  382   11 Sep 2017, 14:03 Gerd WellenreutherGeneralInformationTAS updatedDear all,

I updated the tunnel access schedule
to reflect the access to the XTDs tomorrow.
  
  383   11 Sep 2017, 14:04 Gerd WellenreutherGeneralInformationTAS updatedDear all,

I updated the tunnel access schedule
to reflect the access to the XTDs tomorrow.
  
  386   18 Sep 2017, 17:39 Gerd WellenreutherGeneralInformationTunnel access schedule updatedDear all,

XTD9 will be accessible tomorrow
until the afternoon, but access should be
  
  388   22 Sep 2017, 16:06 Gerd WellenreutherGeneralInformationStatus and plans after SASE1 Status/SASE3 Readiness MeetingGeneral


First users have done experiments
- despite the current problems it appears
  
  392   29 Sep 2017, 10:43 Gerd WellenreutherGeneralInformationStatus and plans after Readiness MeetingSPB (A. Mancuso): 

 

​Users
are in good shape
Beam operation
  
  398   06 Oct 2017, 11:15 Gerd WellenreutherGeneralInformationStatus and plans after Readiness MeetingSPB (B. Weinhausen): 


​Users
took good data
Problems occured
  
  404   16 Oct 2017, 17:11 Gerd WellenreutherGeneralInformationTunnel access schedule updatedDear all,

I updated the schedule for the
tunnel access in the upcoming weeks based
  
  415   06 Nov 2017, 13:58 Gerd WellenreutherGeneralInformationTunnel access schedule updatedDear all,

I updated the TAS to include the
upcoming user runs up to and including the
  
  420   14 Nov 2017, 11:05 Gerd WellenreutherGeneralInformationTunnel access schedule updatedDear all,

I received updates from DESY (M.
Hüning) about how the access to the
  
  436   18 Dec 2017, 10:48 Gerd WellenreutherGeneralInformationStatus and plans after Readiness MeetingPSPO:


M. Areste presented a report
about the progress so far achieved in the
  
  439   09 Jan 2018, 10:14 Gerd WellenreutherGeneralInformationAccess to XTDsDear all,

according to H. Sinn the closing
of the XTDs 2, 4 and 10 will be delayed until
  
  448   12 Jan 2018, 11:10 Gerd WellenreutherGeneralInformationStatus and plans after Readiness Meeting

  
  455   22 Jan 2018, 10:36 Gerd WellenreutherGeneralInformationStatus and plans after Readiness MeetingSPB/SFX:


2nd AGIPD intervention
will be finished today.
SE worked
  
  460   29 Jan 2018, 09:29 Gerd WellenreutherGeneralInformationStatus and plans after SASE1 Status/SASE3 Readiness Meeting 26.1.SPB/SFX:



Preparation
for the mirror installation were ongoing
  
  461   29 Jan 2018, 10:02 Gerd WellenreutherGeneralInformationLink to "Access Request" gathering for tunnels after the shutdownDear all,

please enter your access requests
to the tunnels into the list provided by
  
  479   23 Feb 2018, 15:54 Gerd WellenreutherGeneralInformationStatus and plans after Readiness Meeting 23.02. Photon Run Coordinator (L. Samoylova):


SASE1 tuning is ongoing
(350 microJ)
SASE3 3000microJ
SASE1
  
  492   25 Mar 2018, 10:57 Gerd WellenreutherXHEXPProblemFXE emergency power-off has been triggeredDear all,
apparently the Emergency Power-Off
at FXE was triggered at around 10:00 - 10:30
  
  497   04 Apr 2018, 13:43 Gerd WellenreutherGeneralInformationStatus reports after dispatch meeting 13:00 4.4.SPB/SFX:


Mirror installation next
week


FXE:
  
  514   18 Apr 2018, 15:06 Gerd WellenreutherGeneralInformationTunnel closing after shutdownDear all,

below please find the hottest and
most up-to-date times for the closing of
  
  557   03 Sep 2018, 09:49 Gerd WellenreutherGeneralInformationStatus report after dispatch meeting 09.30 SPB / SFX:


Experiments are ongoing,