General Announcement:
- Tobias Clever mentions that the tasks for the UPS repair is cancelled for the summer maintenance period.
CTRL:
- Not present.
DA:
- Nothing to report.
EEE:
- All fine with maintenance activities.
VAC:
- Everything works (more or less) accordingly to the plan
XPD:
- PES in XTD10 will be repaired today.
- Progressing accordingly to the plan.
DET:
- Nothing to report.
ITDM:
- E-mail was sent to xo-info on maintenance / updates of gateway and Maxwell for next Friday after lunch or around lunch time. In case of questions please contact ITDM.
- Today the new storage system is being moved. Old one still available and e-mail will be sent.
- Regarding online resources: essentially finished and DAQ will be brought back.
XRO:
- Going well but new activities appeared since last week, needing interaction with instruments:
- Solid attenuator in SA2: was decided to disable the arm; the other solid attenuator has the same problem – needs to be discussed with instruments.
- Accumulate issues with motors and findings are being sent to Bernard B. but contact to EEE will be done in order to speed up fixes due to the large amount of findings.
LAS:
- SA1 parameters are lost as well with network connections. ITDM will be contacted.
- Control and libraries are also having issues for Galvo system in SA1.
UNSYS:
- Pending task is the replacement of Almemo batteries in SA3. Other tasks are completed.
SPB:
- Not present.
FXE:
- Last week replacement of chamber was done, thanks to Janni E. from VAC to support.
MID:
- All well for the moment.
HED:
- Nothing to report.
SCS:
- Not present.
SQS:
- Nothing to report.
SXP:
- Nothing to report. |