Technical integration and coordination
SASE1 Status and SASE3 Readiness
|
Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther |
Not logged in |
 |
|
Message ID: 436
Entry time: 19 Jul 2023, 10:25
|
Author: |
Frederik Wolff-Fabris |
Location: |
General |
Severity: |
Information |
Subject: |
Notes XO Integration Meeting 19.07.2023 |
|
|
General Announcement:
- SEPS interlock tests are done in SA1 and SA2. It continues tomorrow in SA3 during the morning.
- Machine accelerator startup is ongoing. Photons are being produced and operators are working hard to improve conditions.
- When summer maintenance started in mid-June some instruments' staff were entirely gone and none were available to open hutches, which delayed some tasks.
XO will have a look next maintenance into this issue.
CTRL:
- Proceeding with bring up days.
DA:
- Working on the bring up days.
EEE:
- Work with bring up days and support SEPS tests.
VAC:
- All normal with VAC systems.
XPD:
- Not present.
DET:
- Nothing to report.
ITDM:
- Nothing to report.
XRO:
- Starting today with ramp up.
- ZZ for M6 mirror in SA3 tomorrow morning.
LAS:
- Received report from Pouneh S. on the Lasermet events.
UNSYS:
- All fine.
SPB:
- Nothing to report.
FXE:
- Nothing to report.
MID:
- All fine at MID.
HED:
- Nothing to report.
SCS:
- Busy at beamline.
SQS:
- Not present.
SXP:
- Not present. |