Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther, Page 31 of 31  Not logged in ELOG logo
ID Date Author Locationdown Severity Subject Text Attachments
  605   16 Apr 2025, 09:33 Andreas GallerGeneralInformationNotes XO Integration Meeting 15.04.2025General Announcement:


 


CTRL:


nothing 


DA:
  
  606   23 Apr 2025, 09:27 Andreas GallerGeneralInformationNotes XO Integration Meeting 23.04.2025General Announcement:


 


CTRL:


guiserver at MID

backbone
  
  607   28 Apr 2025, 09:44 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 28.04.2025General Announcement:
- From PRC, Maurizio V. and Raul V. have
no new things to report, apart of the HXRSS
  
  608   30 Apr 2025, 10:12 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 30.04.2025General Announcement:
- Kimon F. informs that tests for a multi-mode
fiber communication in XTD4 have to be scheduled
  
  609   05 May 2025, 09:55 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 05.05.2025General Announcement:
-  
  
  610   07 May 2025, 09:50 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 07.05.2025General Announcement:
-  
  
  611   12 May 2025, 09:36 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 12.05.2025General Announcement:
- Successful delivery last days with exceptional
machine performance. From tomorrow we have
  
  612   14 May 2025, 09:39 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 14.05.2025General Announcement:
- As PRC, Jan Gruenert reports a problem
with fire detection system in XTD4 needed
  
  613   19 May 2025, 09:42 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 19.05.2025General Announcement:
- Harald Sinn inform on the first lasing
for XFELO on Sunday morning shift; 100 bunches
  
  614   21 May 2025, 09:36 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 21.05.2025General Announcement:
-  
  
  615   26 May 2025, 09:56 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 26.05.2025General Announcement:
- A. Galler mentions the V0 was operated
by another group after being interlock on
  
  616   28 May 2025, 09:42 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 28.05.2025General Announcement:
-  
  
  617   02 Jun 2025, 09:51 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 02.06.2025General Announcement:
- The ongoing delivery sees a HXRSS at 12GeV
with 1mJ total intensity (~350uJ background).
  
  618   04 Jun 2025, 09:44 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 04.06.2025General Announcement:
-  
  
  Draft   30 Mar 2020, 08:57 Andreas Galler   CTRL:


Broker Pile Up in 4 topics
over the weekend

LAS affected
  