SASE1 Status and SASE3 Readiness
|
Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther |
Not logged in |
 |
|
Message ID: 378
Entry time: 30 Nov 2022, 09:55
|
Author: |
Frederik Wolff-Fabris |
Location: |
General |
Severity: |
Information |
Subject: |
Notes XO Integration Meeting 30.11.2022 |
|
|
General Announcement:
- Reminder on the Power cut activity on Dec. 3rd: please contact XO for questions.
- The heating at HXQ will be switched OFF on Friday 8AM.
- There will be no available drinking water from Friday 15:00.
CTRL:
- Related to 03.12: Karabo and other topics will be shut down on Friday starting at 11:00AM.
DA:
- No updates for today.
EEE:
- In process of preparing for the power cut; groups were contacted for timeframe work.
VAC:
- Not present.
XPD:
- Preparing for power cuts.
- Ramp down day on Monday found only minor issues; very useful data were taken; XGMs were placed OFF; beam transport was brought to safe state.
DET:
- Nothing to report; no news on Jungfrau burst mode.
ITDM:
- Working accordingly to the plan.
XRO:
- Not present.
LAS:
- Lasers will be switched down from tomorrow.
UNSYS:
- Maintenance work is ongoing.
SPB:
- Nothing to report.
FXE:
- Nothing to report.
MID:
- All fine at MID; 95% of devices are already OFF.
- Reminder: on Monday TS has work in MID rack rooms; MID start back on Tuesday with maintenance work.
HED:
- Question related to cooling water for the PLC CPUs (which are not being switched OFF): Nerea J. and A. Galler confirm that water cooling is available.
SCS:
- Nothing to report.
SQS:
- Not present: on a retreat. |