Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 617     Entry time: 02 Jun 2025, 09:51
Author: Frederik Wolff-Fabris 
Location: General 
Severity: Information 
Subject: Notes XO Integration Meeting 02.06.2025 
General Announcement:
- The ongoing delivery sees a HXRSS at 12GeV with 1mJ total intensity (~350uJ background). 

CTRL:
- Nothing major to report.

DA:
- Nothing to be reported.

EEE:
- Nothing to report.

VAC:
- Not present.

XPD:
- No issues to report.
- Big brother stopped SA1 because of HIREX power limit: J. Gruenert reports that all pulses of the train are now being seen by Big Brother and things worked as expected.

DET:
- Nothing major to report.

ITDM: 
- Nothing to report.

XRO:
- Nothing to report.

LAS:
- Ticket was discussed for SPB (timing issues): under investigation and a bug on the code has been found and is under work.

UNSYS:
- Issue with PS in cell#8 in SA1 was already fixed remotely.

SPB:
- Two issues: 1. HIREX watchdog needs a change of filter then works fine; 2. Issue with sample delivery leads that SPB will not use beam tonight (FXE can take if wanted).
- uTCA tested a monitor for received timing info together with ITDM and this test was performed parasitically at SPB.

FXE:
- Nothing to report.

MID:
- Nothing to report.

HED:
- HXRSS performance this week is excellent.

SCS:
- Not present.

SQS:
- Nothing to report.

SXP:
- Not present.