|  Notes XO Integration Meeting 22.10.2025, posted by Frederik Wolff-Fabris on 22 Oct 2025, 09:47 | 
| General Announcement: 
 - M. Doering announces on the LIMP-25 for next week:
 | 
|  Notes XO Integration Meeting 20.10.2025, posted by Andreas Galler on 20 Oct 2025, 09:17 | 
| General Announcement: 
 
 the XO integration elog will move to Zulip / Metadata on Wednesday
 Martin updates
 
 humidity control in precision
 air conditioning is currently impeded due to a broken controller.
 Gas Monitoring System still out of service --> in case gases are needed
 | 
|  Notes XO Integration Meeting 15.10.2025, posted by Andreas Galler on 15 Oct 2025, 09:25 | 
| General Announcement: 
 
 Martin shows the preview for cw43
 
 Karabo 3 deploymebt ongoing
 Interruption of the main 1.3 GHz main referenfce
 
 Th.
 23.10.25 from 9:00 - 15:00 --> requests for standalone? if yes, please contact xo-planning@xfel.eu or M. Doering directly
 
 
 electrical
 | 
|  Notes XO Integration Meeting 13.10.2025, posted by Frederik Wolff-Fabris on 13 Oct 2025, 09:39 | 
| General Announcement: - Tobias Clever informs on the gas maintenance system: the central gas supply is currently disconnected;
 One shall not bypass it by installing other gas bottles as the gas monitoring alarm is not working and thus pose a safety threat if leakage happens.
 | 
|  Notes XO Integration Meeting 08.10.2025, posted by Frederik Wolff-Fabris on 08 Oct 2025, 09:45 | 
| General Announcement: - M. Doering announces on the LIMP-25:
 1. Karabo deployment ongoing;
 | 
|  Notes XO Integration Meeting 06.10.2025, posted by Frederik Wolff-Fabris on 06 Oct 2025, 09:45 | 
| General Announcement: - M. Doering announces on the LIMP-25:
 1. Pressurizer exchange is postponed from today to a date likely in two weeks, to be informed;
 | 
|  Notes XO Integration Meeting 01.10.2025, posted by Frederik Wolff-Fabris on 01 Oct 2025, 09:47 | 
| General Announcement: - M. Doering announces on the LIMP-25 for next week:
 1. PLC updates in SA2 and SA3 tunnels (HED postponed to later week);
 | 
|  Notes XO Integration Meeting 29.09.2025, posted by Frederik Wolff-Fabris on 29 Sep 2025, 09:50 | 
| General Announcement: - On the LIMP-25: the XS4 shaft building elevator is not working and repair is to be done. Please use other shaft buildings or ways when accessing SA2
 tunnel with equipment.
 | 
|  Notes XO Integration Meeting 24.09.2025, posted by Frederik Wolff-Fabris on 24 Sep 2025, 09:43 | 
| General Announcement: - Martin Doering announces for next week's LIMP-25:
 1. PLC updates to be continued in SA3 tunnels and instruments;
 | 
|  Notes XO Integration Meeting 22.09.2025, posted by Frederik Wolff-Fabris on 22 Sep 2025, 09:42 | 
| General Announcement: - Construction noises heard at XHQ 2nd floor comes from HXS works at the experimental Hall.
 - Tobias Clever: a power glitch was seen on Sunday around 17:00 and some pumps supplying cooling water to XHQ level 0 were affected; also ventilation at
 | 
|  Notes XO Integration Meeting 17.09.2025, posted by Frederik Wolff-Fabris on 17 Sep 2025, 09:40 | 
| General Announcement: - F. Wolff-Fabris comments on the LIMP-25: for cw38 schedule sees:
 1. the PLC updates as main activity;
 | 
|  Notes XO Integration Meeting 15.09.2025, posted by Frederik Wolff-Fabris on 15 Sep 2025, 09:45 | 
| General Announcement: - On the LIMP25, no news apart of what was mentioned last week by Martin Doering (see 10.09 minutes)
 - Inaki de Diego informs that AIBS and airboxes installation is completed, with the exception of HED, where there is a problem with a cable (or connector)
 | 
|  Notes XO Integration Meeting 10.09.2025, posted by Frederik Wolff-Fabris on 10 Sep 2025, 10:31 | 
| General Announcement: - M. Doering announces on the LIMP-25:
 1. XTD10 Scaffolding is installed for cabling work in October;
 | 
|  Notes XO Integration Meeting 08.09.2025, posted by Frederik Wolff-Fabris on 08 Sep 2025, 09:42 | 
| General Announcement: - Regarding LIMP-25, there is nothing different apart of what was already mentioned on Wednesday for this week cw37.
 
 | 
|  Notes XO Integration Meeting 03.09.2025, posted by Frederik Wolff-Fabris on 03 Sep 2025, 10:29 | 
| General Announcement: - LIMP-25: next week cw37 sees the PLC updates starting in SPB/SFX and SQS; also the re-installation of AIBS will be completed.
 
 | 
|  Notes XO Integration Meeting 01.09.2025, posted by Frederik Wolff-Fabris on 01 Sep 2025, 09:37 | 
| General Announcement: -  There are no general updates regarding LIMP-25.
 
 | 
|  Notes XO Integration Meeting 27.08.2025, posted by Andreas Galler on 27 Aug 2025, 09:30 | 
| General Announcement: 
 
 Martin shows the preview for cw36,
 
 Implementation of central gas management
 safety lights maintenance
 
 
 
 
 CTRL:
 
 
 nothing major
 
 
 DA:
 | 
|  Notes XO Integration Meeting 25.08.2025, posted by Andreas Galler on 25 Aug 2025, 09:28 | 
| General Announcement: 
 
 Martin Doering
 
 XTD6 today maintenance of cooling water pumps --> fluctuations can occur
 Safety: a couple
 of EPDs have not been logged out
 
 
 
 
 CTRL:
 | 
|  Notes XO Integration Meeting 20.08.2025, posted by Frederik Wolff-Fabris on 20 Aug 2025, 09:43 | 
| General Announcement: - Martin Doering announces on the LIMP-25 (Main infrastructure works are ending in general):
 1. Water related activities will be finished this week;
 | 
|  Notes XO Integration Meeting 18.08.2025, posted by Frederik Wolff-Fabris on 18 Aug 2025, 09:36 | 
| General Announcement: - O. Bilani informs transport and crane activities are being made at truck bay today. Please be careful when walking around.
 - M. Prollius informs on Wednesday afternoon the NDR is making footages at undulator tunnels, organized by COMS.
 |