Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther, Page 17 of 30  Not logged in ELOG logo
Entry   Status and plans after SASE1 Readiness Meeting, posted by Tobias Haas on 07 Jun 2017, 11:43 
Entry   Motion loop update, posted by NEREA JARDON on 07 Jun 2017, 12:00 
Entry   Motion loop update, posted by NEREA JARDON on 07 Jun 2017, 14:19 
Entry   XTD10 open , posted by Tobias Haas on 08 Jun 2017, 08:24 
Entry   XTD10 and XTD9 tunnel opening and closings, posted by Harald Sinn on 08 Jun 2017, 08:24 
Entry   Status and plans after SASE1 Readiness Meeting, posted by Monica Aresté on 09 Jun 2017, 12:41 
Entry   Information AE OCD June 9 -- 12, posted by Nicola Coppola on 09 Jun 2017, 19:09 
Entry   Status and plans after SASE1 Readiness Meeting, posted by Monica Aresté on 12 Jun 2017, 10:55 
Entry   Tunnel's schedule, posted by Monica Aresté on 12 Jun 2017, 11:17 
Entry   Tunnel's schedule updated, posted by Monica Aresté on 12 Jun 2017, 13:21 
Entry   Status and plans after SASE1 Readiness Meeting, posted by Monica Aresté on 14 Jun 2017, 10:57 
Entry   Status and plans after SASE1 Readiness Meeting, posted by Monica Aresté on 16 Jun 2017, 10:18 Radiation_Measurments_for_Commissioning.pptx20170615-Components-Detectors.xlsx
Entry   WP74 OCD plan update, posted by Jan Grünert on 16 Jun 2017, 18:12 WP74-OCD-plan-6-8-2017.xlsx
Entry   Status and plans after SASE1 Readiness Meeting, posted by Monica Aresté on 19 Jun 2017, 10:17 
Entry   Status and Plans after 09:30 meeting, posted by Tobias Haas on 21 Jun 2017, 10:21 
Entry   Tunnel access schedule updated, posted by Gerd Wellenreuther on 21 Jun 2017, 14:13 
Entry   Status and plans after SASE1 Readiness Meeting, posted by Tobias Haas on 23 Jun 2017, 11:11 
Entry   Status and Plans after 09:30 meeting, posted by Tobias Haas on 26 Jun 2017, 10:57 
Entry   Tunnel access schedule updated, posted by Gerd Wellenreuther on 26 Jun 2017, 15:52 
Entry   Tunnel access schedule updated, posted by Gerd Wellenreuther on 27 Jun 2017, 10:26 