Technical integration and coordination
SASE1 Status and SASE3 Readiness
|
Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther |
Not logged in |
 |
|
Message ID: 386
Entry time: 16 Jan 2023, 09:54
|
Author: |
Frederik Wolff-Fabris |
Location: |
General |
Severity: |
Information |
Subject: |
Notes XO Integration Meeting 16.01.2023 |
|
|
General Announcement:
- Tomorrow and Wednesday the 5Hz test take place; Wednesday as the pure 5Hz operation and on Wednesday there is the hybrid test. Every second pulse will not see any train.
CTRL:
- New version of Beckhoff Karabo device will be deployed today at 14:00; it shall take 5-10 mins.
DA:
- Nothing to report.
EEE:
- Continuing with remaining maintenance tasks and preparing the bring-up days with instruments.
VAC:
- Nothing to report. Tunnels XTD6 and XTD9 remain open until Wednesday.
XPD:
- Preparing for tunnel closure, stat-up and 5Hz tests.
DET:
- Gotthard1 detectors: need a firmware upgrade and will be coordinated with instruments.
ITDM:
- Announcement: on Friday exchange of SA1 devices.
XRO:
- All fine from XRO.
LAS:
- Working on the Lasers back-up; Lasers will be shut down for the 5Hz tests.
- Issue with Smaract stages being worked.
UNSYS:
- Nothing to report.
SPB:
- Nothing to report.
FXE:
- Nothing to report.
MID:
- Nothing to report.
HED:
- Nothing to report.
SCS:
- Nothing to report.
SQS:
- Nothing to report. |