  181   27 Apr 2017, 07:11 Raúl Villanueva-GuerreroXTD2ProblemXTD2 Differential Pumping completely OUT OF OPERATION!

    

       
            
  
  135   11 Apr 2017, 17:44 Raúl Villanueva-GuerreroXTD2FeedbackXTD2 Complete Gas Section (DPS-XGM-DPS) Isolation Interlock tested - SUCCESSFUL The interlock definition for complete
isolation of the whole section based on high
pressure signal has been successfully tested. 
  
  282   08 Jun 2017, 08:24 Tobias HaasGeneralInformationXTD10 open  Author: limberg, tischhauser
due
to the cryogenic failure we will open XTD10
from 9am for working.
at XTL and
  
  223   11 May 2017, 18:26 Harald SinnXTD10InformationXTD10 not open on Monday Dear all, 
contrary to the rumor that I spread
last Tuesday in the PBS meeting, the magnet
  
  408   26 Oct 2017, 17:34 Tobias HaasXTD10InformationXTD10 closed and interlockedThe SASE3 tunnel XTD10 was searched by
Janni and her team and interlocked about
one hour ago.
  
  283   08 Jun 2017, 08:24 Harald SinnGeneralInformationXTD10 and XTD9 tunnel opening and closingsDear all, 
according to the DESY logbook XTD10
will be opened today again: See DESY
  
  494   27 Mar 2018, 14:18 Jan GruenertGeneralInformationXTD1 openInfo from BKR:  the southern tunnels
were opened, thus XTD1 can be accessed now.
  
  175   26 Apr 2017, 12:58 Adriano ViolanteGeneralInformationXSDU2 access The XSDU2  area will be open
(as XTD2) tomorrow between 9 ans 12. To register
the access, please send also in this case
  
  138   11 Apr 2017, 22:36 Jan GrünertXTD2InformationXGMs in loopBoth SASE1 XGMs (in XTD2 and XTD9) are
now again in the Vacuum Control Loop, their
vacuum being controlled by Beckhoff/karabo.
  
  155   21 Apr 2017, 09:59 Jan GrünertGeneralInformationXGM statusXGM status 21.4.2017
During Easter break, the two XGMs
in the control system (XTD2+9) had no issues.
  
  197   02 May 2017, 20:11 Jan GrünertXTD2ProblemXGM scenes/devices offline - UHV pressures increasing - Please respond now !!All devices went into unknown state in
the karabo XGM scenes in XTD2 and XTD9 at
19h52.
  
  35   02 Feb 2017, 17:54 Jan GrünertGeneralInformationXGM resistors - progress w5Presentation for SASE1readiness-Meeting
on XGM resistor issue progress (w5)
and plan (w6)
 XGM-resistors.pptx 
  31   01 Feb 2017, 17:42 Jan GrünertGeneralProblemXGM resistor issue - analysis progressThis is the current (w5) progress at DESY
concerning the analysis of the serious XGM
resistor issue (summary; a detailed report
  
  27   26 Jan 2017, 17:02 Tobias HaasXTD2ProblemXGM at XTD2 / issue with in-vacuum-resistorPost on behalf
of Jan Grünert:
  
  19   19 Dec 2016, 09:44 Frederike WittmaackGeneralInformationXGM Safe State Definitionas defined by Jan Grünert:

available on
Alfresco: XGM-safe-state.docx

and available
at N:\4all\intern\User data\wp74\Devices\11-1_XGMD\03
  
  78   16 Mar 2017, 13:34 Torben FalkGeneralFeedbackWiring statusWiring status SASE 1:
Wiring progress:

    Internal wiring of the
  
  89   31 Mar 2017, 07:24 Liubov SamoylovaGeneralInformationWeb cameras in SASE1 tunnels   TmpPhCom_CR_2017-03-31-1.pptx 
  504   12 Apr 2018, 15:34 Adriano ViolanteGeneralInformationWater cooling mointenance by MKK doneDie Arbeiten an der Kühlwassersteuerung
konnten innerhalb des genannten

Zeitraums abgeschlossen werden,
  
  36   02 Feb 2017, 18:29 Bernard BaranasicXTD2InformationWP74 components in XTD2 - electrical connectionsStatus   
  332   14 Jul 2017, 09:31 Jan GrünertGeneralInformationWP74 SASE1/3 readiness status and outlookSASE1 / SASE3 readiness --- WP74

2017-07-14

SASE1: 
  