Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther, Page 9 of 30  Not logged in ELOG logo
ID Date Author Location Severitydown Subject
  150   18 Apr 2017, 16:36 Andreas KochGeneralInformationTrigger and IP address

All trigger problems in XTD2 and XTD9 solved except for one: spb_xtd9_imgpi, probably a cabling issue on the camera side.

IP address problem for camera of sa1_xd2_imgpii45 solved.

  151   19 Apr 2017, 11:47 NEREA JARDONXTD9InformationMotion loop

Dear all,

Today from 13:30h  Mahadi and Natalia will be doing local tests in the PBLM in Rack 1.14 of XTD9, therefore, if someone will be working in the following racks of XTD9, will loose connection to the Motion loop.

Thank you and best regards,

  152   19 Apr 2017, 11:49 Tobias HaasGeneralInformationStatus and Plans after 09:30 meeting

Tunnels XTD2 and XTD4 are closed, XTD9/10 remain open

Vacuum:

  • Running stably
  • Work continues on M3 in XTD9 and on the vacuum in XTD10 

EPS Loop:

  • Input from undulator still missing. This requires  fixing a cable in balcony rooms and then testing

PBLM/Motion Loop:

  • Work on the PBLM motors (ELMO controller) continues.
  • It appears that the uneven movement is due to improper setting of motor parameters

Imagers

  • Trigger problem reported yesterday was due to a cabling issue. Apparently during work on the relevant rack cables were unplugged and then wrongly put back
  • Network issue with pop-in (245) in XTD9 solved

SPB Tunnel components

  • Crate with "problem on signal pins" was brought to the lab and checked. Everything was ok. Problem was due to spurious measurement.

Karabo:

  • PSLIT was tested successfully yesterday
  • Behaviour of Karabo when a loop goes down needs to be made more graceful. 
  • Cleanup continues

Tasks for today:

Note: All loops should be left running and no changes to Karabo.

  • Prepare mirror M3 installation
  • Continue testing of PBLMs in XTD9
  • Continue testing of SPB tunnel loop

Other topics

  • None
     

 

  153   20 Apr 2017, 10:25 Tobias HaasGeneralInformationStatus and Plans after 09:30 meeting

 Tunnels XTD2 and XTD4 are closed, XTD9/10 remain open

Vacuum:

  • PLC/Karabo Running stably
  • Local tests of ion pumps in XTD9 being done by J. Eidam
  • Work continues on M3 in XTD9 and on the vacuum in XTD10 
  • DPS in XTD9 should be integrated into the vacuum loop. This requires a cycling of the loop. Timing should be coordinated with WP74 because of XGM in XTD2. Unfortunately nobody from WP74 attended the meeting. Hence it was decided to perform the work tomorrow morning.

EPS Loop:

  • Checks for the signal from the undulators and for the fast valve will be done with DESY MPS today

PBLM/Motion Loop:

  • Work on the PBLM motors (ELMO controller) continues.
  • Yesterday it was possible to align the screens 
  • There is a resource problem when trying to read out the cameras. For this reason an additional server needs to be set up dedicated to acquiring the images from the cameras.

SPB Tunnel components

  • Crate that was checked in the lab yesterday was moved back into the tunnel
  • The unstable support of the imager was fixed
  • B. Weinhausen and M. Messerschmidt are testing
  • All modules necessary for loops 1 & 2 were received from Poland
  • Waiting for the "Freigabe" of the cables for SPB Optics

FXE

  • Loops 1,2 and 4 are waiting for input from EETF
  • Loops 3&5 are running
  • No visible testing activity from FXE team

Karabo:

  • Cleanup continues

Tasks for today:

Note: All loops should be left running and no changes to Karabo.

  • Prepare mirror M3 installation
  • Continue testing of PBLMs in XTD9
  • Continue local tests of ion pumps in XTD9
  • Continue testing of SPB tunnel loop

Tasks for tomorrow:

  • Cycle vacuum loop for inclusion of DPS in XTD9

Other topics

  • Weekly SASE1 Readiness meeting tomorrow at 09:00 in XHQ 1.173
  • L. Samoylova requests access to XTD2 to install another webcam
  • Magnet current tests will likely continue through Wednesday in XTD2. Maintenance day to be shifted accordingly probably to Thursday/Friday. More information later
  154   20 Apr 2017, 17:18 Tobias HaasGeneralInformationMaintenance/Access in KW17

 In KW17 there will be NO maintenance day on Tuesday (25.04.) 

 
On Monday (24.04.) morning up to about 11:00 we will have the TÜV approval of CS8. During that time 
NO access of "other people" to the XTL tunnel is possible. After the TÜV approval 
up to 13:00 there will be the possibility for URGENT access to the XTL. Access requests 
have to written to the logbook/access requests entry. 
 
The tunnel XTL/XTIN will stay in interlock, access will be possible by ZZ only. 
 
The northern branch XTD2->XS3->XTD4->XDU2 will stay closed, in order not to interrupt the 
magnet commissioning. 
 
This elogbook entry was sent to following experts: 
xfel-opl@desy.de RC mailing list  
  155   21 Apr 2017, 09:59 Jan GrünertGeneralInformationXGM status

XGM status 21.4.2017

During Easter break, the two XGMs in the control system (XTD2+9) had no issues.
XGM@XTD10 however had an issue: tuesday morning it was found that all pumps had stopped. The scroll pump showed an error. UPS apparently had excess load sunday evening 19h30 but couldn't send email (network error). Possibly vented with tunnel air up to 10mbar since that time. Investigation is ongoing.

Thursday enabled DOOCS pressure reading of XGM in XTD10, UPS rechecked

System surveillance on coming weekend: Jan and Theo 1 day

Other remarks:
- WP74 staff have received their dosimeters for ZZ access if required
- some automatic monitoring and info system is needed soon, e.g. karabo to NAGIOS connection

 

  160   21 Apr 2017, 14:36 Tobias FreyermuthXTD9InformationSASE EPS RACK 1.14 disconnect

We have to disconnect the EPS crate in RACK 1.14 in order to check the interface to the MPS.

I will keep you updated

  161   21 Apr 2017, 15:22 NEREA JARDONGeneralInformationOCD

Dear all,

The service of On-call Duty will be available from AE group during weekend in this number: 6442

Please make a post with the OCD numbers from CAS, WP74 and WP73.

Thank you and bests.

  162   21 Apr 2017, 15:26 Jan GrünertXTD2InformationCycling of PLC loop (shutdown and restart) - effects on XGM XTD2 and XTD9
Together with Nerea and Wajid and Alessandro

  • 10:00 closed vatterflies at XTD9 and XTD2 from Karabo
  • Florian is at XTD9 next to the XGM
XTD9: 
  • LOOP re-cycle
  • All valve closed and scroll off (turbos in unknown state; Florian in tunnel sees 990 Hz)
  • Scroll and turbos switched ON
  • Angle valve opened over Karabo
  • Problem to open gate-valve
  • Set Karabo offline
  • Nerea switched turbos at XTD2 ON (XTD9 were on) by PLC
  • Karabo is reconnected to PLC (brought online again)
XTD2: (with Alessandro) 
  • Scene optimized: Turbo speed, new prevac display, and preliminary scroll icon
  • Open KF angle and gate valve (follow "XGM vacuum incident procedure")
XTD9: (with Alssandro) 
  • Scene optimized: Turbo speed, new prevac display, and scroll icon
  • Open angle and gate valve (follow "XGM vacuum incident procedure")
New project created "SASE1-XGM" which contains both XTD2 and XTD9 XGM vacuum projects, thus scenes from both can be opened from one GUI simultaneously.

11:55 XTD9 vatterflies OPEN 
12:00 XTD2 vatterflies OPEN  
      (V10120V could only be opened after shutdown of device and re initialization) 
 
Maybe upper pressure probes need new calibration -> Check formula 
Prevacuum pressures: 
  • XTD9: 6.4E-4 mbar (G11081P)
  • XTD2: 2.5E-2 mbar (G10100P) and 1.2E-3 mbar (G10101P)

Summary : both XGMs in XTD2 and XTD9 are now back in normal pumping operation, and they were never exposed to more than a few 10E-6mbar. Good. But it took 2 hours and 4 experts.

  164   21 Apr 2017, 17:22 Sandor BrockhauserGeneralInformationCAS OCD April 22-23

In case of any problems, please, call the CAS personnel on 9-6443, 9-5630, or 9-6840.

Have a nice week-end, Sandor

  165   24 Apr 2017, 11:08 Tobias HaasGeneralInformationStatus and Plans after 09:30 meeting

 

Tunnels XTD2 and XTD4 are closed, XTD9/10 remain open

Karabo:

  • Bad crash of GUI server occured on Friday.
  • System running over the weekend but performance of the GUI was sluggish
  • There appears to be a resource leak. Experts are working on it.
  • Fix is urgently needed for continued testing

Vacuum:

  • Systematic tests of ion pumps start again since V. Bondar is back
  • Fix for the interlock of the gas section in XTD9 to be deployed today.
  • Gas system tests to be done starting tomorrow

PBLM/Motion Loop: 

  • There is a resource problem when trying to read out the cameras. This problem will be reconsidered once the general issue with the GUI server is solved.

SPB Tunnel components

  • The Renishaw encoders can not be read out via the PLC
  • The problem appears to be that the signal level is not TTL. 
  • T. Freyermuth is working on a fix
  • Work can continue once the encoder problem is solved
  • The same problem also affects FXE components
FXE
  • FXE team not represented

 

Tasks for today:

  • Re-deploy vacuum loop for the tests of the gas section tomorrow
  • Identify a fix/workaround for the GUI server resource problem
  • Find a solution for the Renishaw encoder problem
  • Restart testing of ion pumps in XTD9

Tasks for tomorrow:

  • Test of gas section interlock

Other topics

  • J. Grünert requests to put the XGM in XTD10 under PLC/Karabo control
  • This would require extensive work by several groups (ITDM, AE, CAS) and cannot be done at the moment in view of established priorities

 

  166   25 Apr 2017, 10:49 Adriano ViolanteGeneralInformationStatus and Plans after the 9:30 meeting

XTDs Info:

Tunnel XTD2 will be accessible this Thursday, 27.04. between 9 and 12. Dosimeter and General radiation training required. Access requests should go to T.Haas.

XTD10 will be closed starting from this Thursday, 27.04. at 12:00

Provided that the authorities give the "go ahead", DESY plans to put beam in XTD2 on Thursday's evening.

 

Karabo:

  • System running  but performance of the GUI still sluggish
  • There appears to be a resource leak. Second server will be set up tomorrow as workaround. Experts are working on it.
  • In parallel experts are working on a definitive solution
  • Deployment today on a new beckhoff device for the decodification of PLC error messages.

Vacuum:

  • Systematic tests of ion pumps started again

PBLM/Motion Loop: 

  • There is a resource problem when trying to read out the cameras. This problem will be reconsidered once the general issue with the GUI server is solved.
  • ASilenzi will ask Natalia for acceptance test definition for PBLM
  • Motion loop will be down until 10:30 for update. An entry will be written when the loop is again up. 

SPB Tunnel components

  • The Renishaw encoders can be read and positions are reliable. An error message is coming from the encoder and is probably due to a wrong voltage level delivered to the encoder. The encoders can be operated in this condition.
  • T. Freyermuth is in contact with the encoder company tu understand the problem and work on a fix
  • The same problem also affects FXE components
  • The cameras operated at 1Hz deliver delayed images. 1/3 Hz operation (almost live mode) is OK - probably related to GUI memory issues

FXE

  • Encoders of Loop1 have the same error message as SPB - the encoder positions are reliable - local components test can go on (e.g. OGT1)
  • Encoders of loop2 are not powered - AE to investigate

 

Tasks for today:

  • Identify a fix/workaround for the GUI server resource problem
  • Deployment of a beckhoff device for the decodification of the error messages.
  • Find a solution for the Renishaw encoder problem SPB Tunnel/ FXE Loop1
  • Investigation of the FXE Loop2 encoders power
  • Continue testing of ion pumps in XTD9
  • Test of gas section interlock in XTD9

Tasks for tomorrow:

  • Setup of the second server for karabo GUI
  167   25 Apr 2017, 10:51 NEREA JARDONGeneralInformationMotion loop

Dear all.

Motion loop is running again.

Thank you

  168   25 Apr 2017, 13:49 Raúl Villanueva-GuerreroXTD9InformationXTD9 Complete Gas Section (DPS-XGM-DPS) Isolation Interlock tested - Not Working (yet)

 After some minor issues, the first test has been done today and the interlock wasn´t triggered despite the conditions were met (also visible in Karabo).

 

This requires intervention and revision from AE

 

The next try-out should be done as soon as possible during this week.

 

Regards.

 

Raúl, Benoit and Valerii

 

 

 

  169   25 Apr 2017, 14:20 NEREA JARDONGeneralInformationMotion loop

Dear all,

We have to make some changes again into the Motion loop. Therefore I will do an update at 14.45h.

I will keep you inform when it is running again.

Thanks!

  170   26 Apr 2017, 09:10 NEREA JARDONGeneralInformationVacuum Loop

Dear all,

We need to update the Vacuum loop in order to correct and add some configuration to the interlock conditions.

It would be running in few minutes again.

Thank you!

  171   26 Apr 2017, 09:14 NEREA JARDONGeneralInformationMotion and Vacuum

Vacuum is running again and Motion also, yesterday I forgot to update you about the Motion PLC.

Sorry and best regards,

  173   26 Apr 2017, 11:44 NEREA JARDONGeneralInformationMotion loop

Dear all,

I will do an update of the motion loop so the PBLM could be tested. I will do it know and the PLC will be again available in few minutes.

Thank you!

  174   26 Apr 2017, 11:55 Adriano ViolanteGeneralInformationStatus and Plans after the 9:30 meeting

 

XTDs Info:

Tunnel XTD2 will be accessible this Thursday (TUNNEL OPEN, NO ZZ), 27.04. between 9 and 12. Dosimeter and General radiation training required. Access requests should go to T.Haas.

XTD10 will be closed starting from this Thursday, 27.04. at 12:00

Provided that the authorities give the "go ahead", DESY plans to put beam in XTD2 on Thursday evening.

Access to XSDU2 being clarified - separate entry will be posted.

Karabo:

  • System running  but performance of the GUI still sluggish - CAS was not able to reproduce the problem, still under investigation
  • Second server has been set up as workaround.
  • In parallel experts are working on a definitive solution
  • Deployment today on a new beckhoff device for the decodification of PLC and interlock error messages. 

Vacuum:

  • Systematic tests of ion pumps ongoing. in XTD 9 two controllers/beckhoff terminal for pumps were wrongly connected (exchanged). To reconnect the controllers in the right orders the loop has to be interrupted. This will be done after the vacuum test on the XGM is done.

PBLM/Motion Loop: 

  • There is a resource problem when trying to read out the cameras. This problem will be reconsidered once the general issue with the GUI server is solved.
  • ASilenzi will discuss offilen with Natalia the acceptance test definition for PBLM
  • List of errors and relative solution concerning ELMO absolute encoder implementation being worked out by AE/CAS

SPB Tunnel components

  • Error message fore the Renishaw encoders is coming from wrond specifics of the interpolator between encoder and input terminal. This is due to wrong datasheet provided by the company. This is not a problem for reading of the encoders and their reliability. Error signal is currently ingnored
  • The same problem also affects FXE components
  • The cameras operated at 1Hz deliver delayed images. 1/3 Hz operation (almost live mode) is OK - probably related to GUI memory issues

FXE

  • Encoders of Loop1 have the same error message as SPB - the encoder positions are reliable - local components test can go on (e.g. OGT1)
  • Encoders of loop2 are not powered - AE to investigate today

 

Tasks for today:

  • XGM vacuum test and solution implementation of pump restart in Karabo
  • GUI server resource problem ongoing
  • Deployment of a beckhoff device for the decodification of the error messages.
  • Find a solution for the Renishaw encoder problem SPB Tunnel/ FXE Loop1
  • Investigation of the FXE Loop2 encoders power
  • Continue testing of ion pumps in XTD9
  • Vacuum signal alarms to be checked by AE,Harlad, Janni
  • Implement and test the CRLs in XTD2 in the Beckhof loop for test.

Tasks for tomorrow:

  • Vacuum signal alarms to be checked by AE,Harlad, Janni
  • Implement and test the CRLs in XTD2 in the Beckhof loop for test.
  • Checking of the absober for first lasing (inc. filter chamber). 
  175   26 Apr 2017, 12:58 Adriano ViolanteGeneralInformationXSDU2 access

 The XSDU2  area will be open (as XTD2) tomorrow between 9 ans 12. To register the access, please send also in this case a mail to T.Haas.