Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther, Page 21 of 30  Not logged in ELOG logo
ID Date Author Location Severitydown Subject Text Attachments
  415   06 Nov 2017, 13:58 Gerd WellenreutherGeneralInformationTunnel access schedule updatedDear all,

I updated the TAS to include the
upcoming user runs up to and including the
  
  416   06 Nov 2017, 14:13 Tobias HaasGeneralInformationStatus after 0930 meetingGeneral


Recomissioning of the FEL
has been bumpy and up to this point only
  
  417   09 Nov 2017, 13:21 Tobias HaasGeneralInformationStatus after 0930 meetingGeneral


There is currently no beam
less than 24h before user operation is supposed
  
  418   10 Nov 2017, 11:46 Tobias HaasGeneralInformationStatus and plans after SASE1 Status/SASE3 Readiness MeetingGeneral


User operation is delayed
by 48h due to rocky startup of FEL.
FEL
  
  419   13 Nov 2017, 09:45 Adriano ViolanteGeneralInformationStatus after 9.30 dispatch meetingGeneral


No user operation.
During
the week end the accelerator was not able
  
  420   14 Nov 2017, 11:05 Gerd WellenreutherGeneralInformationTunnel access schedule updatedDear all,

I received updates from DESY (M.
Hüning) about how the access to the
  
  421   15 Nov 2017, 11:51 Tobias HaasGeneralInformationStatus after 0930 meetingInstruments


SPB:

Waiting
for beam to come in a usable condition (500
  
  422   17 Nov 2017, 17:14 Tobias HaasGeneralInformationStatus and plans after SASE1 Status/SASE3 Readiness MeetingGeneral


Beam is back with good
intensity (up to 1 mJ) 
Next
  
  423   20 Nov 2017, 10:21 Tobias HaasGeneralInformationStatus after 0930 meetingGeneral


Intensity and availability
of beam was good over the weekend
Large
  
  424   22 Nov 2017, 10:57 Tobias HaasGeneralInformationStatus and Plans after 0930 meetingGeneral


User experiments resume
tomorrow morning
Beam should be
  
  425   24 Nov 2017, 13:15 Tobias HaasGeneralInformationStatus and plans after SASE1 Status/SASE3 Readiness MeetingGeneral


User operation ongoing
in SPB/SFX and FXE


 
  
  426   29 Nov 2017, 09:56 Adriano ViolanteGeneralInformationStatus after 9.30 dispatch meetingGeneral


Preparation for the user's
run starting tomorrow (until 7:00 Tuesday
  
  427   01 Dec 2017, 11:42 Tobias HaasGeneralInformationStatus and plans after SASE1 Status/SASE3 Readiness MeetingGeneral:


User Operation ongoing
until Tuesday 5 Dec 8 AM
CAS shall
  
  428   04 Dec 2017, 10:56 Tobias HaasGeneralInformationStatus after 0930 meetingGeneral:


User operation with good
beam conditions over the weekend
One
  
  429   06 Dec 2017, 13:46 Adriano ViolanteGeneralInformationStatus report after dispatch meeting 13:00General:


Shutdown started.


Instruments


SPB:

AGIPD
  
  430   06 Dec 2017, 17:17 NEREA JARDONGeneralInformationSASE1 MOVThe Motion loop in SASE1 is totally operated
again.
  
  431   07 Dec 2017, 09:04 Tobias HaasGeneralInformationRack extinguishing system in SASE2Please note following info from DESY:

 

Author: F. Saretzki
  
  432   08 Dec 2017, 11:35 Tobias HaasGeneralInformationStatus and plans after SASE1 Status/SASE3 Readiness MeetingGeneral


Starting from next week
shutdown activities will be tracked using M.
  
  433   08 Dec 2017, 15:49 Tobias HaasGeneralInformationFire alarms in tunnels and shafts on 13 Dec 9 - 11FYI

Author: F. Saretzki
  
  434   13 Dec 2017, 16:28 Tobias HaasGeneralInformationStatus and plans after SASE1 Status/SASE3 Readiness MeetingGeneral


Meeting on Friday will
take place at 1300 due to overlap with XDAC
M.
  