Shift summary Feb 11th, posted by Jörg Hallmann on 12 Feb 2023, 01:56
|
intense data taking on various samples
2 main issues:
- data collection using the optimize macro is too fast for the system and calibration and the data transfer from SDD to HDD is slower than collecting |
Status, posted by Andreas Galler on 11 Feb 2023, 13:55
|
Gun Modulator Problems
Gun Trip at 11:23 and since then the Modulator trips after each restart.
Accelerator Shift Crews and On Call personnel working on fixing the issue. |
Shift end, posted by Jayanath Koliyadu on 11 Feb 2023, 07:06
|
X-ray delivery
9.3 keV, 1-85 pulses, 1 mJ, stable delivery
Optical laser delivery
800 nm, 1-226 pulses, stable delivery
ns laser for illumination
Achievements/Observations |
Shift summary, posted by Jörg Hallmann on 11 Feb 2023, 01:09
|
sucessfull data taking for user samples
beam loss for ~15 min and a small issue with scannerX of the FSSS (could be fixed without support) but otherwise smooth operation
contact with ITDM since the data collection speed could be too high for the transfer speed from SDD to HDD - should be kept under investigation.... |
Shift end, posted by Jayanath Koliyadu on 10 Feb 2023, 08:17
|
X-ray delivery
9.3 keV, 1-85 pulses, 1 mJ, stable delivery
Optical laser delivery |
Shift end, posted by Jayanath Koliyadu on 09 Feb 2023, 07:14
|
X-ray delivery
9.3 keV, 1-85 pulses, 1.3 mJ, stable delivery
Optical laser delivery
800 nm, 1-226 pulses, stable delivery except for shift change issues
Achievements/Observations |
Shift summary Feb 8th, posted by Jörg Hallmann on 09 Feb 2023, 01:11
|
stable beam at 9kev (about 1.1 mJ)
checks of the sample environment required for the upcoming user experiment
test data aquisition of SiO2 samples (data analysis still ongoing) |
SA3 status, posted by Andreas Koch on 08 Feb 2023, 11:14
|
Bunch number control - SA3 FEL imager
As announced today in the XO meeting the SA3 FEL imager has a new feature, see screenshot, encircled:
- In case of danger for the YAG screen the bunches SA3 are set to "0" via the BunchPatternServer (SA3 Main scene). |
Issue, posted by Harald Sinn on 05 Feb 2023, 15:18
|
15:15 SCS called and reported an issue with one of the motors of the SCS exit slit. DOC already looked at the problem and could not make the motor
move. XRO (Maurizio) is now informed and looks at the problem
17:10 ZZ access to XTD by Maurzio and Mikako |
morning shift summary, posted by Natalia, Zhong on 05 Feb 2023, 12:32
|
achievements:
- Viking spectrometer set up in 8th order around 1280eV and calibrated
problems: |
Shift summary, posted by karen appel on 05 Feb 2023, 08:40
|
Start up of HED ongoing for the three shifts
Day shift:
work on the new X-ray alignment scheme at 2, 2.5 and 3 mrad: test was positive and we can not work with Tx of M3 fixed at 4 mm for all |
Shift summary, posted by karen appel on 04 Feb 2023, 08:34
|
We took the beam from 7 am, 24 h operation in three shifts.
We set up a new scheme for aligning the beam to the HED branch, which gives one X-ray axis downstream of the tunnel even if we operate at different
angles of M1 and M2 (i.e. 3 to 2 mrad). This relies on a fixed M3 Tx position and was tested for 2.5 mrad and 3 mrad during the shifts. CRL3 in the HED |
Shift summary, posted by Peter Zalden on 02 Feb 2023, 09:25
|
FXE bring-up, summary of shifts 31.1. and 1.2.:
Beam delivery (11.5 GeV)
9.3 keV, 1.5 mJ (31.1.)
7.1 keV, 1.7 mJ (1.2.)
Horizontal beam jitter 200 µm (RMS), a bit more than usual
Tunnel |
Issue, posted by Chan Kim on 02 Feb 2023, 06:37
|
SPB_IRU_DPA/MOTOR issue
X stage looks okay, but Y, AX, and AY values have been changed by 2-3mm. (see attachment 1 and 2)
|
SASE2 Summary of Maintenance Period and Ramp up activities, posted by Maurizio Vannoni on 30 Jan 2023, 19:06
|
SASE2 Summary of Maintenance Period and Ramp up activities
Maintenance
- Many vibration tests were done. |
SASE1 Summary of Maintenance Period and Ramp up activities, posted by Maurizio Vannoni on 30 Jan 2023, 16:31
|
SASE1 Summary of Maintenance Period and Ramp up activities
Maintenance
- MC2 library update was deployed by EEE and most of the motors were tested afterwards |
SASE3 Summary of Maintenance Period and Ramp up activities, posted by Maurizio Vannoni on 30 Jan 2023, 15:21
|
SASE3 Summary of Maintenance Period and Ramp up activities
Maintenance |
ZZ Access on 24th January (19:30h) - Replacement of Motor on SASE2 Undulator - Cell 17 Phase Shifter, posted by Raúl Villanueva-Guerrero on 25 Jan 2023, 08:44
|
Dear all,
last evening Suren Karabekyan and myself did a short notice ZZ access to XTD1. The reason is that machine operators detected the lack of response
on the Cell 17 Phase Shifter. The intervention was successful and around 20:30 we left the tunnel. |
All SASE's - SEPS Interlock Test - Results, Status & Upcoming Schedule, posted by Raúl Villanueva-Guerrero on 25 Jan 2023, 08:40
|
Dear all,
please find here a summary of the status on this critical topic provided yesterday evening (around 19:15) by Zunaira Ansari (extract from her
e-mail). |
Status, posted by Jan Gruenert on 23 Jan 2023, 10:43
|
Status of machine SASE tuning (just before switching off for monday maintenance):
11.5 GeV operation
SASE1
SASE2
SASE3
Photon
energy
7 keV
7 keV
700 eV
Max. obtained average pulse energy
3.25 mJ
1.35 |