  397   22 Feb 2023, 09:44 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 22.02.2023General Announcement:
- Situation of He gas: currently it is a
bit more relaxed than last year but it is
  
  396   20 Feb 2023, 11:05 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 20.02.2023General Announcement:
- Accesses to XTD10 and XTD4 are happening
this morning. The South branch sees continuation
  
  395   15 Feb 2023, 10:14 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 15.02.2023General Announcement:
-  
  
  394   13 Feb 2023, 10:05 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 13.02.2023General Announcement:
- Accelerator downtime on Saturday of 5-6
hours due to a matching capacitor located
  
  393   08 Feb 2023, 10:25 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 08.02.2023General Announcement:
- When questions or issues with operations
or beam parameters appears, please contact
  
  392   06 Feb 2023, 12:48 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 06.02.2022General Announcement:
- A. Galler shows at the TTFinfo schedule
where to find information for operation calendars.
  
  391   01 Feb 2023, 10:56 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 01.02.2023General Announcement:
- A. Galler reminds instruments to use the
Operation-2023 e-log for daily reports.
  
  390   30 Jan 2023, 09:49 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 30.01.2023General Announcement:
-  
  
  389   25 Jan 2023, 11:01 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 25.01.2022General Announcement:
-  As PRC, Raul V. thanks to CTRL and EEE
for the work with the SEPS yesterday.
  
  388   23 Jan 2023, 10:01 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 23.01.2023General Announcement:
- As PRC Jan G. says machine was tuned at
7keV for SA1 and SA2 and 700eV for SA3 with
  
  387   18 Jan 2023, 11:37 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 18.01.2023General Announcement:
- The 5Hz tests were successfully completed.
Contrary to the original schedule all tests
  
  386   16 Jan 2023, 09:54 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 16.01.2023General Announcement:
- Tomorrow and Wednesday the 5Hz test take
place; Wednesday as the pure 5Hz operation
  
  385   11 Jan 2023, 11:16 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 11.01.2023General Announcement:
- If you have a forwarded invitation for
the XO Int. meeting in your calendar, it
  
  384   09 Jan 2023, 10:10 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 09.01.2023General Announcement:
- Interlock tests light taking place today
and tomorrow, starting at Desy premises and
  
  383   19 Dec 2022, 10:01 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 19.12.2022General Announcement:
- This is the last XO Integration meeting
of this meeting.
  
  382   14 Dec 2022, 09:55 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 14.12.2022General Announcement:
- There will not be Xo Int. meeting next
Wednesday 21.12. The last meeting for this
  
  381   12 Dec 2022, 10:01 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 12.12.2022General Announcement:
- So far there is no reports of big bad effects
from the power outage on 03.12 caused by
  
  380   07 Dec 2022, 12:06 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 07.12.2022General Announcement:
- Tobias Clever informs to contact TS (Oleg
E.) in case of broken fuses (see UNSYS).
  
  379   05 Dec 2022, 09:59 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 05.12.2022General Announcement:
- Dec.3rd power an drinking water maintenance:
many thanks to TS and MKK groups for their
  
  378   30 Nov 2022, 09:55 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 30.11.2022General Announcement:
- Reminder on the Power cut activity on Dec.
3rd: please contact XO for questions.
  