General Announcement:
- Eric Boyd comments on Interlock tests: today FXE and MID hutches are being searched for ~30 mins. Please contact Eric in case you find lights ON.
For tomorrow, Tuesday: OFF buttons will be tested and jumped in SA1/SA3 instruments and on Wednesday the SA2 instruments. Access is restricted and e-mail will be sent to communicate when people are
allowed to resume access/work.
Also please clean up the hutches for the inspection and tests.
CTRL:
- Nothing to report; Karabo redeployment went well last week.
DA:
- Nothing to report.
EEE:
- Nothing to report.
VAC:
- Nothing to report.
XPD:
- XTD6 tunnel access is needed for HIREX.
DET:
- Intervention at SPB AGIPD: modules were swept, severe effect due to radiation (one module not working). One module was swept in the quadrant. It was successful.
ITDM:
- Nothing to report.
XRO:
- Nothing to report.
LAS:
- Some surprises but under control.
UNSYS:
- All fine.
SPB:
- All fine.
FXE:
- Software and firmware updates with detectors taking place.
MID:
- All fine at MID.
HED:
- Nothing to report.
SCS:
- Nothing to report.
SQS:
- Nothing to report.
SXP:
- Not present. |