Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther, Page 3 of 30  Not logged in ELOG logo
New entries since:Thu Jan 1 01:00:00 1970
ID Date Author Location Severity Subjectdown Text Attachments
  293   16 Jun 2017, 18:12 Jan GrünertGeneralInformationWP74 OCD plan updateThe WP74 OCD plan is also published in
WP74-Alfresco and sent by email to HR/WoCo/STGL.

Please
note that this plan could be subject to changes
 WP74-OCD-plan-6-8-2017.xlsx 
  414   04 Nov 2017, 03:28 Jan GrünertGeneralInformationWP74 OCD plan until next shutdown   WP74_OCD_Plan.xlsx 
  413   04 Nov 2017, 03:26 Jan GrünertGeneralInformationWP74 OCD contacts for this weekend4.11. from 08:00 until 5.11. 08:00 - Jan
Gruenert by email (work mobile
defect)
  
  224   11 May 2017, 19:12 Jan GrünertGeneralInformationWP74 OCD contactsPlan of WP74 OCD contacts for May.
Assignments are subject to change.
Initially availability is 10h-18h
 WP74-OCD-5-2017.xlsx 
  374   01 Sep 2017, 20:14 Jan GrünertGeneralInformationWP74 - OCD contacts for this weekend02.09. from 08:00 until
03.09. 08:00 - Wolfgang Freund
9-5630  
  
  395   29 Sep 2017, 14:46 Andreas KochGeneralInformationWP74 - OCD contacts for this weekend30.09. from 08:00 until 01.10. 08:00 -
Andreas Koch 9-6443

01.10. from 08:00 until 02.10.
  
  210   06 May 2017, 14:50 Jan GrünertGeneralInformationWP74 OCD contacts for this weekendWP74   OCD  for the 
weekend 6.5.-7.5.2017:
Saturday: Jan, jan.gruenert@xfel.eu,
  
  191   28 Apr 2017, 15:44 Jan GrünertGeneralInformationWP74 OCD contacts for the coming weekendWP74   OCD  for the coming
weekend 29.4.-1.5.2017:
 
  
  214   10 May 2017, 10:59 NEREA JARDONGeneralInformationVacuum loopDear all,
The update of the Vacuum loop will
take place in the next few minutes, later
  
  245   18 May 2017, 11:57 Jan GrünertGeneralProblemVacuum issue in XTD9 during cycling of PLC loop yesterdayDuring the usual recovery procedure after
the planned and announced cycling of the
SASE1 VAC loop yesterday, we observed a serious
  
  192   28 Apr 2017, 16:29 Janni EidamGeneralInformationVacuum group call serviceNot really official, but in emergency case
you can call 96993 for vacuum group. Next
week Martin is back and I think we will have
  
  73   13 Mar 2017, 15:47 NEREA JARDONGeneralInformationVacuum and Motion downTomorrow, 14th of March, Vacuum and Motion
loop will be down at least during morning
due to technical reasons .
  
  74   14 Mar 2017, 13:55 NEREA JARDONGeneralInformationVacuum and Motion downDear all,
Finally today the Vacuum and Motion
will still running the hole day and I would
  
  76   15 Mar 2017, 11:31 NEREA JARDONGeneralInformationVacuum and MotionToday Denis has to make some changes in
the Vacuum and Motion hardware loop, therefore
they would be down some time. 
  
  77   15 Mar 2017, 17:00 NEREA JARDONGeneralInformationVacuum and MotionVacumm and Motion are running again after
the hardware changes.
  
  57   02 Mar 2017, 11:55 NEREA JARDONGeneralInformationVacuum PLCDear all,
The Vacuum PLC is up and running
and Karaboo guys have already started to
  
  329   13 Jul 2017, 10:27 NEREA JARDONXTD9InformationVacuum Loop in XTD9Dear all,

One power supply needs to be changed
in SASE1 XTD9 rack 1.12 tomorrow and it's
  
  102   04 Apr 2017, 19:25 NEREA JARDONGeneralInformationVacuum LoopDear all,
Tomorrow at first hour, some hardware
modules would added in Rack 1.1 and 1.9 in
  
  105   05 Apr 2017, 14:27 NEREA JARDONGeneralInformationVacuum LoopDear all, 
The XGM XTD2 is already into the
Vacuum loop and the loop is running. We would
  
  121   10 Apr 2017, 09:36 NEREA JARDONGeneralInformationVacuum LoopDear all,
I will update the Vacuum loop in
order to add the XGM XTD9 into it. It will
  