Technical integration and coordination SASE1 Status and SASE3 Readiness
  Joint Operation and Readiness Logbook, Contact: T.Haas, A. Violante, G. Wellenreuther, Page 2 of 30  Not logged in ELOG logo
ID Date Author Location Severitydown Subject
  245   18 May 2017, 11:57 Jan GrünertGeneralProblemVacuum issue in XTD9 during cycling of PLC loop yesterday

During the usual recovery procedure after the planned and announced cycling of the SASE1 VAC loop yesterday, we observed a serious mistake by somebody:

The gatevalve(s) of the DP section in XTD9 were opened before the related turbo pumps were (fully) operating.
This caused a pressure increase on the UHV-side to briefly 1E-2mbar (!) and for about 30min to 1E-3mbar before this was cured.
Essentially the prevacuum side gases entered the UHV-side through the DP-turbos, that's not good at all.
Especially it would be tragic, if we had the XGM high voltages on during such a mistake (which was luckily not the case)
Below is the pressure record of the XGM UHV vacuum gauge.

This must not happen again ! Therefore please observe the following points:
1) after PLC reboots, these valves shall only be opened by the experts who know the correct sequence
2) the pressures and TP operation must be verified before opening these valves.
3) WP74 (e.g. Jan or Theo) and VAC (e.g. Raul) must be informed about a planned recycling of the VAC loop (this is an established scheme and always worked very well, also yesterday)

https://ttfinfo.desy.de/XFEL-WP74-elog/data/2017/20/17.05/2017-05-17T14:02:31-03.jpg

Explanations to graph:
13h30 the preparation of the cycling started with closing the XGM vatterfly valves by WP74
14h00 apparently the gate valves of the entire gas section closed at the PLC reboot which increases slightly the pressure at the XGM
around 14h18 the pressure shoots up although nothing changed at the XGM, and it is found that DP gatevalves are open without full operation of the associated turbos
around 14h50 (after some cross-checking and phone calls) the concerned gate valves were closed and the vatterfly valves at the XGM were opened to bring the XGM (and the entire gas section) down to about 1E-7mbar

 

  258   21 May 2017, 17:10 Dennis GoeriesXTD2ProblemSASE1 Imager FR

Dear all,

we are experiencing constantly crashes with the photonic science camera in the SA1 imager FR. We found now out

- If the pixel format is set to Mono16 the camera will most likely crash, go in error.

- Before instantiation the camera may show Mono16. During connection Karabo but gets a fresh update and the field in the scene switches to Mono8.

 

Please don't apply Mono16 again.

Best wishes, Dennis

  276   03 Jun 2017, 22:39 Alessandro SilenziGeneralProblemSOLVED BROKER Problem

A pile up in the BrokerQueue was detected by CAS monitoring system and

a response action from the On-Call personnel was triggered.

Regrettably, the following device servers have been shutdown and will be re-instantiated.

- Dataloggers
- alarm server
- camera servers
- Motion Loop and Vacuum Loop beckhoff servers

Sorry for the inconvenience

  286   09 Jun 2017, 21:40 Gabriele GiovanettiXTD2ProblemMotor in error

Called at 21.18 for SASE1_XTD2_IMGSR/MOTOR/Y being in error.

Solved by pressing 'Reset' button in Karabo GUI

  334   14 Jul 2017, 12:44 Martin DommachXTD9ProblemFast Valves in XTD9

Dear all,

the fast valves in XTD9 were causing some trouble. From time to time they collect some electrical noise what triggers the valve. The pressure reading on the valve controller then shows oscillations of up to 10^-5 mbar, while the pressure around the fast valve gauges in the beamline is in the 10^-9 mbar range.
To operate the beamline in the meantime I have opened and disabled both fast valves. 

This needs further investigation on the service day next wednesday.

Best regards,
Martin

  366   22 Aug 2017, 09:48 Hugo Silva SantosGeneralProblemKarabo down in tunnel

Dear All,

We have a issue on the control servers and we are already working on it...

Best,

Hugo

  367   22 Aug 2017, 10:24 Hugo Silva SantosGeneralProblemKarabo down in tunnel

Dear All,

We solved the incident and the services are running normally. We are still try to investigate, as far as we know we have some "zumbies" process running in the GUI servers and it was not consuming the HEATBEATs.

Hugo Silva Santos wrote:

Dear All,

We have a issue on the control servers and we are already working on it...

Best,

Hugo

 

  440   09 Jan 2018, 10:32 Martin DommachGeneralProblemShutdown of compressed air distribution in XTDs today

Dear all,

we got the information from MKK, that they have to fix a leak in the main compressed air line. Therefore they will close the valves to the tunnels for approximately one hour starting today at 1 p.m.

Please do not use the compresed air system in the tunnels during that time with air driven tools or air guns, as the volume of the distribution systems acts as a buffer.

Regards,

Martin

 

  492   25 Mar 2018, 10:57 Gerd WellenreutherXHEXPProblemFXE emergency power-off has been triggered

Dear all,
apparently the Emergency Power-Off at FXE was triggered at around 10:00 - 10:30 (my estimate). As far as I know power has been switched on again. BKR / PRC have been informed. More information will be provided by TS / Torsten Schön soon.

Edit: T. Schoen is on site and can be contacted under 0160 977 287 97

Regard, Gerd

  1   26 Oct 2016, 13:55 Tobias HaasGeneralInformationStart of Logbook

Dear Colleagues,

in the future we would like to use this mechanism to record and exchange information that concerns the work done within the context of this task force. Please use this generously. We shall also put a link to the minutes after each weekly meeting.

 

regards,

 

Tobias 

  2   26 Oct 2016, 14:26 Tobias HaasGeneralInformationMinutes of last week's meeting

 http://tinyurl.com/gvvv392

  3   03 Nov 2016, 12:58 Alessandro SilenziXTD2InformationCurrent PLC-Karabo Conflict

Tobias Freyermuth and me worked on the system and as of last night, we found two new issues between Karabo and the PLC interlock:
 - one is a Karabo issue from the Interlock PLC interaction, the Karabo device waits for a PLC response that does not come when the PLC is interlocked (i.e. Karabo wants to open a valve but the PLC correctly refuses and ignores the command)


 - one is a PLC issue, the interlock is not triggered in all cases after testing (e.g. a ion pump out of set point does not closes a gate valve closure as specified).

The first one was reproduced with the BeckhoffSim simulation. It can therefore be fixed by CAS without dependencies from AE (except for the next integration test).

  4   03 Nov 2016, 17:00 Sabine CunisXTD2Informationoverview of required racks

just for reference ... here are pictures and schematics of the racks which are involved in the current commissioning.

Attachment 1: VCCT_Rack_1p06_b.jpg
VCCT_Rack_1p06_b.jpg
Attachment 2: VCCT_Rack_1p07_b.jpg
VCCT_Rack_1p07_b.jpg
  5   04 Nov 2016, 08:03 Frederike WittmaackGeneralInformationMinutes of last weeks meeting (Oct 28, 2016)
http://tinyurl.com/jy5rsbx
  6   04 Nov 2016, 14:22 Frederike WittmaackGeneralInformationMinutes - Meeting November 4, 2016
http://tinyurl.com/jbog6tz
  7   04 Nov 2016, 18:08 Alessandro SilenziGeneralInformationBeckhoffDevices back to responsive

 I reproduced the behaviour of the PLC on beckhoffSim. This reproduces the same behaviour seen in the tunnel devices (devices hang).

Implemented the fix and verified the correct behaviour with beckhoffSim.

Fixes will be verified next Monday with the tunnel system.

Have a nice weekend

Alessandro

 

ps: For future reference:

beckhoffSim  tags/1.1.0-1.4  (implements the recent plc behaviour (framework tag N/A Could not find tobias))

beckhoffDevices tags/2.0.1-1.4 hangs

beckhoffDevices tags/2.0.2-1.4 does not

 
  8   07 Nov 2016, 19:15 Alessandro SilenziXTD2InformationKarabo Installation back to normal

 Karabo to PLC communication has been tested successfully in the SA1 Vacuum installation.

in attachment:

OK.png -> Initial Status, all OK

interlocked.png -> pump P10300I is turned off -> Setpoint -> off -> Valve automatically close and set "Interlock OK" to false

afteron.png ->  pump P10300I is turned on again but-> Setpoint -> off -> Valve automatically close and set "Interlock OK" to false

backToNormal.png -> Like initial status but valves stay closed

 
Attachment 1: OK.png
OK.png
Attachment 2: interlocked.png
interlocked.png
Attachment 3: backToNormal.png
backToNormal.png
Attachment 4: afteron.png
afteron.png
  9   09 Nov 2016, 15:36 Tobias HaasGeneralInformationUpdate of Component list

I have included the status columns provided by Alessandro and Sandor in the component list. Please find it in the usual location here: http://tinyurl.com/zn7otsa

Attachment 1: elog.tiff
  10   11 Nov 2016, 15:43 Tobias HaasGeneralInformationMandate for the Extension of the Vacuum Controls Commissioning Task Force

The Vacuum Controls Commissioning Task Force initially helped to get the vacuum components extending from the gate valve at 2678 m to the gate valve at 2730 m in XTD2. This comprised the valves and pumps and the associated vacuum interlock logic. The necessary components were all installed and locally tested. As the next step the PLC firmware for the control of these devices was generated including the interlock logic. Finally the system was connected to version 1.47 of Karabo, which was able to monitor and control all components. A live demonstration is currently still outstanding.

 

As the next step the vacuum section considered should be extended upstream to include all components up to the gate valve at 2630m. In addition to vacuum components this should include the installed photon beam line components. The goal is to include all these systems into one continuous vacuum, commission all systems locally, generate the PLC firmware, implement the required vacuum interlocks, monitor the state of the system remotely via the PLC command line interface and eventually connect to Karabo and monitor and control the system via Karabo remotely using the consolidated version 2.0. While this commissioning effort is going on, development should occur on three days during the week (Mo-Wed) while the system should be operated continuously during the remaining time, thus also testing long-term stability. This should be achieved by the end of 2016.

  11   14 Nov 2016, 14:10 Frederike WittmaackGeneralInformationMeeting Minutes 11 Nov 2016
http://tinyurl.com/juhjcbf