Group Selection Page HELP DOC Controls Group Data Analysis Group ITDM WP76 DET Vacuum XRO EEE WP78 WP74 FXE SCS SPB MID HED SQS SXP Sample Environment Photon Commissioning Team Operation PSPO XO TS
Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther, Page 12 of 29  Not logged in ELOG logo
ID Date Author Location Severity Subject Text Attachments
  357   12 Sep 2022, 09:55 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 12.09.2022General Announcement:
- Machine tried the switch between 24 and
20keV at SA1 during the weekend: it was tuned
  
  356   07 Sep 2022, 10:43 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 07.09.2022General Announcement:
- With respect to the X-ray delivery parameters
table: it is pre-filled with parameters agreed
  
  355   05 Sep 2022, 10:07 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 05.09.2022General Announcement:
- If an instrument experiences a feature
of machine that does not work, please do
  
  354   31 Aug 2022, 10:16 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 21.03.2022General Announcement:
- Announcement from Martin Doering on the
next Winter maintenance period: 1. presented
  
  353   29 Aug 2022, 09:56 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 29.08.2022General Announcement:
- During the next Wednesday XO Integration
Meeting a kick-off presentation by Martin
  
  352   24 Aug 2022, 09:28 Andreas GallerGeneralInformationNotes XO Integration Meeting 24.08.2022

General Announcement:


 


CTRL:
  
  351   22 Aug 2022, 09:50 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 21.03.2022General Announcement:
- Power glitch on Saturday morning took two
cryo streets down and beam was recovered
  
  350   17 Aug 2022, 11:19 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 17.08.2022General Announcement:
-  Machine is currently set at 12 GeV to
best accommodate the requests for the next
  
  349   15 Aug 2022, 09:49 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 15.08.2022General Announcement:
-  On Saturday 4AM there was a very short
power glitch. Machine kept running and to
  
  348   10 Aug 2022, 09:56 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 10.08.2022General Announcement:
- Machine has restarted after the cryo failure:
SA3 is receiving photons and tuning in SA1
  
  347   08 Aug 2022, 09:54 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 08.08.2022General Announcement:
- The accelerator is down since Sunday morning.
An oil pump of the warm compressor failed
  
  346   03 Aug 2022, 10:10 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 03.08.2022General Announcement:
- Regarding the cw32 photon energies: it
is expected for 8 GeV to have up to 6keV
  
  345   01 Aug 2022, 10:02 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 01.08.2022General Announcement:
- Today the SEPS interlock tests take place
at all SASEs. This happens usually after
  
  344   25 Jul 2022, 09:14 Andreas GallerGeneralInformationNotes XO Integration Meeting 25.07.2022General Announcement:


 


CTRL:


Today "bring up"
  
  343   20 Jul 2022, 09:30 Andreas GallerGeneralInformationNotes XO Integration Meeting 20.07.2022

General Announcement:


none


CTRL:
  
  342   18 Jul 2022, 09:31 Andreas GallerGeneralInformationNotes XO integration meeting 18.07.2022

General Announcement:


none


CTRL:
  
  341   13 Jul 2022, 09:59 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 13.07.2022General Announcement:
-  Today and tomorrow the TUV / Interlock
tests are taking place. Emergency OFF are
  
  340   11 Jul 2022, 09:52 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 11.07.2022General Announcement:
-  User Operation Meeting will re-start on
cw30 (Friday 29.07).
  
  339   06 Jul 2022, 10:22 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 06.07.2022General Announcement:
- Interlock tests in tunnels start today
so there is no tunnel access today. Tests
  
  338   04 Jul 2022, 09:30 Andreas GallerGeneralInformationNotes XO Integration Meeting 04.07.2022

General Announcement:


M. Döring:

almost
  
ELOG V3.1.4-7c3fd00