Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 519     Entry time: 05 Jun 2024, 09:55
Author: Frederik Wolff-Fabris 
Location: General 
Severity: Information 
Subject: Notes XO Integration Meeting 05.06.2024 
General Announcement:
- On Monday 10.06 a few slides on the Summer maintenance will be presented by Martin Doering in this meeting series. The task list will be released next Friday 07.June.

CTRL:
- Working on the all watchdog: hotfix was released last Monday and follow up is being done. Will get in touch with instruments for deployments if needed.

DA:
- Nothing to report.

EEE:
- Nothing to report.

VAC:
- Everything is running fine.

XPD:
- In a retreat.

DET:
- Nothing to report; as info: DAC meeting is taking place this week at XFEL.

ITDM: 
- Nothing to report.

XRO:
- Nothing to report.

LAS:
- Sync issues seen at SCS last weekend were fixed and did not happen again.

UNSYS:
- On SA1 cell#21, two ZZs were needed on Monday: first power distribution was replaced; 
after switching on cabinet the linear encoders were not communicated and after placing controller to the rotary encoders the motor of the PS was found broken and was replaced.

SPB:
- Nothing to report.

FXE:
- Nothing to report.

MID:
- Nothing to report.

HED:
- Problem with on a spectrometer camera: ticket was sent to CTRL and needs further help. 
Wajid E. says DOC was also contacted and seems to be an issue with the hardware/camera as controls side it seems fine. A test with a spare camera is needed.

SCS:
- 400nm laser issue: follow up on the info regarding this failure is appreciated to be shared to other instruments that perform pump-probe experiments.

SQS:
- Not present.

SXP:
- Not present.