Notes XO Integration Meeting 13.10.2025, posted by Frederik Wolff-Fabris on 13 Oct 2025, 09:39
|
General Announcement:
- Tobias Clever informs on the gas maintenance system: the central gas supply is currently disconnected;
One shall not bypass it by installing other gas bottles as the gas monitoring alarm is not working and thus pose a safety threat if leakage happens.
|
Notes XO Integration Meeting 08.10.2025, posted by Frederik Wolff-Fabris on 08 Oct 2025, 09:45
|
General Announcement:
- M. Doering announces on the LIMP-25:
1. Karabo deployment ongoing;
|
Notes XO Integration Meeting 06.10.2025, posted by Frederik Wolff-Fabris on 06 Oct 2025, 09:45
|
General Announcement:
- M. Doering announces on the LIMP-25:
1. Pressurizer exchange is postponed from today to a date likely in two weeks, to be informed;
|
Notes XO Integration Meeting 01.10.2025, posted by Frederik Wolff-Fabris on 01 Oct 2025, 09:47
|
General Announcement:
- M. Doering announces on the LIMP-25 for next week:
1. PLC updates in SA2 and SA3 tunnels (HED postponed to later week);
|
Notes XO Integration Meeting 29.09.2025, posted by Frederik Wolff-Fabris on 29 Sep 2025, 09:50
|
General Announcement:
- On the LIMP-25: the XS4 shaft building elevator is not working and repair is to be done. Please use other shaft buildings or ways when accessing SA2
tunnel with equipment.
|
Notes XO Integration Meeting 24.09.2025, posted by Frederik Wolff-Fabris on 24 Sep 2025, 09:43
|
General Announcement:
- Martin Doering announces for next week's LIMP-25:
1. PLC updates to be continued in SA3 tunnels and instruments;
|
Notes XO Integration Meeting 22.09.2025, posted by Frederik Wolff-Fabris on 22 Sep 2025, 09:42
|
General Announcement:
- Construction noises heard at XHQ 2nd floor comes from HXS works at the experimental Hall.
- Tobias Clever: a power glitch was seen on Sunday around 17:00 and some pumps supplying cooling water to XHQ level 0 were affected; also ventilation at |
Notes XO Integration Meeting 17.09.2025, posted by Frederik Wolff-Fabris on 17 Sep 2025, 09:40
|
General Announcement:
- F. Wolff-Fabris comments on the LIMP-25: for cw38 schedule sees:
1. the PLC updates as main activity;
|
Notes XO Integration Meeting 15.09.2025, posted by Frederik Wolff-Fabris on 15 Sep 2025, 09:45
|
General Announcement:
- On the LIMP25, no news apart of what was mentioned last week by Martin Doering (see 10.09 minutes)
- Inaki de Diego informs that AIBS and airboxes installation is completed, with the exception of HED, where there is a problem with a cable (or connector) |
Notes XO Integration Meeting 10.09.2025, posted by Frederik Wolff-Fabris on 10 Sep 2025, 10:31
|
General Announcement:
- M. Doering announces on the LIMP-25:
1. XTD10 Scaffolding is installed for cabling work in October;
|
Notes XO Integration Meeting 08.09.2025, posted by Frederik Wolff-Fabris on 08 Sep 2025, 09:42
|
General Announcement:
- Regarding LIMP-25, there is nothing different apart of what was already mentioned on Wednesday for this week cw37.
|
Notes XO Integration Meeting 03.09.2025, posted by Frederik Wolff-Fabris on 03 Sep 2025, 10:29
|
General Announcement:
- LIMP-25: next week cw37 sees the PLC updates starting in SPB/SFX and SQS; also the re-installation of AIBS will be completed.
|
Notes XO Integration Meeting 01.09.2025, posted by Frederik Wolff-Fabris on 01 Sep 2025, 09:37
|
General Announcement:
- There are no general updates regarding LIMP-25.
|
Notes XO Integration Meeting 27.08.2025, posted by Andreas Galler on 27 Aug 2025, 09:30
|
General Announcement:
Martin shows the preview for cw36,
Implementation of central gas management
safety lights maintenance
CTRL:
nothing major
DA: |
Notes XO Integration Meeting 25.08.2025, posted by Andreas Galler on 25 Aug 2025, 09:28
|
General Announcement:
Martin Doering
XTD6 today maintenance of cooling water pumps --> fluctuations can occur
Safety: a couple
of EPDs have not been logged out
CTRL: |
Notes XO Integration Meeting 20.08.2025, posted by Frederik Wolff-Fabris on 20 Aug 2025, 09:43
|
General Announcement:
- Martin Doering announces on the LIMP-25 (Main infrastructure works are ending in general):
1. Water related activities will be finished this week;
|
Notes XO Integration Meeting 18.08.2025, posted by Frederik Wolff-Fabris on 18 Aug 2025, 09:36
|
General Announcement:
- O. Bilani informs transport and crane activities are being made at truck bay today. Please be careful when walking around.
- M. Prollius informs on Wednesday afternoon the NDR is making footages at undulator tunnels, organized by COMS.
|
Notes XO Integration Meeting 13.08.2025, posted by Frederik Wolff-Fabris on 13 Aug 2025, 09:50
|
General Announcement:
- A. Galler informs on the LIMP-25 plans for next week:
1. TS tasks: last week with water, dehumidification activities;
|
Notes XO Integration Meeting 11.08.2025, posted by Frederik Wolff-Fabris on 11 Aug 2025, 09:39
|
General Announcement:
- A. Galler informs that regarding the LIMP-25 scheduling there is nothing new as compared to what was announced last Wednesday.
|
Notes XO Integration Meeting 06.08.2025, posted by Frederik Wolff-Fabris on 06 Aug 2025, 09:40
|
General Announcement:
- A. Galler informs on the LIMP-25 for next week:
1. Water: dirty traps maintenance ongoing in all tunnels but without interruptions, only changes in water pressure;
|