Group Selection Page HELP Controls Group ITDM Vacuum WP78 SPB SQS XO ToBeMigrated2XWiki ToBeMigrated2GitlabPages ToBeMigratedByGroup Migrated2Zulip Archived2PDF not2MigrateOrArchive
SCS SXP Migrated2Zulip Photon Commissioning Team XRO DOC HED Migrated2Zulip WP74 MID PSPO_XO XO_Operation SQS Migrated2Zulip FXE Migrated2Zulip DET Sample Environment SPB Migrated2Zulip
SASE1 Status and SASE3 Readiness Technical integration and coordination
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 421     Entry time: 24 May 2023, 09:50
Author: Frederik Wolff-Fabris 
Location: General 
Severity: Information 
Subject: Notes XO Integration Meeting 24.05.2023 
General Announcement:
-	 

CTRL:
- Not present.

DA:
- Nothing to report.

EEE:
- Nothing to report.

VAC:
- Nothing to report.

XPD:
- Everything working fine.

DET:
- Not present.

ITDM: 
- Nothing to report.

XRO:
- Nothing to report.

LAS:
- PP-lasers are back and running. All fine.

UNSYS:
- Nothing to report.

SPB:
- Nothing to report.

FXE:
- Nothing to report.

MID:
- Issue with clipping the beam was found and relates to a combination of devices.
- Progress is being made for user experiment.

HED:
- Preparation for next week ongoing.
- Needs to get in contact with RCs for next Monday tuning.

SCS:
- Preparing the THz setup for beamtime.

SQS:
- Nothing to report.

SXP:
- Used beam yesterday for commissioning KB. 