Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther, Page 21 of 29  Not logged in ELOG logo
New entries since:Thu Jan 1 01:00:00 1970
Entry   Vacuum Loop, posted by NEREA JARDON on 26 Apr 2017, 09:10 
Dear all,
We need to update the Vacuum loop in order to correct and add some configuration to the interlock conditions.
It would be running in few minutes again.
Entry   Motion loop, posted by NEREA JARDON on 25 Apr 2017, 14:20 
Dear all,
We have to make some changes again into the Motion loop. Therefore I will do an update at 14.45h.
I will keep you inform when it is running again.
Entry   XTD9 Complete Gas Section (DPS-XGM-DPS) Isolation Interlock tested - Not Working (yet), posted by Raśl Villanueva-Guerrero on 25 Apr 2017, 13:49 
 After some minor issues, the first test has been done today and the interlock wasn´t triggered despite the conditions were met (also visible
in Karabo).
 
Entry   Motion loop, posted by NEREA JARDON on 25 Apr 2017, 10:51 
Dear all.
Motion loop is running again.
Thank you
Entry   Status and Plans after the 9:30 meeting, posted by Adriano Violante on 25 Apr 2017, 10:49 
XTDs Info:
Tunnel XTD2 will be accessible this Thursday, 27.04. between 9 and 12. Dosimeter and General radiation training
required. Access requests should go to T.Haas.
Entry   Status and Plans after 09:30 meeting, posted by Tobias Haas on 24 Apr 2017, 11:08 
 

    
        

           
Entry   CAS OCD April 22-23, posted by Sandor Brockhauser on 21 Apr 2017, 17:22 
In case of any problems, please, call the CAS personnel on 9-6443, 9-5630, or 9-6840.
Have a nice week-end, Sandor
Entry   SASE EPS RACK 1.14 connected, posted by Tobias Freyermuth on 21 Apr 2017, 15:30 





The EPS-loop is now complete again.
The interface from EPS to MPS is working now. One broken wire in the cable between EPS and MPS was found. We are using now other pairs for the
signals "SA1_SYS_EPS2MPS/DCTRL/MODE1", "SA1_SYS_EPS2MPS/DCTRL/MODES" and "SA1_SYS_EPS2MPS/DCTRL/MODEM".
Entry   Cycling of PLC loop (shutdown and restart) - effects on XGM XTD2 and XTD9, posted by Jan Grünert on 21 Apr 2017, 15:26 

Together with Nerea and Wajid and Alessandro

10:00 closed vatterflies at XTD9 and XTD2 from KaraboFlorian is at XTD9 next to
the XGM XTD9: 
LOOP re-cycleAll valve closed and scroll off (turbos in unknown state; Florian in tunnel sees 990 Hz)Scroll
and turbos switched ONAngle valve opened over KaraboProblem to open gate-valveSet Karabo offlineNerea switched
Entry   OCD, posted by NEREA JARDON on 21 Apr 2017, 15:22 
Dear all,
The service of On-call Duty will be available from AE group during weekend in this number: 6442
Please make a post with the OCD numbers from CAS, WP74 and WP73.
Entry   SASE EPS RACK 1.14 disconnect, posted by Tobias Freyermuth on 21 Apr 2017, 14:36 
We have to disconnect the EPS crate in RACK 1.14 in order to check the interface to the MPS.
I will keep you updated
Entry   Access to control PC, posted by Jan Tolkiehn on 21 Apr 2017, 13:54 
exflplcgwSA1 seems not reachable. This inhibits support for the PLC systems.
Entry   FAILED - Interlock test of the whole gas section in XTD9 - NOT SUCCESSFUL, posted by Raśl Villanueva-Guerrero on 21 Apr 2017, 12:28 
 Due to problems and lack of support of CAS for accessing the devices in XTD9 tunnel through KARABO we couldn´t run the test. The system has
been returned to manual operation and will remain like that until next notice.
 
    Reply   FAILED - Interlock test of the whole gas section in XTD9 - NOT SUCCESSFUL, posted by Raśl Villanueva-Guerrero on 21 Apr 2017, 13:23 


    
        
            Raúl Villanueva-Guerrero wrote:
        
        
           

             Due to problems and lack of support of CAS for accessing the devices in
       Reply   FAILED - Interlock test of the whole gas section in XTD9 - NOT SUCCESSFUL, posted by Raśl Villanueva-Guerrero on 21 Apr 2017, 13:35 


    
        
            Raúl Villanueva-Guerrero wrote:
        
        
           

            
            
Entry   XGM status, posted by Jan Grünert on 21 Apr 2017, 09:59 
XGM status 21.4.2017
During Easter break, the two XGMs in the control system (XTD2+9) had no issues. 
XGM@XTD10 however had an issue: tuesday morning it was found that all pumps had stopped. The scroll pump showed an error. UPS apparently had excess
Entry   Maintenance/Access in KW17, posted by Tobias Haas on 20 Apr 2017, 17:18 
 In KW17 there will be NO maintenance day on Tuesday (25.04.) 

 On Monday (24.04.) morning up to about 11:00 we will have the TÜV approval of CS8. During that time  NO access of "other people" to the XTL tunnel is possible. After the TÜV approval 
Entry   Status and Plans after 09:30 meeting, posted by Tobias Haas on 20 Apr 2017, 10:25 
 Tunnels XTD2 and XTD4 are closed, XTD9/10 remain open
Vacuum:

    PLC/Karabo Running stably
    Local
Entry   Status and Plans after 09:30 meeting, posted by Tobias Haas on 19 Apr 2017, 11:49 
Tunnels XTD2 and XTD4 are closed, XTD9/10 remain open
Vacuum:

    Running stably
    Work continues
Entry   Motion loop, posted by NEREA JARDON on 19 Apr 2017, 11:47 
Dear all,
Today from 13:30h  Mahadi and Natalia will be doing local tests in the PBLM in Rack 1.14 of XTD9, therefore, if someone will be working in
the following racks of XTD9, will loose connection to the Motion loop.
Entry   Trigger and IP address, posted by Andreas Koch on 18 Apr 2017, 16:36 
All trigger problems in XTD2 and XTD9 solved except for one: spb_xtd9_imgpi, probably a cabling issue on the camera side.
IP address problem for camera of sa1_xd2_imgpii45 solved.
Entry   KW16 Accelerator Plans, posted by Tobias Haas on 18 Apr 2017, 13:21 
 Author: Decking