  OPERATION-2023 logbook, Contact: F.Wolff-Fabris, A.Galler, L.Samoylova, H.Sinn  Not logged in ELOG logo
Message ID: 16     Entry time: 05 Feb 2023, 08:40
Author: karen appel 
Group: HED 
Subject: Shift summary 

Start up of HED ongoing for the three shifts

Day shift:

  • work on the new X-ray alignment scheme at 2, 2.5 and 3 mrad: test was positive and we can not work with Tx of M3 fixed at 4 mm for all M1 and M2 mirror angles.
  • alignment of CRL2 to the new beam axis in XTD6

Late shift:

  • test of MDL at 2 , 2.5 and 3 mrad: the beam was brought back with the actual stored positions
  • Continuation of commissioning of the new IPM
  • PAM, ILM and power slit alignment to new beam axis
  • ALAS alignment to the new beam position

Night shift:

  • AGIPD tests after ASICS have been replaced and timing scans, flat fielding could not be achieved and has to be done prior to the next user experiment in May using AGIPD
  • Test of epix after repair (new Peltier)

Issues:

  • calibration pipeline of epix does not work as darks cannot be applied and there is no signal on the background corrected signal
  • there has been obviously some miscommunication about the RF window length: HED had requested 150 musec for the weekend and XO had confirmed that on Friday. To do that the timing was shifted earlier by 10 -20 musec on Friday. It sseems that this was no longer the setting for Saturday evening when we needed that for AGIPD test. Not sure where the message got lost.