Subject: Notes XO Integration Meeting 01.10.2025 
General Announcement:
- M. Doering announces on the LIMP-25 for next week: 
1. PLC updates in SA2 and SA3 tunnels (HED postponed to later week); 
2. Karabo deployment happening (no availability); 
3. Timing system update on Tuesday from 09:00 to 16:00 with interruptions during this time; 
4. MKK maintenance on pressurizer for 8C water (e-mail to be sent - please avoid changes on cooling water on Monday); 
5. Magnet cabling in XTD10 starts on Wednesday 08.10.  
- M. Prollius says hot work permits are allowed again.
- I. de Diego says D3 will be testing AIBS / air boxes systems in SA3 experiments tomorrow (access is required).
- Nerea Jardon says please contact EEE if EEE systems need to be operated during the time Karabo is down.

CTRL:
- Preparing for Karabo3 rollout from today.

DA:
- Nothing to report.

EEE:
- Delay on PLC CPU replacement in tunnels: to be done after Karabo is back.
- Timing systems have to be updates - discussed with LAS already and fine with them. 

VAC:
- Everything fine.

XPD:
- Nothing to report.

DET:
- Nothing to report.

ITDM: 
- Long standing issue with SA2 storage system: needs to power cycle system probably tomorrow or Monday, when Karabo is anyway down.
- Update PCs in experiment Hall next week.

XRO:
- Not present.

LAS:
- Nothing to report.

UNSYS:
- Not present.

SPB:
- Nothing to report.

FXE:
- Nothing to report.

MID:
- Nothing to report.

HED:
- Nothing to report.

SCS:
- Nothing to report.

SQS:
- Not present.

SXP:
- Nothing to report.
ELOG V3.1.4-7c3fd00