Notes XO Integration Meeting 19.03.2025, posted by Frederik Wolff-Fabris on 19 Mar 2025, 09:35
|
General Announcement:
- As PRC, A. Galler informs delivery has started this week and everything runs accordingly to the plan so far.
|
Notes XO Integration Meeting 17.03.2025, posted by Frederik Wolff-Fabris on 17 Mar 2025, 09:36
|
General Announcement:
- As DRC, Jola S.-D. says it was a quiet weekend.
|
Notes XO Integration Meeting 12.03.2025, posted by Frederik Wolff-Fabris on 12 Mar 2025, 09:36
|
General Announcement:
- A. Galler informs the beam delivery start is delayed currently up to 15:00 due to difficulties in setting up the machine after the FD week.
- Couple of meetings regarding the LIMP are scheduled; plans have been distributed and will be shared during the meetings.
|
Notes XO Integration Meeting 10.03.2025, posted by Frederik Wolff-Fabris on 10 Mar 2025, 09:53
|
General Announcement:
- From the DRC side, there is nothing particular to report.
- From the PRC side, nothing apart of what was reported below.
|
Notes XO Integration Meeting 05.03.2025, posted by Frederik Wolff-Fabris on 05 Mar 2025, 09:40
|
General Announcement:
- On the LIMP-2025 (accordingly to an e-mail sent by M. Doering on 24.02): reminder that groups are requested to give a feedback on the task list for the
LIMP until tomorrow, 06.March.
|
Notes XO Integration Meeting 03.03.2025, posted by Frederik Wolff-Fabris on 03 Mar 2025, 09:48
|
General Announcement:
- For next Friday 07.03 UOM a jitter report from instruments is expected together with presentations from groups using beam during this FD week.
|
Notes XO Integration Meeting 26.02.2025, posted by Andreas Galler on 26 Feb 2025, 09:24
|
General Announcement:
-
CTRL: |
Notes XO Integration Meeting 24.02.2025, posted by Andreas Galler on 24 Feb 2025, 09:26
|
General Announcement:
-
CTRL: |
Notes XO Integration Meeting 19.02.2025, posted by Andreas Galler on 19 Feb 2025, 09:29
|
General Announcement:
-
CTRL: |
Notes XO Integration Meeting 17.02.2025, posted by Frederik Wolff-Fabris on 17 Feb 2025, 09:39
|
General Announcement:
-
|
Notes XO Integration Meeting 12.02.2025, posted by Frederik Wolff-Fabris on 12 Feb 2025, 09:53
|
General Announcement:
- Delivery to instruments restarted this morning with good FEL performance (above the average). HXRSS in SA2 to be done during the day.
- As PRC, Maurizio Vannoni has nothing to report. So far so good.
|
Notes XO Integration Meeting 10.02.2025, posted by Frederik Wolff-Fabris on 10 Feb 2025, 09:45
|
General Announcement:
-
|
Notes XO Integration Meeting 05.02.2025, posted by Frederik Wolff-Fabris on 05 Feb 2025, 09:44
|
General Announcement:
-
|
Notes XO Integration Meeting 03.02.2025, posted by Frederik Wolff-Fabris on 03 Feb 2025, 09:39
|
General Announcement:
- Experiment tuning week is ongoing; Two downtimes happened over the weekend due to 1. an electronic component part of quench circuit of a cold magnet
in A20 (11hs) and 2. interlock issues at the injector
|
Notes XO Integration Meeting 29.01.2025, posted by Frederik Wolff-Fabris on 29 Jan 2025, 09:50
|
General Announcement:
- Steffen Hauf comments that DOC is active from today and also requests SXP and SCS to get in touch with DRC on needed nodes.
- UOM will restart next Friday at 9AM.
|
Notes XO Integration Meeting 27.01.2025, posted by Frederik Wolff-Fabris on 27 Jan 2025, 09:59
|
General Announcement:
- Maurizio Vannoni reports on behalf of XRO on the ramp-up activities over the weekend:
SA1 - positions of mirrors were found (post in Zulip) No major problems were found; Attenuators look fine;
|
Notes XO Integration Meeting 22.01.2025, posted by Frederik Wolff-Fabris on 22 Jan 2025, 09:47
|
General Announcement:
- Please call DOC number and get in touch with DRC is one needs to save data for any activity or face issues with CTRL and DAQ.
- User and Operation Meeting will start only next week 31.01.
|
Notes XO Integration Meeting 20.01.2025, posted by Frederik Wolff-Fabris on 20 Jan 2025, 09:50
|
General Announcement:
- E. Boyd reminds on the return of the beam shutter keys: actual plan is to return keys no later than Friday. The SA3 hutches are to be closed on the weekend.
- The User & Operation meeting will start from next week, Friday 31.01.
|
Notes XO Integration Meeting 15.01.2025, posted by Frederik Wolff-Fabris on 15 Jan 2025, 09:40
|
General Announcement:
- A. Galler announces that yesterday the cooling water of 20C was leaking. The reason is still to be found, as per e-mail from TS sent to the xo-info.
|
Notes XO Integration Meeting 13.01.2025, posted by Andreas Galler on 13 Jan 2025, 09:29
|
General Announcement:
-
|