General Announcement:
- M. Doering announces on the LIMP-25:
1. Karabo deployment ongoing;
2. PLC updates see works at FXE, HED for next week cw42 (SQS later time);
3. Central gas management will be implemented by TS - Tobias Clever informs that since yesterday company is onsite for programming the system changes. For the next couple of days
a short interruptions of gases bottles may happen and to be finished by the end of next week.
- On Monday M. Doering sent an e-mail regarding the next Winter maintenance "light" for recurring activities that always happens during a regular winter maintenance.
If groups have new tasks (unknown by the planning phase of the LIMP) that shall be done prior the start of operation, please let M. Doering know, especially if may affect other
groups.
For example, emergency OFF will be triggered in SA1 and SA2 instruments as well as cooling water will be interrupted for one day.
CTRL:
- Proceeding with Karabo updates.
DA:
- Nothing to report.
EEE:
- Timing system update happening at SA3 instruments today.
VAC:
- Not present.
XPD:
- Nothing to report.
DET:
- Nothing to report.
ITDM:
- Nothing to report.
XRO:
- Everything fine; yesterday the work in pre-absorber was finished well.
- This week the pre-alignment of ODL in SA3 is planned to be finished and then Vacuum can be closed.
LAS:
- Nothing to report.
UNSYS:
- Nothing to report.
SPB:
- Nothing to report.
FXE:
- Nothing to report.
MID:
- Nothing to report.
HED:
- Not present.
SCS:
- Next week works on the hutch will be made by an external company (area to be fenced). Please contact Jan Torben if access is needed.
SQS:
- Not present.
SXP:
- Nothing to report. |