Entry   Notes XO Integration Meeting 29.01.2024, posted by Frederik Wolff-Fabris on 29 Jan 2024, 09:57 
General Announcement:
- Experiment tuning week starts on Wed 7AM until Tue 7AM next week. It is the first week with Tuesday as tuning day by machine.
Entry   Notes XO Integration Meeting 22.01.2024, posted by Frederik Wolff-Fabris on 22 Jan 2024, 09:47 
General Announcement:
- Reminder that machine tuning day is on Tuesdays and Friday's User op meeting does not contain Coordinator reports this year which are to be done on Mondays
RC meeting.
Entry   Notes XO Integration Meeting 17.01.2024, posted by Frederik Wolff-Fabris on 17 Jan 2024, 09:44 
General Announcement:
- Functional interlock tests at instruments are ongoing by D3 and SRP. Information was sent by e-mail.
- A. Galler reminds that from this year the machine maintenance and tuning day takes place on Tuesdays. 
Entry   Notes XO Integration Meeting 15.01.2024, posted by Frederik Wolff-Fabris on 15 Jan 2024, 10:52 
General Announcement:
- Interlock tests light: functional tests will happen this Wednesday starting at 09:00 at the instruments. Emergency OFF will not be pressed.
Entry   Notes XO Integration Meeting 10.01.2024, posted by Frederik Wolff-Fabris on 10 Jan 2024, 10:37 
General Announcement:
- Interlock tests are finished and XTD6 and XTD9 will be closed again today during the day. They shall close on January 19th.
Entry   Notes XO Integration Meeting 08.01.2024, posted by Frederik Wolff-Fabris on 08 Jan 2024, 09:41 
General Announcement:
-  
Entry   Notes XO Integration Meeting 20.12.2023, posted by Frederik Wolff-Fabris on 20 Dec 2023, 09:43 
General Announcement:
-  This is the last XO Integration meeting for this year. 
Entry   Notes XO Integration Meeting 18.12.2023, posted by Frederik Wolff-Fabris on 18 Dec 2023, 10:13 
General Announcement:
-  
Entry   Notes XO Integration Meeting 13.12.2023, posted by Frederik Wolff-Fabris on 13 Dec 2023, 10:04 
General Announcement:
-  
Entry   Notes XO Integration Meeting 11.12.2023, posted by Frederik Wolff-Fabris on 11 Dec 2023, 09:51 
General Announcement:
-  
Entry   Notes XO Integration Meeting 06.12.2023, posted by Frederik Wolff-Fabris on 06 Dec 2023, 09:49 
General Announcement:
- Jan Gruenert announces a seminar done by UK guests from Daresbury on UK plans for FEL. The seminar happens on THU 13:30 at XHQ E2.042. Please contact
Jan G. for zoom link.
Entry   Notes XO Integration Meeting 04.12.2023, posted by Frederik Wolff-Fabris on 04 Dec 2023, 09:52 
General Announcement:
-  
Entry   Notes XO Integration Meeting 29.11.2023, posted by Frederik Wolff-Fabris on 29 Nov 2023, 09:43 
General Announcement:
-  Please remember and remind group members that the machine day is on Tuesdays and not Mondays anymore. Delivery will then start on Wednesday.
- Regarding the 2025 shutdown at the 2nd half of the year: XO is collecting initial tasks. Please groups are asked to provide a draft to XO of the planned
Entry   Notes XO Integration Meeting 27.11.2023, posted by Frederik Wolff-Fabris on 27 Nov 2023, 09:39 
General Announcement:
- User operation finished this morning 7AM for the year.
- Reminder that WMP starts on Thursday. Possible photon tunnels open on Wednesday but this still to be confirmed and e-mail will be sent.
Entry   Notes XO Integration Meeting 22.11.2023, posted by Frederik Wolff-Fabris on 22 Nov 2023, 10:39 
General Announcement:
-  
Entry   Notes XO Integration Meeting 20.11.2023, posted by Frederik Wolff-Fabris on 20 Nov 2023, 10:01 
General Announcement:
-  
Entry   Notes XO Integration Meeting 15.11.2023, posted by Frederik Wolff-Fabris on 15 Nov 2023, 09:48 
General Announcement:
- As PRC, A. Galler informs the machine runs without major issues but kicker adaptation has difficulties with 4.5MHz. For the next 20 mins machine colleagues
will introduce stronger kickers and during 
Entry   Notes XO Integration Meeting 13.11.2023, posted by Frederik Wolff-Fabris on 13 Nov 2023, 10:16 
General Announcement:
- This and next week of operation are the last 2 delivery weeks, which are done with 4.5MHz base rep rate. 
Entry   Notes XO Integration Meeting 08.11.2023, posted by Frederik Wolff-Fabris on 08 Nov 2023, 09:55 
General Announcement:
-  
Entry   Notes XO Integration Meeting 06.11.2023, posted by Frederik Wolff-Fabris on 06 Nov 2023, 09:53 
General Announcement:
- As PRC, Jan G. reports that on Saturday morning no beam permission at the North branch happened. An issue with XTD2 solid attenuator vacuum happened
and together with VAC-OCD the threshold was changed 