Subject: Notes XO Integration Meeting 24.05.2023 
General Announcement:
-	 

CTRL:
- Not present.

DA:
- Nothing to report.

EEE:
- Nothing to report.

VAC:
- Nothing to report.

XPD:
- Everything working fine.

DET:
- Not present.

ITDM: 
- Nothing to report.

XRO:
- Nothing to report.

LAS:
- PP-lasers are back and running. All fine.

UNSYS:
- Nothing to report.

SPB:
- Nothing to report.

FXE:
- Nothing to report.

MID:
- Issue with clipping the beam was found and relates to a combination of devices.
- Progress is being made for user experiment.

HED:
- Preparation for next week ongoing.
- Needs to get in contact with RCs for next Monday tuning.

SCS:
- Preparing the THz setup for beamtime.

SQS:
- Nothing to report.

SXP:
- Used beam yesterday for commissioning KB. 