Group Selection Page HELP DOC Controls Group Data Analysis Group ITDM WP76 DET Vacuum XRO EEE WP78 WP74 FXE SCS SPB MID HED SQS SXP Sample Environment Photon Commissioning Team Operation PSPO XO TS
Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther, Page 2 of 30  Not logged in ELOG logo
New entries since:Thu Jan 1 01:00:00 1970
ID Date Author Location Severity Subjectdown Text Attachments
  181   27 Apr 2017, 07:11 Raúl Villanueva-GuerreroXTD2ProblemXTD2 Differential Pumping completely OUT OF OPERATION!

    

       
            
  
  135   11 Apr 2017, 17:44 Raúl Villanueva-GuerreroXTD2FeedbackXTD2 Complete Gas Section (DPS-XGM-DPS) Isolation Interlock tested - SUCCESSFUL The interlock definition for complete
isolation of the whole section based on high
pressure signal has been successfully tested. 
  
  282   08 Jun 2017, 08:24 Tobias HaasGeneralInformationXTD10 open  Author: limberg, tischhauser
due
to the cryogenic failure we will open XTD10
from 9am for working.
at XTL and
  
  223   11 May 2017, 18:26 Harald SinnXTD10InformationXTD10 not open on Monday Dear all, 
contrary to the rumor that I spread
last Tuesday in the PBS meeting, the magnet
  
  408   26 Oct 2017, 17:34 Tobias HaasXTD10InformationXTD10 closed and interlockedThe SASE3 tunnel XTD10 was searched by
Janni and her team and interlocked about
one hour ago.
  
  283   08 Jun 2017, 08:24 Harald SinnGeneralInformationXTD10 and XTD9 tunnel opening and closingsDear all, 
according to the DESY logbook XTD10
will be opened today again: See DESY
  
  494   27 Mar 2018, 14:18 Jan GruenertGeneralInformationXTD1 openInfo from BKR:  the southern tunnels
were opened, thus XTD1 can be accessed now.
  
  175   26 Apr 2017, 12:58 Adriano ViolanteGeneralInformationXSDU2 access The XSDU2  area will be open
(as XTD2) tomorrow between 9 ans 12. To register
the access, please send also in this case
  
  138   11 Apr 2017, 22:36 Jan GrünertXTD2InformationXGMs in loopBoth SASE1 XGMs (in XTD2 and XTD9) are
now again in the Vacuum Control Loop, their
vacuum being controlled by Beckhoff/karabo.
  
  155   21 Apr 2017, 09:59 Jan GrünertGeneralInformationXGM statusXGM status 21.4.2017
During Easter break, the two XGMs
in the control system (XTD2+9) had no issues.
  
  197   02 May 2017, 20:11 Jan GrünertXTD2ProblemXGM scenes/devices offline - UHV pressures increasing - Please respond now !!All devices went into unknown state in
the karabo XGM scenes in XTD2 and XTD9 at
19h52.
  
  35   02 Feb 2017, 17:54 Jan GrünertGeneralInformationXGM resistors - progress w5Presentation for SASE1readiness-Meeting
on XGM resistor issue progress (w5)
and plan (w6)
 XGM-resistors.pptx 
  31   01 Feb 2017, 17:42 Jan GrünertGeneralProblemXGM resistor issue - analysis progressThis is the current (w5) progress at DESY
concerning the analysis of the serious XGM
resistor issue (summary; a detailed report
  
  27   26 Jan 2017, 17:02 Tobias HaasXTD2ProblemXGM at XTD2 / issue with in-vacuum-resistorPost on behalf
of Jan Grünert:
  
  19   19 Dec 2016, 09:44 Frederike WittmaackGeneralInformationXGM Safe State Definitionas defined by Jan Grünert:

available on
Alfresco: XGM-safe-state.docx

and available
at N:\4all\intern\User data\wp74\Devices\11-1_XGMD\03
  
  78   16 Mar 2017, 13:34 Torben FalkGeneralFeedbackWiring statusWiring status SASE 1:
Wiring progress:

    Internal wiring of the
  
  89   31 Mar 2017, 07:24 Liubov SamoylovaGeneralInformationWeb cameras in SASE1 tunnels   TmpPhCom_CR_2017-03-31-1.pptx 
  504   12 Apr 2018, 15:34 Adriano ViolanteGeneralInformationWater cooling mointenance by MKK doneDie Arbeiten an der Kühlwassersteuerung
konnten innerhalb des genannten

Zeitraums abgeschlossen werden,
  
  36   02 Feb 2017, 18:29 Bernard BaranasicXTD2InformationWP74 components in XTD2 - electrical connectionsStatus   
  332   14 Jul 2017, 09:31 Jan GrünertGeneralInformationWP74 SASE1/3 readiness status and outlookSASE1 / SASE3 readiness --- WP74

2017-07-14

SASE1: 
  
ELOG V3.1.4-7c3fd00