Author: Frederik Wolff-Fabris 
Location: General 
Severity: Information 
Subject: Notes XO Integration Meeting 23.09.2024 
General Announcement:
-  As DRC, Krzysztof Wrona and Monica Turcato report all is fine at DOC, no major issues and no DRC calls overnight.

CTRL:
- Nothing to report.

DA:
- Nothing to report.

EEE:
- EEE is on retreat next Wed afternoon and entire Thursday.

VAC:
- Nothing to report.

XPD:
- Nothing to report.

DET:
- Nothing to report.
- Meeting ongoing on chiller issues together with TS, SPB/SFX.

ITDM: 
- Nothing to report.

XRO:
- Nothing to report.

LAS:
- Not present.

UNSYS:
- No news; all fine.

SPB:
- Issue with chiller is a treat to next experiments.

FXE:
- Problem with laser shutter (2-3x trigger interlock). 
- Pouneh S. asks which shutter closes: it's AMPHOS shutter.

MID:
- Nothing to report.

HED:
- Runs good with users.

SCS:
- Nothing to report.

SQS:
- Nothing to report.

SXP:
- Preparing for commissioning in cw41.