Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 539     Entry time: 14 Aug 2024, 09:44
Author: Frederik Wolff-Fabris 
Location: General 
Severity: Information 
Subject: Notes XO Integration Meeting 14.08.2024 
General Announcement:
- This morning difficulties to switch to SA2 9keV SASE happen but right now it is working for delivery to HED.
- Eric Boyd informs D3 would like to access an optical hutch to test insert for BTM on next Tuesday. An e-mail will be sent to xo-info mailing list asking for an instrument to open one optics hutch. 

CTRL:
- Nothing to report.

DA:
- Nothing to report.

EEE:
- Nothing to report.

VAC:
- Nothing to report.

XPD:
- Nothing to report.

DET:
- Issue with chiller at SPB/SFX for AGIPD which does not maintain temperature. Investigation shows it is a cooling water flow so T is not stable; 
Issue started after LOOP5 upgrade but seems to be coincidence. Solution still pending, maybe an installation of a new pumping system will happen.

ITDM: 
- Not present.

XRO:
- Not present.

LAS:
- Nothing to report.

UNSYS:
- Everything is fine; HXRSS 2nd crystal is now retracted in parking position.

SPB:
- Nothing apart of the AGIPD issue.

FXE:
- Nothing to report.

MID:
- Nothing to report.

HED:
- Not present.

SCS:
- Not present.

SQS:
- Not present.

SXP:
- Not present.