Message ID: 8     Entry time: 25 Jan 2023, 08:40
Author: Raśl Villanueva-Guerrero 
Group: PRC 
Subject: All SASE's - SEPS Interlock Test - Results, Status & Upcoming Schedule 

Dear all,

please find here a summary of the status on this critical topic provided yesterday evening (around 19:15) by Zunaira Ansari (extract from her e-mail).

 

"Dear colleagues,

Thank you very much for your cooperation. SEPS interlock tests are completed in all SASEs except SASE3. AIBS interlock tests are complete in all hutches.

SASE3 SEPS interlock will be tested on Monday the 30th of January strating from 9a.m.

I kindly request the use of the SQS control hutch for the testing.

All SASE3 hutches will be interlocked on Monday morning.

@Maurizio and Bernard/ Nerea: Could you please be present during the testing? IIt will be much appreciated.

I would very much like to thank Eric, Nerea and especially Bernard for helping with the interlock tests today.

Best regards,

Zunaira

 