ID |
Date |
Author |
Location |
Severity |
Subject |
645
|
10 Sep 2025, 10:31 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 10.09.2025 | General Announcement:
- M. Doering announces on the LIMP-25:
1. XTD10 Scaffolding is installed for cabling work in October;
2. PLC updates: remaining work in tunnels to be done next week (discussed with VAC and XPD) as well as at SQS;
3. Update task list: M. Doering will send to the groups the Task list for that it is updated accordingly to the latest status (e.g. completed, cancelled, delayed...);
4. Recurring tasks for the Winter Maintenance will be planned for the end of the year. A list will be sent to the groups and please inform XO if you have new activities to be done before 2026.
CTRL:
- Karabo upgrade: start with MID next week to spot possible issues. MID topic will be accessible from the hutch only.
DA:
- Nothing to report.
EEE:
- PLC updates: see above.
VAC:
- Everything progressing well in XTD6 also with PLCs.
XPD:
- Nothing to report.
DET:
- Nothing to report; starting AGIPD at MID before Karabo is down in October.
ITDM:
- Nothing to report.
- Fast-X gateway upgrade last week is done.
XRO:
- Busy with SA1 activities.
LAS:
- Not present.
UNSYS:
- Delays with water and cable from Desy groups; but all ongoing.
SPB:
- Not present.
FXE:
- Nothing to report.
MID:
- MID control room is very warm: needs to check temperatures in control room; Gerd W. says technical infrastructure needs to be modified.
HED:
- Nothing to report.
SCS:
- Issue with installation of beam stop and AIBS position.
SQS:
- Not present.
SXP:
• Not present. |
648
|
15 Sep 2025, 09:45 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 15.09.2025 | General Announcement:
- On the LIMP25, no news apart of what was mentioned last week by Martin Doering (see 10.09 minutes)
- Inaki de Diego informs that AIBS and airboxes installation is completed, with the exception of HED, where there is a problem with a cable (or connector) that needs to be
fixed by MPS during the next days.
It will be confirmed when fixed/done.
CTRL:
- Today proceed with test deployment at MID.
DA:
- Nothing to report.
EEE:
- PLC team starting to replace the PLC CPUs with SA1 after agreement with instruments.
VAC:
- Not present.
XPD:
- Nothing to report.
DET:
- Nothing to report.
ITDM:
- Nothing to report.
XRO:
- Nothing to report.
LAS:
- Not present.
UNSYS:
- All proceeding and the hardware is prepared; only waiting for construction/MEA work.
SPB:
- Nothing to report.
FXE:
- Thanks to Hall crew who helped with craning.
MID:
- All fine; Temperature in the control hutch to be addressed today.
HED:
- Not present.
SCS:
- Not present.
SQS:
- Nothing to report.
SXP:
- Nothing to report. |
Draft
|
30 Mar 2020, 08:57 |
Andreas Galler | | | | CTRL:
- Broker Pile Up in 4 topics over the weekend
- LAS affected in all topics, LA2 even twice
- SPB affected once
- mitigation startegy worked
EEE:
VAC:
nothing to report
XPD
- vac systems in the lab had been secured --> secuvac valves installed plus webcams
DET:
ITDM:
- exflgateway hardware problem on Saturday --> fixed
XRO:
SPB:
- rough pump turned off, possibly lack of cooling water
- interlock tripped --> pressures raised
- were able to set remotely
FXE:
MID:
HED:
- VAC is fine, ion pumps are on, no roughing pumps running
DA:
|
|