SASE1 Status and SASE3 Readiness Technical integration and coordination
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 420     Entry time: 22 May 2023, 10:00
Author: Frederik Wolff-Fabris 
Location: General 
Severity: Information 
Subject: Notes XO Integration Meeting 22.05.2023 
General Announcement:
-	 

CTRL:
- Nothing to report.

DA:
- Nothing to report.

EEE:
- OCD Call related to motors in SXP was addressed.

VAC:
- Nothing to report.

XPD:
- No issues on the week.
- Successful progress with measurements on Wavefront sensors.

DET:
- Nothing to report.

ITDM: 
- Nothing to report.

XRO:
- Commissioning of KB mirror at SXP worked well.

LAS:
- SA1 PP-laser is back but no yet at full power. Hopefully by evening will run at specs.

UNSYS:
- All fine with undulators systems.

SPB:
- Program with XPD went well.

FXE:
- Nothing to report.

MID:
- Issue with a motor; MID in contact with EEE.
- Collimator in tunnel was lifted by 5mm last week. 
M. Vannoni checked on the weekend and confirms the beam can move higher but another device is now blocking beam - still to be found which device.

HED:
- Nothing to report.

SCS:
- Nothing to report.

SQS:
- Nothing to report.

SXP:
- Commissioning KB mirror successfully.
- Two issues: 1. Motion middle layer device crashed; 2. Gas attenuator issues with changing attenuation (not properly working) @ 1keV photon energy. Contact to VAC will be done.
- Measurements of focus size with KB will be done by tomorrow.