Notes XO Integration Meeting 10.09.2025, posted by Frederik Wolff-Fabris on 10 Sep 2025, 10:31
|
General Announcement:
- M. Doering announces on the LIMP-25:
1. XTD10 Scaffolding is installed for cabling work in October;
|
Notes XO Integration Meeting 08.09.2025, posted by Frederik Wolff-Fabris on 08 Sep 2025, 09:42
|
General Announcement:
- Regarding LIMP-25, there is nothing different apart of what was already mentioned on Wednesday for this week cw37.
|
Notes XO Integration Meeting 03.09.2025, posted by Frederik Wolff-Fabris on 03 Sep 2025, 10:29
|
General Announcement:
- LIMP-25: next week cw37 sees the PLC updates starting in SPB/SFX and SQS; also the re-installation of AIBS will be completed.
|
Notes XO Integration Meeting 01.09.2025, posted by Frederik Wolff-Fabris on 01 Sep 2025, 09:37
|
General Announcement:
- There are no general updates regarding LIMP-25.
|
Notes XO Integration Meeting 27.08.2025, posted by Andreas Galler on 27 Aug 2025, 09:30
|
General Announcement:
Martin shows the preview for cw36,
Implementation of central gas management
safety lights maintenance
CTRL:
nothing major
DA: |
Notes XO Integration Meeting 25.08.2025, posted by Andreas Galler on 25 Aug 2025, 09:28
|
General Announcement:
Martin Doering
XTD6 today maintenance of cooling water pumps --> fluctuations can occur
Safety: a couple
of EPDs have not been logged out
CTRL: |
Notes XO Integration Meeting 20.08.2025, posted by Frederik Wolff-Fabris on 20 Aug 2025, 09:43
|
General Announcement:
- Martin Doering announces on the LIMP-25 (Main infrastructure works are ending in general):
1. Water related activities will be finished this week;
|
Notes XO Integration Meeting 18.08.2025, posted by Frederik Wolff-Fabris on 18 Aug 2025, 09:36
|
General Announcement:
- O. Bilani informs transport and crane activities are being made at truck bay today. Please be careful when walking around.
- M. Prollius informs on Wednesday afternoon the NDR is making footages at undulator tunnels, organized by COMS.
|
Notes XO Integration Meeting 13.08.2025, posted by Frederik Wolff-Fabris on 13 Aug 2025, 09:50
|
General Announcement:
- A. Galler informs on the LIMP-25 plans for next week:
1. TS tasks: last week with water, dehumidification activities;
|
Notes XO Integration Meeting 11.08.2025, posted by Frederik Wolff-Fabris on 11 Aug 2025, 09:39
|
General Announcement:
- A. Galler informs that regarding the LIMP-25 scheduling there is nothing new as compared to what was announced last Wednesday.
|
Notes XO Integration Meeting 06.08.2025, posted by Frederik Wolff-Fabris on 06 Aug 2025, 09:40
|
General Announcement:
- A. Galler informs on the LIMP-25 for next week:
1. Water: dirty traps maintenance ongoing in all tunnels but without interruptions, only changes in water pressure;
|
Notes XO Integration Meeting 04.08.2025, posted by Frederik Wolff-Fabris on 04 Aug 2025, 09:43
|
General Announcement:
- A. Galler informs on the LIMP-25: 1. TS task #7 takes place this week with firm upgrade of the building management system will affect infrastructure
system for about a minute or so.
|
Notes XO Integration Meeting 30.07.2025, posted by Andreas Galler on 30 Jul 2025, 09:22
|
General Announcement:
electrical meintenance on July 30th XHQ green marked area
electrical maintenance on July 31st - Aug 1st XHQ blue marked area
CTRL:
issue with fastADC device, investigation going on together with EEE
DA: |
Notes XO Integration Meeting 28.07.2025, posted by Andreas Galler on 28 Jul 2025, 09:20
|
General Announcement:
electrical maintenance on July 28th
electrical sockets in the IT-Rack rooms E1.010 & E1.092 & E1.174; Meeting room
equipment in E1.173; Reception
electrical meintenance on July 29th - 30th
electrical maintenance on July 31st - Aug |
Notes XO Integration Meeting 23.07.2025, posted by Frederik Wolff-Fabris on 23 Jul 2025, 09:25
|
General Announcement:
- Martin Doering informs on the LIMP-25:
1. Today it happen crane activities in the XHEXP1 and please take the appropriated safety measurements when craning takes place.
|
Notes XO Integration Meeting 21.07.2025, posted by Frederik Wolff-Fabris on 21 Jul 2025, 09:54
|
General Announcement:
- M. Doering informs on the Limp-25 / current week:
1. Cooling water maintenance in XHPSC: replacement of valves taking place and the filling back is ongoing; expected that cooling water will be back today. |
Notes XO Integration Meeting 16.07.2025, posted by Frederik Wolff-Fabris on 16 Jul 2025, 09:51
|
General Announcement:
- Martin Doering informs on the LIMP-25 on cw30:
|
Notes XO Integration Meeting 14.07.2025, posted by Frederik Wolff-Fabris on 14 Jul 2025, 09:59
|
General Announcement:
- On Crane activities:
1. Next craning activity from truck bay to HXS area will take place on Wednesday 16.07 from early morning. During the time helmets will be provided in |
Notes XO Integration Meeting 09.07.2025, posted by Frederik Wolff-Fabris on 09 Jul 2025, 08:32
|
General Announcement:
- LIMP-25 update for this week: elevators were to be maintained this week but it is now shifted to 16-19.July.
- A. Galler announces on the LIMP-25 regarding next week:
|
Notes XO Integration Meeting 07.07.2025, posted by Frederik Wolff-Fabris on 07 Jul 2025, 09:44
|
General Announcement:
- Martin Doering announces:
1. Karabo will be stopped this week accordingly to a distributed e-mail;
|