SASE1 Status and SASE3 Readiness
|
Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther |
Not logged in |
|
|
Message ID: 539
Entry time: 14 Aug 2024, 09:44
|
Author: |
Frederik Wolff-Fabris |
Location: |
General |
Severity: |
Information |
Subject: |
Notes XO Integration Meeting 14.08.2024 |
|
|
General Announcement:
- This morning difficulties to switch to SA2 9keV SASE happen but right now it is working for delivery to HED.
- Eric Boyd informs D3 would like to access an optical hutch to test insert for BTM on next Tuesday. An e-mail will be sent to xo-info mailing list asking for an instrument to open one optics hutch.
CTRL:
- Nothing to report.
DA:
- Nothing to report.
EEE:
- Nothing to report.
VAC:
- Nothing to report.
XPD:
- Nothing to report.
DET:
- Issue with chiller at SPB/SFX for AGIPD which does not maintain temperature. Investigation shows it is a cooling water flow so T is not stable;
Issue started after LOOP5 upgrade but seems to be coincidence. Solution still pending, maybe an installation of a new pumping system will happen.
ITDM:
- Not present.
XRO:
- Not present.
LAS:
- Nothing to report.
UNSYS:
- Everything is fine; HXRSS 2nd crystal is now retracted in parking position.
SPB:
- Nothing apart of the AGIPD issue.
FXE:
- Nothing to report.
MID:
- Nothing to report.
HED:
- Not present.
SCS:
- Not present.
SQS:
- Not present.
SXP:
- Not present. |