General Announcement:
- M. Doering announces on the LIMP-25:
1. Pressurizer exchange is postponed from today to a date likely in two weeks, to be informed;
2. Magnet cabling in XTD10 starts on Wednesday and pre-absorber work must finish before (see VAC/XRO);
3. News on timing system (see EEE).
CTRL:
- Preparing for Karabo3 rollout as scheduled.
DA:
- Nothing to report.
EEE:
- Update of timing system is scheduled for today after lunch. Groups are informed.
- PLC side: SPB and MID tests are ongoing.
VAC:
- XTD10 pre-absorber works: XPD part is done and VAC has to extract the pre-absorber and seal the vacuum, no issues to do in the next two days to avoid collision with magnet cabling.
XPD:
- Nothing to report.
DET:
- Nothing to report.
ITDM:
- Nothing to report.
XRO:
- Nothing to report; pre-absorber work is ongoing well.
LAS:
- Nothing to report; no collisions with timing update.
UNSYS:
- Nothing to report.
SPB:
- Nothing to report.
FXE:
- Nothing to report.
MID:
- All fine at MID.
HED:
- Nothing to report.
SCS:
- Nothing to report.
SQS:
- Nothing to report.
SXP:
- All fine at SXP. |