Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther, Page 3 of 30  Not logged in ELOG logo
ID Date Author Location Severitydown Subject
  12   24 Nov 2016, 11:38 Frederike WittmaackGeneralInformationMeeting Minutes 17 Nov 2016
http://tinyurl.com/hxaxdm9
  13   02 Dec 2016, 11:43 Sabine CunisXTD2Informationnew components list

please find the new (extended) components list under the old link given in the minutes http://tinyurl.com/zn7otsa ,

and check whether all components are included and charakterized by the correct data.

 

  14   02 Dec 2016, 11:46 Frederike WittmaackGeneralInformationMeeting Minutes 25 Nov 2016
http://tinyurl.com/jydty26
  15   02 Dec 2016, 11:47 Frederike WittmaackGeneralInformationRemote access to control network form
http://tinyurl.com/jskzj2h
  16   07 Dec 2016, 17:09 Frederike WittmaackGeneralInformationMeeting Minutes 02 Dec 2016
http://tinyurl.com/hzq7ats
  17   09 Dec 2016, 15:31 Frederike WittmaackGeneralInformationMeeting Minutes 09 Dec 2016
http://tinyurl.com/gqykf7z
  18   19 Dec 2016, 09:32 Frederike WittmaackGeneralInformationMeeting Minutes 16 Dec 2016
http://tinyurl.com/zzzy7sd
  19   19 Dec 2016, 09:44 Frederike WittmaackGeneralInformationXGM Safe State Definition
as defined by Jan Grünert: available on Alfresco: XGM-safe-state.docx and available at N:\4all\intern\User data\wp74\Devices\11-1_XGMD\03 - Components\XGM-safe-state.docx
  20   03 Jan 2017, 08:46 Frederike WittmaackGeneralInformationMeeting Minutes 23 Dec 2016
Please follow the link to view the minutes: http://tinyurl.com/h3qspzz
  21   09 Jan 2017, 10:47 Sabine CunisXTD2InformationVCTF-list updated

The VCTF-components-list  has been updated. Labels on components, as far as visible, are in accordance with names in list.

... please, check for consistency, when naming and labeling XGM components!

  22   24 Jan 2017, 08:17 Tobias HaasXTD2InformationSTATUS UPDATE: XTD2 Differential Pumping Modules running under interlock control

 Post on behalf of Raul Villanueva:

As we just finished the exhaustive testing and final adjustments of local
test and the interlock program for each of the turbopumps at each
Differential Pumping Sections in XTD2 Tunnel, we are happy to announce
that the system has been released and is up and running smoothly and under
control.  That means that the isolation gate valves in front of each
turbopump is open and therefore the latter is pumping already the beamline
as expected during the upcoming operation phase of the facility. That also
means that WP74, after having already received the wiring documentation
from the Vacuum Group can proceed with the same protocol to keep the whole
gas section in XTD2 in a consistent fail-safe status.

With this positive news, we wish you to have a nice evening,

Regards,

Raúl, Tobias and Nerea,

 

  23   24 Jan 2017, 08:21 Tobias HaasGeneralInformationKarabo Names in Vacuum component list

Post on behalf of Harald Sinn:

 for the non-vacuum part of WP73 we have the following situation: 

Last Friday Alessandro and myself had a meeting and agreed to use the names given in the document
 
 
(CAS inbox for software requirement documents)
 
The only change will be in the naming of the power supplies for the hard X-ray mono 
(which will be changes to analog input /output)
 
You can use the names is this document therefore already. However, Alessandro will 
create Excel tables out of it, which will be then used in the future for reference. 
Also the extension to SASE3/2 will be done in this Excel document. 
 
Best regards 
 
Harald
 
  24   24 Jan 2017, 08:23 Tobias HaasGeneralInformation Karabo Names in Vacuum component list

 Post on behalf of Alessandro Silenzi:

 

please find below the link to the first version of the master component list and the link to the direct download:
 
 
 
Please give your comments directly to me to avoid confusion.
 
The next steps after collecting your input, will be to implement a test in the Firmware project generation that will test the deviceIds against this list.
 
Best regards
 
Alessandro Silenzi
 
  25   24 Jan 2017, 18:36 Alessandro SilenziGeneralInformationMore items in the master equipment list

Master Component list is being updated.

https://docs.xfel.eu/share/proxy/alfresco/api/node/content/workspace/SpacesStore/1c6c10cd-d741-410d-bd05-bb00944514dc/MasterEquipmentList.xlsx?a=true

Best regards

Alessandro

  26   26 Jan 2017, 13:10 Tobias FreyermuthXTD2InformationModification of the vacuum PLC loop

The PLC program was modified and downloaded to the PLC, due to allow work on the XGM crate in rack 1.3.

The PLC vacuum loop includes now all vacuum crates in the racks from rack 1.1 to rack 1.7 except rack 1.3 (XGM)

  28   27 Jan 2017, 09:25 Tobias HaasGeneralInformationSoftware Report

Post on behalf of S. Brockhauser

 Since I am in Grenoble and visiting ESRF, I will not be able to give you the report in person. Instead Alessandro can give you a Summary.

In fact:
- we did collect the full list of the Karabo names for all the equipments involved
- we have started our sprint and we are on track
As next things:
- we are collecting all the required Karabo(!) default parameters
- we plan to finish the sprint as planned and presented last time.
Until now we have not experienced and obstacle.

Best wishes
Sandor

  29   27 Jan 2017, 10:22 Thomas TschentscherXTD2InformationComponent table update
Attachment 1: Components-XTD2-9.xlsx
  30   01 Feb 2017, 17:26 Jan GrünertXTD2InformationStatus of several XTD2 wiring tasks - on behalf of Bernard Baranasic
Dear all,

 

today I connected XGM Gas Supply to Beckhoff terminals in WP73 Vacuum crate in Rack 1.3.
On Gas Panel, HUBA gauge is still not replaced, so it is not connected, I talked to Florian yesterday and give him an idea how we can connect this gauge and other signals for Gebäudeleittechnik (trough wago terminals).
Next step for this crate should be connection to all pump controllers and other vacuum equipment, after this crate should be connected to the tunnel vacuum loop. I assume that Torben and Marc can do this together with AE and Vacuum group, so I didn't take any actions...

 

Additionally in this crate we should connect Inhibit signal from HV iseg crate, for this we need to add:
Proposal from NC:
"I did not test it, to 'create' a TTL we can use either
es9505+es2624 or es9505+es2124
the only difference is that the ES2124 is short-circuit proof, the ES2624  is not, that means that in this case a Flink fuse ~0.3A-0.5A should be inserted."
- WP74 don't have these terminal here and if we order now it will take some time (I am not sure what to do because we don't have proven connection).

 

In Rack 1.7 I connected Inhibit connection to WP73 vacuum crate (terminals EL9505 & EL2624), but cable from MPOD crate to Beckhoff crate is still not there. Torben said that he has connectors so I believe he can connect according to electrical drawings (these pages are added to XTD2 MCP drawings on Alfresco)

 

In Rack 1.5 I tested FEL imager EPS switch and find out that Beckhoff terminal DI (ES1008) is not working (24V is on input, but there is no light on LED, all channels are the same).
EPS switch is removed From FEL imager, and I will reconnect it to Normal Open connection.

 

Best Regards,

___________________________________________

Bernard Baranasic

  32   02 Feb 2017, 14:29 Richard BeanXTD9InformationSPB/SFX updates to component table

Table updated with status of SPB/SFX devices at end of XTD9 in preparation for SASE1 readiness meeting on 03.02.17

Attachment 1: Components-XTD2-9.xlsx
  33   02 Feb 2017, 16:56 Tobias HaasGeneralInformationInstallation List Update

 Updates as of 2 Feb 16:30

Attachment 1: Components-XTD2-9.xlsx