to bring system operational at night; ZZ is ongoing to address above points. Extension of time for ZZ is unclear.
- Problems with central control node also observed. 

SPB:
- Nothing to report.

FXE:
- Not present.

MID:
- Nothing to report.

HED:
- Beamtime good.

SCS:
- Nothing to report.

SQS:
- Nothing to report.

SXP:
- Saturday lost synchronization with both lasers: promptly solved by PRC and LAS-OCD.
Entry   Notes XO Integration Meeting 25.10.2023, posted by Andreas Galler on 25 Oct 2023, 09:26 

General Announcement:

  •  

CTRL:

  • nothing major --> a couple of people on vacation, i.e. issue repsonse time may be a bit longer this week

DA:

  •  

EEE:

  • nothing

VAC:

  • nothing

XPD:

  • nothing to report

DET:

  • nothing

ITDM: 

  • not present

XRO:

  • nothing

LAS:

  • nothing 
  •  

UNSYS: 

  • nothing to report

SPB/SFX:

  • SA3 background affecting focussing of x-rays

FXE:

  • smooth, beam instability yesterday
    • horizontal jitter entagled with PopIn measurements --> around lunch time
    • beam was clipping and LPD was seeing poweder scattering from the collimator pipe

MID:

  • nothing to report

HED:

  • Yesterday evening unexpected venting in the CRL3 (HED-Optics Hutch) --> X-ray Operation cancelled at least for Wed night
    •  

SCS:

  • beam instability in pointing over night
    • this cuased non optimal beam transport --> pulse energy decreased on sample

SQS:

  • nothing to report

SXP:

  • everything is looking 

DRC

  •  

PRC

  • SA1 pulse energy will be lower than possible, because of XGM settings that need to cater 7.8 keV and 12.5 keV
Entry   Notes XO Integration Meeting 23.10.2023, posted by Andreas Galler on 23 Oct 2023, 09:26 

General Announcement:

  •  

CTRL:

  • nothing major

DA:

  • nohting major

EEE:

  • nothing 

VAC:

  • nothing

XPD:

  • nothing major

DET:

  • nothing major

ITDM: 

  • nothing major

XRO:

  • nothing major

LAS:

  • SA3 PPLaser up and running
  • SA1 PPLaser went down from time to time
    • Windows PC crashed
    • instabilities in NOPA

UNSYS: 

  • Everything is fine

SPB/SFX:

  • SA1 PPLASER ISSUES

FXE:

  • Smooth

MID:

  • all fine

HED:

  • all fine

SCS:

  •  

SQS:

  • all good

SXP:

  • nothing 

DRC

  •  

PRC

  • 2 long down times over the weekend
    • from 7 to 12:30 fast valve in BC
    • Sun 10:30 - 19:00  broken network switch
Entry   Notes XO Integration Meeting 18.10.2023, posted by Frederik Wolff-Fabris on 18 Oct 2023, 10:01 
General Announcement:
- Next Friday 20th Oct. is the deadline for submitting the Winter maintenance task list back to XO.

CTRL:
- Nothing to report.

DA:
- Nothing major to report.

EEE:
- Nothing to report.

VAC:
- Nothing from VAC.
- As PRC, Martin D. informs on the issue with the Self-seeding monochromator: X-axis is not operational. A ZZ is needed today by UNSYS. To be seen the HXRSS program.

XPD:
- Not present.

DET:
- Nothing to be reported.
- Jungfrau calibration and DAQ: there is nothing more from DET to be done; P. Schmidt adds that operation modes have to be adapted and there is work on progress in long term.

ITDM: 
- Nothing to add.

XRO:
- Nothing to report.

LAS:
- Technician from AMPHOS arrived yesterday and work in ongoing with SA3 PP-laser; no final conclusion yet.

UNSYS:
- All day working with the SA2 monochromator yesterday (X-axis and roll axis). It looks the X-axis is stuck or broken and in a ZZ an attempt to recover with a manipulator will be done. 
Chances are not high for a fix and if the worst-case scenario, the HXRSS for the remaining of the year may be cancelled.

SPB:
- Nothing to report.

FXE:
- Nothing to report.

MID:
- Busy at beamline and worried with the HXRSS program.

HED:
- All fine at HED.

SCS:
- No outcome form PP-laser; getting a temporary laser from SXP (1030nm) and working to make it for the beamtime (no THz pump probe experiment will be possible).

SQS:
- Issue with digitizers (Smaract and PES); Being followed by EEE as was informed by DOC. For the PES it was discussed with XPD and needs further follow-up with SQS and XPD. 
In general, please contact DOC in case of operational issue or write EEE ticket if not an operational issue.
- High voltage power supply not responding at Karabo; being investigated by CTRL and will be coordinated with SQS for a fix.

SXP:
- Not present.
Entry   Notes XO Integration Meeting 16.10.2023, posted by Frederik Wolff-Fabris on 16 Oct 2023, 09:46 
General Announcement:
- Last X-ray delivery week went normal. 
- Friendly reminder for the submission of the maintenance task list on 20.10, next Friday. In case of questions please do not hesitate in contacting XO.

CTRL:
- Nothing to report.

DA:
- Nothing to report.

EEE:
- Nothing to report.

VAC:
- Nothing to report.

XPD:
- ZZ on XTD2 today at 13:00 to exchange XGMD amplifiers.

DET:
- Investigating the settings of detector with FXE.

ITDM: 
- Nothing to report.

XRO:
- Nothing to report.

LAS:
- SA3 AMPHOS engineer is at XFEL today. Intense work will be made to have PP-laser back by the end of the week - to be seen in coming hours/days.
- In SA1 PP-laser was recovered on Friday.

UNSYS:
- Nothing to report.

SPB:
- Nothing to report.

FXE:
- Nothing to report.

MID:
- Nothing to report.
- Naresh K. will interact with MID to align Hirex for the HXRSS operation this week.

HED:
- Nothing to report.

SCS:
- Needs PP-laser for the beamtime starting on THU.

SQS:
- SQS broke interlock at 6AM and took away beam permission.

SXP:
- Takes beam tomorrow and Wednesday; it will use another laser if SA3 PP-laser is not available.
Entry   Notes XO Integration Meeting 11.10.2023, posted by Frederik Wolff-Fabris on 11 Oct 2023, 10:15 
General Announcement:
- Reminder that next week, on 20.10, is the deadline to submit the Winter maintenance task lists to XO. In case of help, please contact Martin Doering at xo-planning@xfel.eu.

CTRL:
- Nothing to report.

DA:
- Nothing to report; all quiet at the DOC also.

EEE:
- Nothing to report.

VAC:
- Nothing to report.

XPD:
- Nothing to report.

DET:
- A Silicon oil leak at DET cleaning room happened: leak comes from Jungfrau cooling loop (built by external company); status is area was cleaned and leak point is being searched;
- AGIPD setup at SPB got a failure of Julabo chiller; it does not work properly and it does not cool as expected. Detector is interlocked and there was no problems for itself; to be further investigated.

ITDM: 
- Gitlab was down for about 30 mins and now is available again.

XRO:
- Nothing to report.

LAS:
- Status of SA3 PP-laser: still investigating and in contact with AMPHOS. Still to be seen.
- Smaract in SA2 is fixed.

UNSYS:
- All good.

SPB:
- Issue with AGIPD chiller. Installed yesterday mid-day and was cooling slowly but not reaching base temperature.

FXE:
- Handover laser to SQS.

MID:
- Nothing to report.

HED:
- Not present.

SCS:
- In contact with EEE (Bernard) regarding the commissioning of our additional local box for the THz experiment.

SQS:
- Not present.

SXP:
- Nothing to report; backlash of M6 seems to be fine.
Entry   Notes XO Integration Meeting 09.10.2023, posted by Andreas Galler on 09 Oct 2023, 09:23 

General Announcement:

  •  

CTRL:

  • nothing major 

DA:

  • nothing major 

EEE:

  • nothing major

VAC:

  • nothing major

XPD:

  • nothing
    •  

DET:

  • nothing

ITDM: 

  •  

XRO:

  • miror setup tuned for grazing incidence with high photon energy.
  • higher backlash at M6, XRO is monitoring this.

LAS:

  • SA2 treacy compressor  smaract stage not operational --> EEE informed
  • SA3 AMPHOS still suffering from low puse energy

UNSYS: 

  • gap scan
  •  

SPB/SFX:

  • nothing major

FXE:

  • nothing major

MID:

  • nothing to report

HED:

  • nothing to report

SCS:

  • no issues

SQS:

  • uTCA in rack room --> EEE will be informed
    • crate power cycled

SXP:

  • M6 backlash

DRC

  •  

PRC

  •  