Technical integration and coordination
SASE1 Status and SASE3 Readiness
|
Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther |
Not logged in |
|
|
Message ID: 430
Entry time: 28 Jun 2023, 10:22
|
Author: |
Frederik Wolff-Fabris |
Location: |
General |
Severity: |
Information |
Subject: |
Notes XO Integration Meeting 28.06.2023 |
|
|
General Announcement:
- PKG maintenance in SA1-2-3 areas (XHEXP1) is to take place today and fluctuations of temperature are to be expected.
- Please remember that from next Monday 03.07 access is to be done with the new transponder only.
CTRL:
- Karabo deployment done for instruments and SASE topics: couple of issues for LAS (Galvo device could not be started; dependence was then installed manually and is now fixed).
DA:
- Nothing to report.
EEE:
- Runs smoothly with activities; no issues were found so far.
VAC:
- Everything accordingly to the plan.
XPD:
- PES in SASE3 is repaired. No other issues for maintenance plans.
DET:
- Nor present.
ITDM:
- Status of storage: SA1 is up and running; SA3 storage had a hardware upgrade to new technology (old still available) and an e-mail will be sent to local contacts of proposals/users;
SA2 storage upgrade is ongoing and decision where to exchange hardware is to be made today.
XRO:
- Not present.
LAS:
- Galvo issue is solved.
- Other issues were also solved and good to go.
UNSYS:
- Ready with tunnel tasks.
- After replacing quad vacuum chamber in SA3 cell 22 and cell23: Desy vacuum group used a Pt-100 sensor installed and is limiting the travel range of the Quadrupole.
The range was measured and needs to be discussed with MXL if allows operation.
SPB:
- Not present.
FXE:
- Not present.
MID:
- Nothing to report.
HED:
- Everything on the track.
SCS:
- Not present.
SQS:
- Not present.
SXP:
- Not present. |