Tunnel access schedule updated, posted by Gerd Wellenreuther on 21 Jun 2017, 14:13
|
Dear all,
I extended the tunnel access schedule up to the beginning of the shutdown (3.7.). As always, you can find it under https://docs.xfel.eu/share/page/site/PSC/wiki-page?title=Tunnel_access_schedules
Access request to Harald Sinn. Works during the shutdown have to be reported to Harald Sinn and Dirk Nölle for scheduling. |
Status and Plans after 09:30 meeting, posted by Tobias Haas on 21 Jun 2017, 10:21
|
XTDs:
DESY requests the KMONO to be commissioned since the K Values of the undulators appear not to be as accurately calibrated as originally
advertised. Management decided to put KMONO at the top of the priority list for this reason. W. Freund should work together with Mahadi and Nerea on getting |
Access to tunnels updated, posted by Gerd Wellenreuther on 19 Jun 2017, 16:55
|
Tunnel access schedule has been updated, access for XTD9 on Wednesday from 7-14:00 is now for granted.
https://docs.xfel.eu/share/page/site/PSC/wiki-page?title=Tunnel_access_schedules |
Status and plans after SASE1 Readiness Meeting, posted by Monica Aresté on 19 Jun 2017, 10:17
|
XTDs:
There are no major issues, commissioning works smoothly
this weekend.
|
WP74 OCD plan update, posted by Jan Grünert on 16 Jun 2017, 18:12
|
The WP74 OCD plan is also published in WP74-Alfresco and sent by email to HR/WoCo/STGL.
Please note that this plan could be subject to
changes depending on the needs of the involved colleagues (e.g. if they want to swap OCD assignments).
The actually performed OCD-times are
reported to HR at the start of each following month.
|
Status and plans after SASE1 Readiness Meeting, posted by Monica Aresté on 16 Jun 2017, 10:18
|
Normal
0
21
false
false
|
Access to tunnels updated, posted by Gerd Wellenreuther on 15 Jun 2017, 12:18
|
XTD9 will be open until Friday this week 13:30. Check https://docs.xfel.eu/share/page/site/PSC/wiki-page?title=Tunnel_access_schedules |
Status and plans after SASE1 Readiness Meeting, posted by Monica Aresté on 14 Jun 2017, 10:57
|
General:
|
Tunnel's schedule updated, posted by Monica Aresté on 12 Jun 2017, 13:21
|
Last information is that tomorrow Fire brigade will come to inspect the tunnels, therefore all tunnels will be open from 7:00 to 15:00.
H. Sinn inform that XTD9 will not be searched until Wednesday morning.
Tunnel's schedule: |
Tunnel's schedule, posted by Monica Aresté on 12 Jun 2017, 11:17
|
Normal
0
21
false
false
false
|
Status and plans after SASE1 Readiness Meeting, posted by Monica Aresté on 12 Jun 2017, 10:55
|
Tunnel's schedule:
Monday 12th June: XTD10 closed, XTD9 open |
Motor in error, posted by Gabriele Giovanetti on 09 Jun 2017, 21:40
|
Called at 21.18 for SASE1_XTD2_IMGSR/MOTOR/Y being in error.
Solved by pressing 'Reset' button in Karabo GUI |
Information AE OCD June 9 -- 12, posted by Nicola Coppola on 09 Jun 2017, 19:09
|
AE/PLC on call service:
Contact Person:
Nicola Coppolla |
Status and plans after SASE1 Readiness Meeting, posted by Monica Aresté on 09 Jun 2017, 12:41
|
Normal
0
21
false
false
false
|
XTD10 and XTD9 tunnel opening and closings, posted by Harald Sinn on 08 Jun 2017, 08:24
|
Dear all,
according to the DESY logbook XTD10 will be opened today again: See DESY logbook entry:
'due to the cryogenic failure we will open XTD10 from 9am for working. |
XTD10 open , posted by Tobias Haas on 08 Jun 2017, 08:24
|
Author: limberg, tischhauser
due to the cryogenic failure we will open XTD10 from 9am for working.
at XTL and XTD2/4 ZZ is
possible for repairs/work. |
Motion loop update, posted by NEREA JARDON on 07 Jun 2017, 14:19
|
Dear all,
Motion loop is up and running again, now with all the PBLMs configured.
Thank you, |
Motion loop update, posted by NEREA JARDON on 07 Jun 2017, 12:00
|
Dear all,
Due to some hardware changes needed in Motion loop, we will last a little bit more in the Motion update. You will loose communication but I will
come back when it is running again. |
Status and plans after SASE1 Readiness Meeting, posted by Tobias Haas on 07 Jun 2017, 11:43
|
General
Technicians from Actemium/JOWO arrived and
found that a lot more connectors than originally estimated need to be replaced
Tests are finished in SPB Optics (40 connectors to be replaced) |
Motion loop update, posted by NEREA JARDON on 06 Jun 2017, 17:39
|
Dear all,
The Motion loop is running again. We have included today the Mc2motor devices that were already before configured (FXE PBLMs and MCP), tomorrow
we will include the rest of the PBLMs. |