Group Selection Page HELP DOC Controls Group Data Analysis Group ITDM WP76 DET Vacuum XRO EEE WP78 WP74 FXE SCS SPB MID HED SQS SXP Sample Environment Photon Commissioning Team Operation PSPO XO TS
Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther, Page 9 of 30  Not logged in ELOG logo
New entries since:Thu Jan 1 01:00:00 1970
IDdown Date Author Location Severity Subject Text Attachments
  437   08 Jan 2018, 09:50 Monica ArestéGeneralInformationReminder Readiness meeting today at 13:00Dear all,

This is a reminder to inform you
that Readiness meeting will resume today
  
  436   18 Dec 2017, 10:48 Gerd WellenreutherGeneralInformationStatus and plans after Readiness MeetingPSPO:


M. Areste presented a report
about the progress so far achieved in the
  
  435   14 Dec 2017, 09:12 Lewis BatchelorXTD2InformationFXE Collimating CRLThe LENS_3X limit switch (switched when
driving towards the chamber center) is broken
and must be replaced, hence further work
  
  434   13 Dec 2017, 16:28 Tobias HaasGeneralInformationStatus and plans after SASE1 Status/SASE3 Readiness MeetingGeneral


Meeting on Friday will
take place at 1300 due to overlap with XDAC
M.
  
  433   08 Dec 2017, 15:49 Tobias HaasGeneralInformationFire alarms in tunnels and shafts on 13 Dec 9 - 11FYI

Author: F. Saretzki
  
  432   08 Dec 2017, 11:35 Tobias HaasGeneralInformationStatus and plans after SASE1 Status/SASE3 Readiness MeetingGeneral


Starting from next week
shutdown activities will be tracked using M.
  
  431   07 Dec 2017, 09:04 Tobias HaasGeneralInformationRack extinguishing system in SASE2Please note following info from DESY:

 

Author: F. Saretzki
  
  430   06 Dec 2017, 17:17 NEREA JARDONGeneralInformationSASE1 MOVThe Motion loop in SASE1 is totally operated
again.
  
  429   06 Dec 2017, 13:46 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 13:00General:


Shutdown started.


Instruments


SPB:

AGIPD
  
  428   04 Dec 2017, 10:56 Tobias HaasGeneralInformationStatus after 0930 meetingGeneral:


User operation with good
beam conditions over the weekend
One
  
  427   01 Dec 2017, 11:42 Tobias HaasGeneralInformationStatus and plans after SASE1 Status/SASE3 Readiness MeetingGeneral:


User Operation ongoing
until Tuesday 5 Dec 8 AM
CAS shall
  
  426   29 Nov 2017, 09:56 Adriano ViolanteGeneralInformationStatus after 9.30 dispatch meetingGeneral


Preparation for the user's
run starting tomorrow (until 7:00 Tuesday
  
  425   24 Nov 2017, 13:15 Tobias HaasGeneralInformationStatus and plans after SASE1 Status/SASE3 Readiness MeetingGeneral


User operation ongoing
in SPB/SFX and FXE


 
  
  424   22 Nov 2017, 10:57 Tobias HaasGeneralInformationStatus and Plans after 0930 meetingGeneral


User experiments resume
tomorrow morning
Beam should be
  
  423   20 Nov 2017, 10:21 Tobias HaasGeneralInformationStatus after 0930 meetingGeneral


Intensity and availability
of beam was good over the weekend
Large
  
  422   17 Nov 2017, 17:14 Tobias HaasGeneralInformationStatus and plans after SASE1 Status/SASE3 Readiness MeetingGeneral


Beam is back with good
intensity (up to 1 mJ) 
Next
  
  421   15 Nov 2017, 11:51 Tobias HaasGeneralInformationStatus after 0930 meetingInstruments


SPB:

Waiting
for beam to come in a usable condition (500
  
  420   14 Nov 2017, 11:05 Gerd WellenreutherGeneralInformationTunnel access schedule updatedDear all,

I received updates from DESY (M.
Hüning) about how the access to the
  
  419   13 Nov 2017, 09:45 Adriano ViolanteGeneralInformationStatus after 9.30 dispatch meetingGeneral


No user operation.
During
the week end the accelerator was not able
  
  418   10 Nov 2017, 11:46 Tobias HaasGeneralInformationStatus and plans after SASE1 Status/SASE3 Readiness MeetingGeneral


User operation is delayed
by 48h due to rocky startup of FEL.
FEL
  
ELOG V3.1.4-7c3fd00