Message ID: 9     Entry time: 25 Jan 2023, 08:44
Author: Raśl Villanueva-Guerrero 
Group: PRC 
Subject: ZZ Access on 24th January (19:30h) - Replacement of Motor on SASE2 Undulator - Cell 17 Phase Shifter 

Dear all,

last evening Suren Karabekyan and myself did a short notice ZZ access to XTD1. The reason is that machine operators detected the lack of response on the Cell 17 Phase Shifter. The intervention was successful and around 20:30 we left the tunnel.

Regards,

R.